===== MLA/2020/00506 - updated 15th February 2024 ===== {TOC} Initial Application - Submitted 06-Nov-2020 Case ref: MLA/2020/00506/2 Licence ref: L/2021/00333/2 ==== Project title: South Bank Quay - Phase 1 ==== ==== Project background ==== South Tees Development Corporation (STDC) is proposing to construct a new quay at South Bank in the Tees estuary (referred to hereafter as the proposed scheme). The proposed scheme is required to support STDC’s landside proposals for general industry and storage or distribution uses within part of the South Industrial Zone (which has been subject to a separate planning application - reference R/2020/0357/OOM). It is envisaged that the new quay would be utilised predominantly by the renewable energy industry, as well as supporting more general industrial and storage/distribution activities. In summary, the proposed scheme comprises demolition, capital dredging, offshore disposal of dredged material, placement of rock in the berth pocket and construction and operation of a new quay (to be set back into the riverbank). The proposed scheme would require works in both the marine and terrestrial environments and requires Environmental Impact Assessment (EIA) in support of a marine licence application to the Marine Management Organisation (MMO) and a planning application to Redcar and Cleveland Borough Council (RCBC). As the proposed quay is to be constructed in the riverbank (i.e. on land), construction of the new quay has not been included in this marine licence application. The development of the proposed scheme is to be undertaken in phases. This marine licence application covers the works required for Phase 1 of the proposed scheme only. A separate marine licence application has been submitted for Phase 2 of the proposed scheme. ==== Programme of works ==== STDC is intending to commence construction of the facility during 2021 to enable operation of the facility by 2023 (an approximately three-year construction phase). Working hours are proposed to be 24 hours a day during the construction and operational phase. For the purposes of the EIA it has been assumed that construction works could be undertaken at any time of the year (i.e. no seasonal restrictions on works are proposed). Further detail regarding the proposed programme of works is outlined in Section 3.9 of the EIA Report. {html} <iframe width="100%" height="600px" frameborder="0" allowfullscreen src="//umap.openstreetmap.fr/en/map/south-bank-quay-marine-works_858022?scaleControl=false&miniMap=false&scrollWheelZoom=false&zoomControl=true&allowEdit=false&moreControl=true&searchControl=null&tilelayersControl=null&embedControl=null&datalayersControl=true&onLoadPanel=undefined&captionBar=false"></iframe><p><a href="//umap.openstreetmap.fr/en/map/south-bank-quay-marine-works_858022">See full screen</a></p> {/html} ===== Other information ===== ==== Applicant details ==== Mr John McNicholas / 01642 xxx xxx SOUTH TEES DEVELOPMENT CORPORATION / Cavendish House Teesdale Business Park STOCKTON-ON-TEES / TS17 6QY Date application submitted: 06-NOV-2020 Date application validated: 10-OCT-2022 Date initial decision made: 17-DEC-2021 Date decision made for latest variation: 28-FEB-2023 Status: Variation Requested - Completed - (Discharging Conditions) ===== Application and Documents ===== [[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-APPLICATION-FORM.pdf|Application Form]] ==== Response Documents - Licence L/2021/00333/1 ==== |h File|h Size|h Comment|h Date| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-Standard_Marking_Schedule-40.pdf|Standard_Marking_Schedule.pdf]]|//38 KB''|Licence Schedule 7|''27-Sep-2021//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-Condition%205.2.11%20disposal%20exclusion%20zone%20coordnates-41.pdf|Condition 5.2.11 disposal exclusion zone coordnates.docx]]|//12 KB''|Licence Schedule 8|''07-Oct-2021//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-Decision%20Letter%20(Marine)-43.pdf|Decision Letter (Marine).pdf]]|//1 MB''||''17-Dec-2021//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-Marine%20Coordinate%20Schedules-44.pdf|Marine Coordinate Schedules.pdf]]|//14 KB''||''17-Dec-2021//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-Licence%20Document%20(Marine)-45.pdf|Licence Document (Marine).pdf]]|//129 KB''||''17-Dec-2021//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-Returns-46.pdf|Returns.pdf]]|//18 