251224mmo_response_to_pap_letter
Differences
This shows you the differences between two versions of the page.
| Both sides previous revisionPrevious revision | |||
| 251224mmo_response_to_pap_letter [2026/04/30 06:21] – nefcadmin | 251224mmo_response_to_pap_letter [2026/04/30 06:35] (current) – nefcadmin | ||
|---|---|---|---|
| Line 68: | Line 68: | ||
| * 19. Under this ground you allege that the MMO failed to have regard to the impact of the regulated activity on marine waters beyond the water bodies regulated under the 2017 Regulations. This is said to lead to a breach of policy and/or the 2010 Regulations. | * 19. Under this ground you allege that the MMO failed to have regard to the impact of the regulated activity on marine waters beyond the water bodies regulated under the 2017 Regulations. This is said to lead to a breach of policy and/or the 2010 Regulations. | ||
| - | 20. MMO gave detailed consideration to the question as to whether the dredged material is | + | |
| - | suitable | + | * 21. The MMO also concluded, |
| - | accordance | + | * 22. None of these assessments |
| - | Decision | + | * 23. These technical conclusions led the MMO to a conclusion that the proposals were in accordance |
| - | sought and obtained detailed advice from Cefas on the chemical characteristics of the | + | |
| - | material and also consulted Natural England and the Environment Agency. | + | |
| - | 21. The MMO also concluded, | + | |
| - | within the wider marine environment that the proposal was “// | + | |
| - | //other habitats/ | + | |
| - | 22. None of these assessments | + | |
| - | paragraph 43(b) of PAPL 1; the MMO were assessing the consequences of permitting | + | |
| - | the relevant activity against the correct baseline of the marine environment as it currently | + | |
| - | exists with other lawful activities occurring, including the use of the Tees Bay A for the | + | |
| - | disposal of other dredging arisings. | + | |
| - | 23. These technical conclusions led the MMO to a conclusion that the proposals were in | + | |
| - | accordance | + | |
| - | realistically be impugned: | + | |
| - | (1) Policy NE-WQ-1 does no more that make clear that in policy as well as legal terms | + | |
| - | “// | + | |
| - | Regulations]”. | + | |
| - | (2) The 2010 Regulations implement the Marine Strategy Framework Directive (“**the | + | |
| - | **MSF Directive**”). | + | |
| - | exercise its functions so as to secure compliance with the MRF Directive, including | + | |
| - | Article | + | |
| - | GES by 2020. Under both the 2010 Regulations and the MSF Directive this is to | + | |
| - | be achieved through the development of marine strategies under regulation 5, to | + | |
| - | which all public authorities must have regard in the exercise of relevant functions | + | |
| - | (see regulation 9). | + | |
| - | + | ||
| - | 4 See answer to Gateway 3 response at Q10. | + | |
| - | + | ||
| - | + | ||
| - | + | ||
| - | ---- | + | |
| - | + | ||
| - | {{2025.12.24%20PAP%20response%20OUT-8_1.png}} | + | |
| - | + | ||
| - | + | ||
| - | (3) Under the UK’s Marine Strategy, the UK’s waters are divided into sub-regions, | + | |
| - | relevant sub-region being the Greater North S[[2025.12.24%20PAP%20response%20OUT.html# | + | |
| - | One (2019), Part Three (2025) and consultation draft of the most recent update to | + | |
| - | Part One all identify that GES for Contaminants (D8) has not been attained in the | + | |
| - | Greater North Sea. However, the mechanism to achieve GES is via the measures | + | |
| - | set out (most recently) | + | |
| - | maintenance dredging and disposal should be curtailed nor present any basis on | + | |
| - | which it could be said that disposal of dredged material should be at one location | + | |
| - | within a region or sub-region rather than another. | + | |
| - | (4) The MMO has given detailed consideration to the question of whether the dredged | + | |
| - | material is appropriate for disposal to sea. It is not and cannot be suggested that | + | |
| - | the material should be disposed of outside the Greater North Sea sub-region and | + | |
