User Tools

Site Tools


cefas_thoughts_about_the_river_tees_over_time

Differences

This shows you the differences between two versions of the page.

Link to this comparison view

Both sides previous revisionPrevious revision
Next revision
Previous revision
cefas_thoughts_about_the_river_tees_over_time [2025/12/22 00:06] – [Cefas 20th December 2021] nefcadmincefas_thoughts_about_the_river_tees_over_time [2025/12/28 23:19] (current) – [Cefas 5th October 2023] nefcadmin
Line 42: Line 42:
 Observed metal and organotin levels considered acceptable for disposal at sea.  Bamletts Wharf and Britannia Enterprise Zone, showed lead levels in excess of Cefas AL2 comparable to other excluded areas such as Teesport Commerce Wharf (TPC) Dry Dock, all higher than 2010 measurements suggesting some Observed metal and organotin levels considered acceptable for disposal at sea.  Bamletts Wharf and Britannia Enterprise Zone, showed lead levels in excess of Cefas AL2 comparable to other excluded areas such as Teesport Commerce Wharf (TPC) Dry Dock, all higher than 2010 measurements suggesting some
 sporadic source of contaminant input into these sites.  Recommended exclusion from new licence and stopping dredging these areas immediately. sporadic source of contaminant input into these sites.  Recommended exclusion from new licence and stopping dredging these areas immediately.
 +
 +{{ ::251215-1506lmw_pahs.png?nolink&300 |}}
  
 "PAH’s demonstrate some areas of elevation, particularly with respect to those PAH’s associated with redundancy from the petro chemical industry but generally levels observed were consistent with those anticipated in sediments from the Tees estuary and within those ranges previously disposed of to the Tees Bay site. I recommend continuing the monitoring of sediment quality through regular future sampling campaigns." "PAH’s demonstrate some areas of elevation, particularly with respect to those PAH’s associated with redundancy from the petro chemical industry but generally levels observed were consistent with those anticipated in sediments from the Tees estuary and within those ranges previously disposed of to the Tees Bay site. I recommend continuing the monitoring of sediment quality through regular future sampling campaigns."
 +
 +{{ :251215-1506hmw_pahs.png?nolink&300 |}}
  
 "It is my view that these works will fall outside the scope of a relevant project as defined by the "It is my view that these works will fall outside the scope of a relevant project as defined by the
Line 104: Line 108:
 There is a comment about sampling number meeting OSPAR guidelines "Using the OSPAR guidelines, this equates to approximately 30-35 samples required, as the guidelines stipulate that 16 – 30 samples should be taken for dredges between 500,000 m³ and 2,000,000 m³ and an additional 10 samples for each 1,000,000 m³ beyond this amount. As such, the sampling effort, 37 samples including one exclusion, is acceptable."  As elsewhere I have commented on the MMO/Cefas approach to [[https://www.northeastfc.uk/doku.php?id=ospar_sampling_guidelines|OSPAR Sampling Guidelines]] is incorrect as it ignores the area being dredged and only considers the volume of material.  This is particularly inappropriate here, as in the response of 16th October 2019, Cefas had stated how variable the results were for PAHs, showing how inhomogeneous the Tees is and as such as stated by OSPAR "...assuming a reasonably uniform sediment distribution in the area...", so rather than considering the whole dredged area first the area should have been compartmentalised into areas where the sediment was similar. There is a comment about sampling number meeting OSPAR guidelines "Using the OSPAR guidelines, this equates to approximately 30-35 samples required, as the guidelines stipulate that 16 – 30 samples should be taken for dredges between 500,000 m³ and 2,000,000 m³ and an additional 10 samples for each 1,000,000 m³ beyond this amount. As such, the sampling effort, 37 samples including one exclusion, is acceptable."  As elsewhere I have commented on the MMO/Cefas approach to [[https://www.northeastfc.uk/doku.php?id=ospar_sampling_guidelines|OSPAR Sampling Guidelines]] is incorrect as it ignores the area being dredged and only considers the volume of material.  This is particularly inappropriate here, as in the response of 16th October 2019, Cefas had stated how variable the results were for PAHs, showing how inhomogeneous the Tees is and as such as stated by OSPAR "...assuming a reasonably uniform sediment distribution in the area...", so rather than considering the whole dredged area first the area should have been compartmentalised into areas where the sediment was similar.
  