KB''||''17-Dec-2021//| ==== Additional Documents ==== |h File|h Size|h Date| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-MMO%20Results_Template%20MAR00356_1%20V2-1.xlsm|MMO Results_Template MAR00356_1 V2.xlsm]]|//650 KB''|//28-Oct-2020| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-MMO%20Results_Template%20MAR00356_2%20V2-2.xlsm|MMO Results_Template MAR00356_2 V2.xlsm]]|//636 KB''|//28-Oct-2020| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-PC1084-RHD-ZZ-XX-RP-Z-1100_EIA%20Report_Appendices_Part1-3.pdf|PC1084-RHD-ZZ-XX-RP-Z-1100_EIA Report_Appendices_Part1.pdf]]|//47 MB''|//30-Oct-2020| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-PC1084-RHD-ZZ-XX-RP-Z-1100_EIA%20Report_Appendices_Part2-4.pdf|PC1084-RHD-ZZ-XX-RP-Z-1100_EIA Report_Appendices_Part2.pdf]]|//35 MB''|//30-Oct-2020| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-EA%20Response%20to%20consultation%20resolution-42.msg|EA Response to consultation resolution.msg]]|//526 KB''|''10-Dec-2021//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-PC1084-RHD-ZZ-XX-RP-Z-1108_NTS-5.pdf|PC1084-RHD-ZZ-XX-RP-Z-1108_NTS.pdf]]|//3 MB''|//30-Oct-2020| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-MMO%20Results_Template%20MAR00356_1%20V2-6.xlsm|MMO Results_Template MAR00356_1 V2.xlsm]]|//650 KB''|//05-Nov-2020| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-MMO%20Results_Template%20MAR00356_2%20V2-7.xlsm|MMO Results_Template MAR00356_2 V2.xlsm]]|//636 KB''|//05-Nov-2020| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-PC1084_RHD-ZZ-XX-RP-Z-1100_EIA%20Report_main%20body-8.pdf|PC1084_RHD-ZZ-XX-RP-Z-1100_EIA Report_main body.pdf]]|//22 MB''|//05-Nov-2020| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-MLA202000506%20Marine%20Plan%20Assessment-9.xls|MLA202000506 Marine Plan Assessment.xls]]|//164 KB''|//20-Nov-2020| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-PC1084_RHD-ZZ-XX-RP-Z-1100_EIA%20Report_main%20body-10.pdf|PC1084_RHD-ZZ-XX-RP-Z-1100_EIA Report_main body.pdf]]|//25 MB''|//25-Nov-2020| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-MLA202000506%20-%20South%20Bank%20Quay%20-%20Phase%20%201%20EIA%20Intent%20to%20Deferral%20Letter-11.pdf|MLA202000506 - South Bank Quay - Phase 1 EIA Intent to Deferral Letter.docx]]|//199 KB''|//30-Nov-2020| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-NE%20formal%20response%20to%20SBW%20MLA,%2029.01.21%20(1)-12.pdf|NE formal response to SBW MLA, 29.01.21 (1).pdf]]|//227 KB''|''29-Jan-2021//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-22-01-2021%20Gazette%20and%20Northern%20Echo-13.pdf|//22-01-2021'' Gazette and Northern Echo.pdf]]|''969 KB''|''29-Jan-2021//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-29-01-2021%20Gazette%20and%20Northern%20Echo-14.pdf|//29-01-2021'' Gazette and Northern Echo.pdf]]|''1 MB''|''29-Jan-2021//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-Cefas%20RFI%20South%20Bank%20Phase%201%20&%202-15.pdf|Cefas RFI South Bank Phase 1 & 2.docx]]|//16 KB''|''23-Feb-2021//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-PC1084-RHD-ZZ-XX-RP-Z-1115_South%20Bank%20Quay%20supplementary%20report-16.pdf|PC1084-RHD-ZZ-XX-RP-Z-1115_South Bank Quay supplementary report.pdf]] - [[this>Teesworks/Planning/MLA_2020_00506/Tabula-MLA_2020_00506-PC1084-RHD-ZZ-XX-RP-Z-1115_South Bank Quay supplementary report-16-EN.ods|Tables from PC1084-RHD-ZZ-XX-RP-Z-1115_South Bank Quay supplementary report.pdf]]|//10 MB''|''23-Feb-2021//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-MMO_Results_Template%20-%20MAR00829%20Interim-17.xlsm|MMO_Results_Template - MAR00829 Interim.xlsm]]|//648 KB''|''26-Feb-2021//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-MMO_Results_Template%20-%20MAR00856%20Interim%202-18.xlsm|MMO_Results_Template - MAR00856 Interim 2.xlsm]]|//591 KB''|''26-Feb-2021//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-MMO_Results_Template%20-%20MAR00874%20Interim-19.xlsm|MMO_Results_Template - MAR00874 Interim.xlsm]]|//629 KB''|''26-Feb-2021//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-MMO_Results_Template%20-%20MAR00825%20Interim%202-20.xlsm|MMO_Results_Template - MAR00825 Interim 2.xlsm]]|//615 KB''|''26-Feb-2021//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-MMO_Results_Template%20-%20MAR00825%20Interim%202-21.xlsm|MMO_Results_Template - MAR00825 Interim 2.xlsm]]|//615 