| - | nothing has been presented to suggest that use of a different disposal site within | + | |
| - | the sub-region would enable or facilitate the attainment of GES. | + | |
| - | **Ground 3: Failure to comply with the waste hierarchy ** | + | |
| - | 24. The MMO gave specific | + | |
| - | Regulations and recorded a conclusion of compliance at Q18 of Gateway 3. This was | + | |
| - | based on consideration of paragraph 3.6 of the Interested Party’s Maintenance Dredging | + | |
| - | Protocol | + | |
| - | Party (as a waste operator and harbour authority itself is required to apply the waste | + | |
| - | hierarchy) has previously managed to find preferrable beneficial uses of the material. In | + | |
| - | the context of a long-standing maintenance activity this was sufficient to demonstrate to | + | |
| - | the MMO’s satisfaction that all alternatives to disposal had been and would continue to | + | |
| - | be considered. The MMO’s conclusion cannot realistically be impugned. | + | |
| - | + | ||
| - | + | ||
| - | + | ||
| - | + | ||
| - | + | ||
| - | 5 https: | + | |
| - | + | ||
| - | + | ||
| - | + | ||
| - | ---- | + | |
| - | + | ||
| - | {{2025.12.24%20PAP%20response%20OUT-9_1.png}} | + | |
| - | + | ||
| - | + | ||
| - | **Ground 4: Failure to carry out a lawful appropriate assessment ** | + | |
| - | 25. As PAPL 2 recognises, | + | |
| - | (“**HRA**”) | + | |
| - | assesses | + | |
| - | England, | + | |
| - | with site specific | + | |
| - | significant effects on the Special Protection Area (“**SPA**”), | + | |
| - | other projects. Site specific features included the evidence from the Interested Party that | + | |
| - | material | + | |
| - | “//peak depositions occurring outside of the SPA boundary// | + | |
| - | the MMO did not accept that there was no pathway. Instead, the MMO’s reasoned view | + | |
| - | was that impacts | + | |
| - | reached in the context that: | + | |
| - | (1) The scale of the potential | + | |
| - | evidence, which led the MMO to conclude that there would “//not be an impact to // | + | |
| - | // | + | |
| - | //pressure impact for Common, Sandwich and Little Tern only”. // | + | |
| - | (2) Relevant baseline pressures at the site would not be increased from the current | + | |
| - | position. | + | |
| - | (3) The activity | + | |
| - | combination with others via other licence applications or licence variations. This | + | |
| - | meant there were no additional | + | |
| - | already been subject to a HRA and approved; and | + | |
| - | (4) Natural | + | |
| - | HRA, and had raised no objection. | + | |
| - | 26. The principles cited at paragraph 18 above are also relevant here. There is no proper | + | |
| - | basis on which to ask the court to impugn the MMO’s assessment as an expert regulator, | + | |
| - | nor the supporting advice of Natural England. | + | |
| - | + | ||
| - | + | ||
| - | + | ||
| - | + | ||
| - | ---- | + | |
| - | + | ||
| - | {{2025.12.24%20PAP%20response%20OUT-10_1.png}} | + | |
| - | + | ||
| - | + | ||
| - | **Ground 5: EIA ** | + | |
| - | 27. PAPL 2 raises | + | |
| - | whether | + | |
| - | Regulations. | + | |
| - | 28. A similar ground was raised in a judicial revi[[2025.12.24%20PAP%20response%20OUT.html# | + | |
| - | (Brighton) Ltd in May 2025, which was consented to on other grounds. Following the | + | |
| - | Brighton Marina claim, the MMO sought advice from Leading Counsel (in which privilege | + | |
| - | is not waived). | + | |
| - | 29. The MMO’s position is that the question of whether material is sludge is a question of | + | |
| - | fact. In this case, maintenance dredging arisings are not sludge within the meaning of | + | |
| - | the EIA Directive as it is sediment and thus comes from natural processes of erosion | + | |
| - | and water movement | + | |
| - | process. The regulated activity is therefore not in the course of a sludge deposition site. | + | |
| - | 30. Further, even if the deposit of maintenance dredging arisings from the Harbour at the | + | |
| - | Disposal Site were an activity within Schedule A2 of the 2007 Regulations, | + | |