-Dredging was allowed to continue.+{{ :251215-18and19lmw_pahs.png?nolink&200 |}}
  
 +Dredging was allowed to continue.
  
 +{{ :251215-18and19hmw_pahs.png?nolink&200 |}}
 ==== Cefas 29th March 2021 ==== ==== Cefas 29th March 2021 ====
  
Line 127: Line 133:
  
 8. Further, the sample plan recommended only 8 samples, but the licence holder has presented data for 20. As these samples appear to be representative of the dredge areas, I will consider the results alongside the 8 recommended samples," 8. Further, the sample plan recommended only 8 samples, but the licence holder has presented data for 20. As these samples appear to be representative of the dredge areas, I will consider the results alongside the 8 recommended samples,"
 +
 +{{ :251215-2110lmw-pahs.png?nolink&200 |}}
  
 PAHs once again show the major concern with most exceeding LMW PAHs ERM and many being close to the HMW PAHs ERM, such results should preclude disposal at sea. PAHs once again show the major concern with most exceeding LMW PAHs ERM and many being close to the HMW PAHs ERM, such results should preclude disposal at sea.
 +
 +{{ :251215-2110hmw_pahs.png?nolink&200 |}}
  
 "14. Viewed in isolation, these results would preclude material from continued disposal at sea. However, it is essential to consider the local and regional context. The Tees river, as with other North-east English rivers, has a documented history of specific industrial activity, which has led to a noticeable presence of both man-made and naturally occurring contaminants. Further, the general PAH footprint of the Tees typically skews more towards LMW PAHs than HMW PAHs, which is reflected in the results presented. Nonetheless, whilst considering local context is important, it is important consider this history holistically, rather than entirely discounting the results presented." "14. Viewed in isolation, these results would preclude material from continued disposal at sea. However, it is essential to consider the local and regional context. The Tees river, as with other North-east English rivers, has a documented history of specific industrial activity, which has led to a noticeable presence of both man-made and naturally occurring contaminants. Further, the general PAH footprint of the Tees typically skews more towards LMW PAHs than HMW PAHs, which is reflected in the results presented. Nonetheless, whilst considering local context is important, it is important consider this history holistically, rather than entirely discounting the results presented."
Line 135: Line 145:
  