KB''|''08-Mar-2021//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-PC1084-RHD-SB-EN-CO-EV-1116%20Response%20to%20Cefas%20comments-25.pdf|PC1084-RHD-SB-EN-CO-EV-1116 Response to Cefas comments.pdf]]|//1 MB''|''16-Mar-2021//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-MMO_Results_Template%20-%20MAR00874%20Interim-22.xlsm|MMO_Results_Template - MAR00874 Interim.xlsm]]|//629 KB''|''08-Mar-2021//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-MMO_Results_Template%20-%20MAR00856%20Interim%202-23.xlsm|MMO_Results_Template - MAR00856 Interim 2.xlsm]]|//591 KB''|''08-Mar-2021//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-MMO_Results_Template%20-%20MAR00829%20Interim%20(1)-24.xlsm|MMO_Results_Template - MAR00829 Interim (1).xlsm]]|//650 KB''|''08-Mar-2021//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-Appendix%202%20Sedichem%20tool_South%20Bank-26.xlsx|Appendix 2 Sedichem tool_South Bank.xlsx]]|//1 MB''|''06-May-2021//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-MMO_Results_Template%20-%20MAR00825_with%20coords-27.xlsm|MMO_Results_Template - MAR00825_with coords.xlsm]]|//620 KB''|''06-May-2021//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-MMO_Results_Template%20-%20MAR00829_with%20coords-28.xlsm|MMO_Results_Template - MAR00829_with coords.xlsm]]|//657 KB''|''06-May-2021//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-MMO_Results_Template%20-%20MAR00856_with%20coords-29.xlsm|MMO_Results_Template - MAR00856_with coords.xlsm]]|//595 KB''|''06-May-2021//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-MMO_Results_Template%20-%20MAR00874_with%20coords-30.xlsm|MMO_Results_Template - MAR00874_with coords.xlsm]]|//633 KB''|''06-May-2021//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-MMO_Results_Template%20-%20MAR00856_with%20coords-37.xlsm|MMO_Results_Template - MAR00856_with coords.xlsm]]|//595 KB''|''06-May-2021//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-MMO_Results_Template%20-%20MAR00874_with%20coords-38.xlsm|MMO_Results_Template - MAR00874_with coords.xlsm]]|//633 KB''|''06-May-2021//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-PC1084-RHD-ZZ-XX-RP-Z-1115_South%20Bank%20Quay%20supplementary%20report-31.pdf|PC1084-RHD-ZZ-XX-RP-Z-1115_South Bank Quay supplementary report.pdf]]|//10 MB''|''06-May-2021//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-Appendix%202%20Sedichem%20tool_South%20Bank-26.xlsx|Appendix 2 Sedichem tool_South Bank.xlsx]]|//1 MB''|''06-May-2021//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-Appendix%205_South%20Bank%20Non-breeding%20Bird%20Surveys%202020-2021-33.xlsx|Appendix 5_South Bank Non-breeding Bird Surveys 2020-2021.xlsx]]|//319 KB''|''06-May-2021//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-PC1084-RHD-SB-EN-CO-EV-1116%20Response%20to%20Cefas%20comments-34.pdf|PC1084-RHD-SB-EN-CO-EV-1116 Response to Cefas comments.pdf]]|//1 MB''|''06-May-2021//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-MMO_Results_Template%20-%20MAR00825_with%20coords-35.xlsm|MMO_Results_Template - MAR00825_with coords.xlsm]]|//620 KB''|''06-May-2021//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-MMO_Results_Template%20-%20MAR00829_with%20coords-36.xlsm|MMO_Results_Template - MAR00829_with coords.xlsm]]|//657 KB''|''06-May-2021//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-Sample%20plan%20response_MLA_2021_00506%20&%20507_Updated%20-39.pdf|Sample plan response_MLA_2021_00506 & 507_Updated .pdf]]|//201 KB''|''13-Aug-2021//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-EA Response to consultation resolution.msg|EA Response to consultation resolution.msg]]|//526 KB''|''10-Dec-2021//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-MLA202000506 and MLA202000507 Final HRA.pdf|MLA202000506 and MLA202000507 Final HRA.pdf]]|//549 KB''|''16-Dec-2021//| ===== MLA/2020/00506/1 ===== Variation 1 - Submitted 05-Apr-2022 Accepted ==== Response Documents - Licence L/2021/00333/2 ==== |h File|h Size|h Date| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-Marine%20Coordinate%20Schedules-55.pdf|Marine Coordinate Schedules.pdf]]|//15 KB''|''26-Aug-2022//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-Returns-56.pdf|Returns.pdf]]|//23 KB''|''26-Aug-2022//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-Decision%20Letter%20(Marine)-57.pdf|Decision Letter (Marine).pdf]]|//1 