| - | provided no evidence that it might give rise to likely significant effects. As set out above, | + | |
| - | the MMO has concluded on the basis of the available scientific information and advice | + | |
| - | (including that of Cefas, Natural England and the Environment Agency) that the licensed | + | |
| - | activities do not give rise to any adverse effects on habitats and species, including those | + | |
| - | protected by the Habitats Regulations and that they do not result in deterioration of water | + | |
| - | quality within any Water Framework Directive waterbody. | + | |
| - | 31. As such the MMO will say that it is therefore highly likely that the outcome on EIA would | + | |
| - | have been substantially the same even if it had concluded that the material in question | + | |
| - | is sludge. | + | |
| - | + | ||
| - | + | ||
| - | + | ||
| - | + | ||
| - | 6 AC-2025-LON-002797 | + | |
| - | + | ||
| - | + | ||
| - | + | ||
| - | ---- | + | |
| - | + | ||
| - | {{2025.12.24%20PAP%20response%20OUT-11_1.png}} | + | |
| + | ==== Ground 3: Failure to comply with the waste hierarchy ==== | ||
| + | * 24. The MMO gave specific | ||
| - | **Further information | + | ==== Ground 4: Failure to carry out a lawful appropriate assessment ==== |
| - | 32. We enclose the following disclosure in response to your request and pursuant to our | + | * 25. As PAPL 2 recognises, |
| - | duty of candour: | + | * (1) The scale of the potential |
| - | (1) A map setting | + | * (2) Relevant baseline pressures at the site would not be increased from the current position. |
| - | (request (i)), | + | * (3) The activity |
| - | (2) The “gateway” internal decision making records (request (iv)); and | + | * (4) Natural |
| - | (3) All advice provided to the MMO by Cefas in relation to the development of sampling | + | * 26. The principles cited at paragraph 18 above are also relevant here. There is no proper basis on which to ask the court to impugn the MMO’s assessment as an expert regulator, nor the supporting advice of Natural England. |
| - | plans for both the Previous Licence and New Licence. This covers (v)(a)-(b), (vi) | + | ==== Ground 5: EIA ==== |
| - | and (viii). | + | * 27. PAPL 2 raises |
| - | provided by the Interested Party, as such the MMO holds nothing under (v)(c). | + | * 28. A similar ground was raised in a judicial review< |
| - | **Conclusion / next steps ** | + | * 29. The MMO’s position is that the question of whether material is sludge is a question of fact. In this case, maintenance dredging arisings are not sludge within the meaning of the EIA Directive as it is sediment and thus comes from natural processes of erosion and water movement |
| - | 33. For all of these reasons, the proposed claim is unarguable and will be defended in full. | + | * 30. |
| - | Further, as set out above, the proposed Claimant is invited to submit any evidence which | + | * 31. As such the MMO will say that it is therefore highly likely that the outcome on EIA would have been substantially the same even if it had concluded that the material in question is sludge. |
| - | he considers should lead the MMO to taking a different decision in relation to the ongoing | + | ==== **Further information requested ==== |
| - | licensing of the regulated activity. If the claim is brought, it will be resisted in full. | + | * 32. We enclose the following disclosure in response to your request and pursuant to our duty of candour: |
| + | | ||
| + | | ||
| + | | ||
| + | ==== Conclusion / next steps ==== | ||
| + | | ||
| Yours faithfully | Yours faithfully | ||
| - | **K Hayes | ||
| - | ** | ||
| - | Kerry Hayes | ||
| - | Drafting & Advisory Lawyer | ||
| - | +44 (0) 2077142806 | ||
| legalteamhq@marinemanagement.org.uk | legalteamhq@marinemanagement.org.uk | ||
| Line 251: | Line 113: | ||
| 3 Inserted in the 2024 update. | 3 Inserted in the 2024 update. | ||
| + | 4 See answer to Gateway 3 response at Q10. | ||
| + | |||
| + | 5 https: | ||
| + | |||
| + | 6 AC-2025-LON-002797 | ||
251224mmo_response_to_pap_letter.1777530103.txt.gz · Last modified: by nefcadmin