 This response was prepared just after the initial crustacean die-off had occurred in the River Tees and the local coast. This response was prepared just after the initial crustacean die-off had occurred in the River Tees and the local coast.
 +
 +==== Cefas 26th July 2023 ====
 +
 +==== Cefas 5th October 2023 ====
 +
 +
 +
 +
 +==== MMO 30th July 2024 ====
 +
 +[[https://www.northeastfc.uk/RiverTees/Planning/MLA_2025_00263/Additional%20Documents/SAM202400054.pdf| -  Sample plan advice for mid licence sampling for Marine Licence L/2015/00427 at
 +Tees and Hartlepool, Teesside]]
 +
 +The MMO advice is introduced by a misquoting of the [[OSPAR Sampling Guidelines]]
 +
 +"2.1. In accordance with the recommendations of the OSPAR Guidelines for the Management of Dredged Material, samples should be taken to provide a good representation of the volume of material to be dredged. The distribution and depth of sampling should reflect the size and depth of the area to be dredged, the amount to be dredged and the expected variability in the horizontal and vertical distribution of contaminants. The MMO also uses the OSPAR guidelines to inform our advice on sampling requirements for other activities which are likely to lead to the mobilisation of sediments. Based on the information submitted (as described above), the following sampling and analysis is required."
 +
 +The advice then advised that "In consideration of the volume details of the proposed dredge, the MMO advises that 31 samples should be taken from within the footprint of the proposed dredge area." and then said "Whilst this could be considered slightly under the guidelines set by OSPAR, which recommends 30 sites for dredges up to 2,000,000 m3 with an additional ten sites per million m3, the MMO is content that these provide adequate spatial coverage across the dredge locations as each Chart Sector contains one or more sampling points, with additional points in non-sectored maintained areas."  The total dredge area of L/2015/00427/7 was 1,660 hectares so this the MMO said that 1 sample was sufficient to sample an area of 55 hectares.  This highlights that the OSPAR volume table is meant to be a check for a deep capital dredge happening in a small spatial area and does not ensure proper spatial coverage for which there is explicit guidance in the [[OSPAR Sampling Guidelines]].
 +
 +The 31 sites were shown in figure 1:
 +
 +{{ :240730mla201500088-sam202400054-figure1.png?nolink&400 |}}
 +
 +Measurements were required from all 31 sites: Particle Size Analysis (PSA), Trace metals (including arsenic), Organotins (tributyltin and dibutyltin), Polycyclic Aromatic Hydrocarbons (PAHs), Polybrominated diphenyl ethers (PBDEs), Total Organic Carbon (TOC).  10 sites also needed to measured for Polychlorinated Biphenyls (PCBs) – must include a sample collected from Chart sectors 1 & 2 (Figure 1), Organochlorine pesticides (OCs) – must include a sample collected from Chart sector 1 & 8, Navigator North Tees and Hartlepool Berths (Figure 1). 
 +
 +==== MMO Covering Letter for Cefas 25th January 2025 ====
 +
 +[[https://www.northeastfc.uk/RiverTees/Planning/MLA_2015_00088/Returns/Post_Consent_Discharge%20MLA201500088%20CP_.pdf|L/2015/00427/7 Mid Licence Sediment Sampling Review – Condition 5.2.3]]
 +
 +The MMO considered that the sample results submitted discharged the conditions on the licence.  However, the levels of BDE209, 99 and 100 were noted as being higher than lower assessment criteria (LAC) but lower than the high assessment criteria (HAC) and as the applicant had not measured total organic carbon (TOC) as requested it was not possible to normalise the values.  So the MMO requested annual measurements of BDEs in future.
 +
 +Cefas comments on particle size were based on the mass particle size distribution, so stated that all but 2 of the samples were similar.  A comparison based on area particle size distribution would have seen less difference between all the samples.
 +
 +All trace metals (including arsenic) showed levels greater than Cefas Action Level 1 (AL1) (beige markers on maps) in multiple samples, but no samples were greater than AL2.
 +
 +{{ :251215-2410separatemetals.png?nolink&600 |}}
 +
 +There is only an AL1 for individual polycyclic aromatic hydrocarbons (PAHs), so the maps for the individual PAHs are colour coded as green when below AL1, beige when between AL1 and 10*AL1 and red when greater than 10xAL1.
 +
 +{{ :251215-2410separatepahs.png?nolink&600 |}}
 +
 +As there is no AL2 for PAHs Cefas uses the Gorham-Test protocol to examine sums of low molecular weight (LMW) and sums of high molecular weight (HMW) PAHs.  The sum of each are assessed against effect range low (ERL) below this the sediment is low risk and effects-range median (ERM) above which the sediment is considered of high risk.
 +
 +"Out of the 31 samples analysed for PAHs 29 were greater than the LMW ERM ranging from around the ERL threshold (3,160 µg/kg) to 4.4x the ERM threshold (14,047 µg/kg). The remaining two samples were 1 (Figure 1 Exolum Riverside) and 27 (Figure 1 Chart 12); sample 1 contained LMW PAH levels greater than ERL but close to the ERM threshold whilst sample 27 contained levels of LMW PAHs less than ERL. Only one sample, sample 6 (Figure 1 Chart 3), was close to, but below, the ERM threshold for HMW PAHs. All remaining levels of HMW PAHs were below the ERM except for three samples which were below the ERL. The three samples below ERL were sample 24 (Figure 1 Chart 9), sample 27 (Figure 1 Chart 12) and sample 28 (Figure 1 Hartlepool Channel). Of note is that sample 27 is the only sample to contain levels of both LMW and HMW PAHs below their respective ERLs."