MB''|''26-Aug-2022//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-Licence%20Document%20(Marine)-58.pdf|Licence Document (Marine).pdf]]|//133 KB''|''26-Aug-2022//| ==== Additional Documents ==== |h File|h Size|h Date| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-20.3987%20-%20POL%20-%20MMO%20License%20-%20Channel%20&%20Berth%20Pocket%20-%20Version%202-47.csv|//20.3987'' - POL - MMO License - Channel & Berth Pocket - Version 2.csv]]|''3 KB''|''05-Apr-2022//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-20.3987%20-%20POL%20-%20MMO%20License%20-%20Turning%20Circle%20-%20Version%202-48.csv|//20.3987'' - POL - MMO License - Turning Circle - Version 2.csv]]|''1 KB''|''05-Apr-2022//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-PC1084-RHD-ZZ-XX-RP-Z-0001%20Technical%20Note%20-%20Hydrodynamic%20and%20Sediment%20Plume%20Modelling_Final-49.pdf|PC1084-RHD-ZZ-XX-RP-Z-0001 Technical Note - Hydrodynamic and Sediment Plume Modelling_Final.pdf]]|//1 MB''|''05-Apr-2022//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-22UK1862_SouthBankTees_NRA_Addendum_Issue_01-50.pdf|//22''UK1862_SouthBankTees_NRA_Addendum_Issue_01.pdf]]|''433 KB''|''26-Apr-2022//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-PC1084-RHD-SB-DN-SK-C-0014-P02-51.pdf|PC1084-RHD-SB-DN-SK-C-0014-P02.pdf]]|//438 KB''|''11-May-2022//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-Proposed_Dredge_Footprint_Berth_Channel_Phase1_20220510-52.kml|Proposed_Dredge_Footprint_Berth_Channel_Phase1_20220510.kml]]|//3 KB''|''11-May-2022//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-PC1084-RHD-ZZ-XX-NT-Z-0001%20MLA.2020.00506.1%20Response%20to%20Further%20Information%20Request-53.pdf|PC1084-RHD-ZZ-XX-NT-Z-0001 MLA.2020.00506.1 Response to Further Information Request.pdf]]|//159 KB''|''11-May-2022//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-South%20Bank%20Quay%20-%20Enabling%20Works%20Methodology-54.pdf|South Bank Quay - Enabling Works Methodology.pdf]]|//132 KB''|''04-Aug-2022//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-20220512_MLA_2020_00506_1_variation_HRA_FINAL.pdf|20220512_MLA_2020_00506_1_variation_HRA_FINAL.pdf]]|//272 KB''|''08-Aug-2022//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-Schedule 8_Condition 5.2.11 disposal exclusion zone coordnates (1).pdf|Schedule 8_Condition 5.2.11 disposal exclusion zone coordnates (1).pdf]]|//65 KB''|''19-Aug-2022//| ===== MLA/2020/00506/2 ===== Variation 2 - Submitted 04-Oct-2022 Open ==== Response Documents ==== |h File|h Size|h Date| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-MLV2 Options Paper - Final.pdf|MLV2 Options Paper - Final.pdf]] - Licence Schedule 9|//542 KB''|''24-Feb-2023//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-Licence Document (Marine).pdf|Licence Document (Marine).pdf]]|//135 KB''|''28-Feb-2023//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-Decision Letter (Marine).pdf|Decision Letter (Marine).pdf]]|//1 MB''|''28-Feb-2023//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-Marine Coordinate Schedules.pdf|Marine Coordinate Schedules.pdf]]|//15 KB''|''28-Feb-2023//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-Returns.pdf|Returns.pdf]]|//31 KB''|''28-Feb-2023//| ==== Additional Documents ==== |h File|h Size|h Date| |[[this>Teesworks/Planning/MLA_202_00506-BH01-15_Sediment%20Sampling%20Results.zip|BH01-15_Sediment Sampling Results.zip]]|//6 MB''|''04-Oct-2022//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-Final%20BH01-BH15%20Logs-60.pdf|Final BH01-BH15 Logs.pdf]]|//1 MB''|''04-Oct-2022//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-MLV2%20Options%20Paper%20-%20Final-61.pdf|MLV2 Options Paper - Final.pdf]]|//542 KB''|''04-Oct-2022//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-PC1084-RHD-SB-EN-NT-EV-1134-L.2021.00333%20South%20Bank%20Quay%20Marine%20Licence%20Variation%20Request%202-62.pdf|PC1084-RHD-SB-EN-NT-EV-1134-L.2021.00333 South Bank Quay Marine Licence Variation Request 2.pdf]]|//285 KB''|''04-Oct-2022//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-SBQ1-GCL-ZZZ-SBKXX-DR-WM-0007%20C02-63.pdf|SBQ1-GCL-ZZZ-SBKXX-DR-WM-0007 C02.pdf]]|//209 KB''|''04-Oct-2022//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-SBQ1-GCL-ZZZ-SBKXX-DR-WM-0008%20C01-64.pdf|SBQ1-GCL-ZZZ-SBKXX-DR-WM-0008 C01.pdf]]|//485 KB''|''04-Oct-2022//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-RE_%20South%20Bank%20Phase%201%20Variation%20MLA_2020_00506_1%20-%20SEAL%20advice_PDF_redacted_Redacted-65.pdf|RE_ South Bank Phase 1 Variation MLA_2020_00506_1 - SEAL advice_PDF_redacted_Redacted.pdf]]|//671 KB''|''01-Nov-2022//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-PC1084-RHD-SB-EN-NT-EV-1137-MLA.2020.00506.2%20South%20Bank%20Quay%20Marine%20Licence%20Variation%202%20RFI%2017-66.pdf|PC1084-RHD-SB-EN-NT-EV-1137-MLA.2020.00506.2 South Bank Quay Marine Licence Variation 2 RFI 17.pdf]]|//268 KB''|''17-Nov-2022//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-MLA_2020_00506_2_RFI 18.pdf|MLA_2020_00506/MLA_2020_00506_2_RFI 18.pdf]]|//174 KB''|''21-Nov-2022//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-PC1084-RHD-SB-EN-NT-EV-1139 South Bank Quay Phase 1 FIR 18 Response.pdf|PC1084-RHD-SB-EN-NT-EV-1139 South Bank Quay Phase 1 FIR 18 Response.pdf]]|//128 KB''|''29-Nov-2022//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-EA_MLA2020005062_OFFICIAL_301122.pdf|EA_MLA2020005062_OFFICIAL_301122.pdf]]|//31 KB''|''01-Dec-2022//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-MLA_2020_00506_2_RFI 19_Cefas Comments_MMO requested updates.pdf|MLA_2020_00506_2_RFI 19_Cefas Comments_MMO requested updates.pdf]]|//122 KB''|''04-Jan-2023//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-20221017_MLA_2020_00506_variation 2_HRA_FINAL.pdf|20221017_MLA_2020_00506_variation 2_HRA_FINAL.pdf]]|//622 KB''|''28-Feb-2023//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-MLA202000506 Variation 2 Meeting Minute.msg|MLA202000506 Variation 2 Meeting Minute.msg]]|//3 MB''|''24-Feb-2023//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-PC1084-RHD-SB-EN-NT-EV-1141-MLA.2020.00506.2 SBQ MLV2 FIR 19 Response.pdf|PC1084-RHD-SB-EN-NT-EV-1141-MLA.2020.00506.2 SBQ MLV2 FIR 19 Response.pdf]]|//544 KB''|''18-Jan-2023//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-PC1084-RHD-SB-EN-NT-EV-1142-MLA.2020.00506.2 South Bank Quay MLV2 Appraisal of Environmental Effects.pdf|PC1084-RHD-SB-EN-NT-EV-1142-MLA.2020.00506.2 South Bank Quay MLV2 Appraisal of Environmental Effects.pdf]]|//4 MB''|''18-Jan-2023//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-MLA_2020_00506_2_Cefas_comments_for_action_RFI_19.pdf|MLA_2020_00506_2_Cefas_comments_for_action_RFI_19.pdf]]|//186 KB''|''17-Feb-2023//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-PC1084-RHD-EN-SB-ME-EV-1144-MLA.2022.00506.2 South Bank Quay FIR 20 Response.pdf|PC1084-RHD-EN-SB-ME-EV-1144-MLA.2022.00506.2 South Bank Quay FIR 20 Response.pdf]]|//2 MB''|''22-Feb-2023//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-MMO VARIATION OBJECTION_S_Rennie.pdf|MMO VARIATION OBJECTION_S_Rennie.docx]]|//5 MB''|''24-Feb-2023//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-20230224_S_Rennie_Comments_MMO_Response_v1.pdf|20230224_S_Rennie_Comments_MMO_Response_v1.docx]]|//12 KB''|''24-Feb-2023//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-20230224_Natural_England_Comments_MMO_Response_v1.pdf|20230224_Natural_England_Comments_MMO_Response_v1.docx]]|//13 KB''|''24-Feb-2023//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-20230224_NEIFCA_Comments_MMO_Response_v1.pdf|20230224_NEIFCA_Comments_MMO_Response_v1.docx]]|//12 KB''|''24-Feb-2023//| |[[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-20230224_S_Bunce_Objection_MMO_Response_v1.pdf|20230224_S_Bunce_Objection_MMO_Response_v1.docx]]|//12 KB''|''24-Feb-2023//| ===== Consultations ===== ===== Case Consultation Responses ===== ==== MMO Coastal Offices & MCT - North East Marine Area ==== Consulted on 23 December 2020. Responded on 18 January 2021. The consultee was asked for their comments on an older version of this case (MLA/2020/00506). They responded: Please see supporting documents The consultee included the following files with their response: [[this>Teesworks/Planning/MLA_2020_00506/MLA-2020-00506.pdf|MLA-2020-00506.docx]] ==== Natural England - 1 - Northumbria ==== Consulted on 23 December 2020. Responded on 29 January 2021. The consultee was asked for their comments on an older version of this case (MLA/2020/00506). They responded: Dear Emmanuel, Please fine NE's formal advice letter uploaded to MCMS. Please note it is the same advice letter for all 4 consultations. Thanks, Josh The consultee included the following files with their response: [[this>Teesworks/Planning/MLA_2020_00506/338486%20-%20338489,%20NE%20formal%20response%20to%20SBW%20MLA,%2029.01.21.pdf|338486 - 338489, NE formal response to SBW MLA, 29.01.21.pdf]] ==== Maritime and Coastguard Agency - Navigational Safety Branch ==== Consulted on 23 December 2020. Responded on 21 January 2021. The consultee was asked for their comments on an older version of this case (MLA/2020/00506). They responded: Thank you for the opportunity to comment on the Marine Licence application and supporting papers for the proposed South Bank Quay - Phase I scheme in the Tees Estuary. The information provided has been considered by representatives of UK Technical Services Navigation at the Maritime and Coastguard Agency (MCA). The MCA has an interest in the works associated with the marine environment, and the potential impact on the safety of navigation, access to ports, harbours and marinas and any impact on our search and rescue obligations. We note that the works fall within the jurisdiction of PD Teesport who are the Statutory Harbour Authority (SHA) and therefore responsible for maintaining the safety of navigation before, during and after these proposed works. We would expect the impacts of the works on the safety of navigation to be considered and addressed by the SHA, in consultation with the Harbour Master and other relevant navigation stakeholders, and we welcome the completion of the Navigation Risk Assessment as part of the EIA process in support of this application On this occasion, the Maritime and Coastguard Agency (MCA) has no objection to consent being granted provided all maritime safety legislation is followed and the conditions/advisories below are applied: Conditions: * The Licencee must ensure that HM Coastguard, in this case zone7@hmcg.gov.uk is made aware of the works prior to commencement. * The Licencee must notify the UK Hydrographic Office to permit the promulgation of maritime safety information and updating of nautical charts and publications through the national Notice to Mariners system. In addition, the following advice should be provided to the applicant to facilitate the proposed works: Advisories: * The Licencee should ensure suitable bunding, storage facilities are employed to prevent the release of fuel oils, lubricating fluids associated with the plant and equipment into the marine environment. 2. Any jack up barges / vessels utilised during the works, when jacked up, should exhibit signals in accordance with the UK Standard Marking Schedule for Offshore Installations. 3. The site is within port limits and the applicant should gain the approval/agreement of the responsible local navigation authority. A local notification must be sent to the Harbour Authority who will decide if a Port NM, as they may wish to issue local warnings to alert those navigating in the vicinity to the presence of the works, as deemed necessary. Details required: start date/ end date, work to be done, positions of the work area (WGS84), marking of the work area. UKHO will then review the subsequent Port NM to see if action is required. 4. A local notification must be sent to the Harbour Authority on completion of the work. Any change data including engineering drawings, hydrographic surveys, details of new or changed aids to navigation must then be sent to the Harbour Authority with the instruction to pass onto the UKHO as per guidance in 'Harbour Master's Guide to Hydrographic and Maritime Information Exchange' published on the UKHO website 5. To address the ongoing safe operation of the marine interface for this project, we would like to point the developers in the direction of the Port Marine Safety Code (PMSC) and its Guide to Good Practice. They will need to liaise and consult with the SHA and develop a robust Safety Management System (SMS) for the project under this code. The code sets out a national standard for every aspect of port marine safety.This can be found here: https://www.gov.uk/government/publications/a-guide-to-good-practice-on-port-marine-operations 6. The MCA recommends that, as the site falls within the jurisdiction of a SHA, consideration is given to the current powers held under the Harbours Act 1964 to cover any changes to the current port operations as a result of these works (i.e. a Harbour Revision Order where necessary). Kind regards Technical Services Navigation ==== Environment Agency - North East Area ==== Consulted on 23 December 2020. Responded on 22 