 +
 +{{ :251215-2410lmw-pahs.png?nolink&200 |}}
 +
 +{{ :251215-2410hmw-pahs.png?nolink&200 |}}
 +
 +"**The levels of LMW PAHs alone would normally preclude the material from continued disposal to sea due to levels that would pose a risk to the marine environment**, however, the river Tees is historically an area that exhibits PAH levels higher than other UK rivers due to industrial sources and history of the river (Nicolaus et al., 2015; Kirby et al., 1999), especially acute LMW PAHs. This has been evident throughout the current licence whereby both LMW and HMW levels detected in sediment sampling and analysis since 2015 have shown elevated levels of LMW and HMW PAHs that are greater than their respective ERLs and ERMs (documents cited in paragraphs nine and ten). It is prudent to compare the current results to historical levels detected within the duration of the licence so that local and regional context of these results are considered; these are visualised in Figures 4 and 5 below."
 +
 +{{ :250130mla201500088-mmoresponsefigure4.png?nolink&400 |}}
 +
 +{{ :250130mla201500088-mmoresponsefigure5.png?nolink&400 |}}
 +
 +Cefas basically say these high levels are not an issue, despite most of the samples having LMW PAHs above ERM and as Cefas said any sample above ERM "can be considered higher risk, with more likelihood of harm occurring."  As such this material should not have been considered safe for disposal at sea, but ....
 +
 +"It is observed that levels of LMW PAHs have maintained a similar level since 2023; the minimum value is less than 2023, the median and mean are of a similar value to 2023 but the maximum has increased since 2023. Viewing the levels of LMW PAHs since the start of the licence in 2015 indicates that they have continued to drop over the years with the Tees and Hartlepool dredge area. Interpretation of the HMW PAH levels is more clear cut with all factors (min, median, mean and max) all decreasing in value since 2015, and in broader terms all seeing a decrease every year since 2019."
 +
 +"Considering these results holistically; in both the local context of the river Tees and in comparison, to previous mid-licence data, the PAH results alone do not preclude material from continued disposal to sea, in this case to Tees Bay A (TY160) disposal site."
 +
 +Neither Cefas figure 4 or 5 show the ERL or ERM levels, but when the ERM level is shown on figure 4, it is obvious that these samples present a significant risk of harm to the marine environment:
 +
 +{{ :250130mla201500088-mmoresponsefigure4-erm.jpg?nolink&400 |}}
 +
 +This chart without the ERM level was reproduced in the Tees MDP Baseline Document to show how the Tees was getting better, which may be the case, but continued dredging and dumping will still be doing damage and as such should be curtailed.
 +
 +Surprisingly only low concentrations of PCBs are seen in the samples and only a few organochlorine samples were found to be above German AL1, as the UK has no AL2.
 +
 +Polybrominated diphenyl ethers were a different story with BDE 209, 99, 100 and 85 show levels that are of concern.  Once again averages were used to appear to minimise the issue, however as stated "It should be noted that the sampling numbers for each year vary for PBDEs and therefore differences could be due to sampling variation e.g. 2023 had ten samples, 2021 had nine whilst 2024 and 2019 had over 30 samples each which will affect averages and thus results are not directly comparable."  There are far too few samples taken to be able to make a sensible statistical analysis not only of BDEs but all the chemicals as the spatial area of dredging is so large.
 +
 +Once again dredging is allowed to continue with disposal of this material to sea: "Given the above, levels of PBDEs pose a high risk to the marine environment at some sites. Overall, my opinion is that **the levels of BDE209 and BDE99 observed in the 2024 data pose a potentially unacceptable risk to the marine environment.** However, the levels for all other BDE congeners and other contaminants analysed do not preclude the material from disposal to sea. Given that **the levels of BDE209 and BDE99 appear to be lower or generally consistent with the levels observed in previous years (excluding the BDE99 maximum)** and given that the **elevated presence of PBDEs in the river Tees that can be traced to historic industrial inputs** the **material whilst of concern may be allowed for disposal, in this case to Tees Bay A (TY160) disposal site.** However, to evidence the impact of the disposal activity with contaminants at these levels it would be prudent to undertake a site-specific monitoring survey to look at impacts in the sediment flora and fauna around the area of the disposal site. I recommend that Tees Bay A (TY160) disposal site and the wider area, is flagged for future monitoring by the MMO."
 +
 +
 +==== MMO Quoting Cefas 1st Arpil 2025 ====
 +
 +[[https://www.northeastfc.uk/RiverTees/Planning/MLA_2025_00263/Additional%20Documents/MLA2015000886_R11.1%20Decision%20Letter.pdf|L/2015/00427/7 Mid Licence Sediment Sampling Review Resubmission – Condition
 +5.2.3]]
cefas_thoughts_about_the_river_tees_over_time.1766361987.txt.gz · Last modified: by nefcadmin