February 2021. The consultee was asked for their comments on an older version of this case (MLA/2020/00506). They responded: Fern Skeldon, Marine Management Organisation, PO Box 1275, Newcastle upon Tyne, NE99 5BN Our ref: NA/2021/115294/01-L01 Your ref: MLA/2020/00506 Date: 22 February 2021 Dear Fern SOUTH BANK QUAY - PHASE 1 WORKS COMPRISING OF DEMOLITION, CAPITAL DREDGING, OFFSHORE DISPOSAL OF DREDGED MATERIAL, PLACEMENT OF ROCK IN THE BERTH POCKET AND CONSTRUCTION AND OPERATION OF NEW QUAY. LAND AT SOUTH BANK WHARF, GRANGETOWN, LACKENBY. Thank you for consulting us on the above marine licence application which we received 23 December 2021. We have also provided comments on Phase 2 of this development (MLA/2020/00507); the same comments apply for both phases. Environment Agency position We OBJECT to this activity, as submitted, as it may cause deterioration of the Tees Transitional waterbody (GB510302509900). The submitted proposal does not include an adequate Water Framework Directive (WFD) assessment. We will maintain our objection until the applicant has provided an updated WFD assessment in respect to the points below: * Site specific sediment surveys and assessments * Site specific benthic ecology surveys and assessments Reason(s) Based on the information submitted, there is a significant risk that the development may * cause deterioration of the water body status * prevent achievement of good ecological potential The Northumbria River Basin Management Plan (RBMP) sets out the environmental objectives for the river basin district, including statutory objectives for water bodies and protected areas. It also includes a summary programme of measures required to achieve these objectives. Under the Water Environment (Water Framework Directive) (England and Wales) Regulations 2017 (WFD Regulations), public bodies must have regard to the relevant RBMP in exercising their functions which affect a river basin district. * i) **Site specific sediment surveys and assessments** At this time, insufficient information has been provided to demonstrate that the risks of pollution posed to the Tees estuary water quality can be safely managed. The EIA considers the results of assessments undertaken for nearby licence applications, namely the Northern Gateway Container Terminal Project. However, we would require site specific sediment surveys. The EIA notes in paragraph 7.4.3 that a site-specific sediment quality survey was proposed to be undertaken in 2020 and we understand through correspondence with agents for this site that this has been completed and is currently being analysed, with the final batch of results being anticipated into mid-April. It is agreed that the water quality assessment would be revisited and this would be undertaken using the Environment Agency's SeDiChem tool. **Requirement: Submit additional suite of site-specific sediment quality surveys prior to determination. The applicant should supply the raw specific data and then repeat the process within Section 7 of the EIA statement to show the site specific water quality impacts of the proposed application. This should then be considered within the updated Water Framework Directive assessment.** * ii) **Site specific benthic ecology surveys and assessments/adequate mitigation** The EIA discusses previous benthic ecology assessments in the Tees Estuary, notably from the Northern Gateway Container Terminal Project undertake in 2006 and 2019 and the Anglo American Harbour Facilities project undertaken in 2014. The EIA goes on to state that a site specific benthic ecological survey will be undertaken during 2020 to provide a detailed understanding of the benthic ecology with and adjacent to the proposed scheme footprint. We have discussed with the applicant the overall scope and design of the ecology survey and we are in agreement with this in principle, although appreciate this will need to be considered by Natural England. We will need to see the results of the survey. In respect to the terrestrial planning application for this scheme, it is understood that the applicant will be undertaking a biodiversity net gain assessment (as a condition) to quantify the loss from the proposal to feed into the Environment and Biodiversity Strategy for the wider Teeswork regeneration. The proposed activity is considered to result in a 2.5ha loss of intertidal area, 5ha loss of subtidal and an additional disturbance of 32.5 ha of subtidal. We acknowledge and support the use of vertipools, however the EIA does note that these would be poor quality overall, and this would still result in an overall net loss. We would appreciate some clarity from the MMO as to how this will feed into the marine licence and requirements for mitigation and/or compensation. **Requirement: We require the submission of the site specific benthic ecology surveys prior to determination to understand the impacts of the proposal. The results of the survey should also be considered within the updated Water Framework Directive assessment** **Overcoming our objection** Please address the following points above and consider this within an updated WFD assessment. Please consult us and we will respond with 21 days. We also would require further clarification on the below matter: **Potential increased erosion of the north bank mudflat** In respect to the impacts of sediment deposition resulting from the Stages 1 to 4 of the proposed dredging programme, the EIA assessment states this is predicted to be immeasurable. We contacted the agent to ask the impact of increased erosion to the north bank had been considered, in respect to a small area of elevated flow which had been modelled. We received the following response: //"The predicted localised increased in current speeds at the upstream end of the proposed scheme footprint would not occure through the whole tide cycle; this is only predicted at times of peak flow. In addition, the predicted effect is so ephemeral, localized in spatial extent and small in magnitude that erosion of the north bank mudflat is not predicted"// On the whole this is acceptable considering the project the in isolation, but we request further clarity if this stance also considers the impact of the NGCT proposal, particularly if dredge activities were to happen concurrently. Please note the location of model point M1 shown on Figure 6.51 Should the above matter be resolved, we would seek to place the following conditions. We welcome discussion on the wording of these conditions with the applicant and the MMO: **Condition - Dissolved Oxygen monitoring** During 1 July to 1 September inclusive, dissolved oxygen levels must be monitored prior to the dredging activity, as a minimum, monitored every hour during the dredging activity. If a drop of 1m/g of dissolved oxygen is observed, than the dredging activity must temporarily pause for a period of 6 hours (a tidal cycle) or until the reading returns to the previously observed level. Recorded data must be shared with the Environment Agency upon completion of the licensed activities, no later than 10 working days after their completion. The MMO must be sent a copy with 7 days of the data being issued. **Reason** The EA has a duty to maintain, improve and develop all salmon, trout, lamprey, smelt and freshwater fisheries, under the Salmon and Freshwater Fisheries Act. 1975 (SSFA) as modified by the Marine and Coastal Access Act, 2009. We are aware the applicant would be against timing restrictions to the dredging schedule. We overall have concerns on the amount to be dredged in conjunction with other planned dredges in the estuary however the above condition would mitigate for this. //'Condition - Programme of site characterisation and remediation// Prior to commencement of construction activities/relevant phase, a programme of site characterisation works is to be submitted to ascertain if contaminants are present in concentrations that could result in pollution to controlled waters. The programme shall include the following components: * A preliminary risk assessment which has identified: * all previous uses * potential contaminants associated with those uses * a conceptual model of the site indicating sources, pathways and receptors * potentially unacceptable risks arising from contamination at the site * A site investigation scheme, based on (1) to provide information for a detailed assessment of the risk to all receptors that may be affected, including those off-site. * The results of the site investigation and the detailed risk assessment referred to in (2) and, based on these, an options appraisal and remediation strategy giving full details of the remediation measures required and how they are to be undertaken. * A verification plan providing details of the data that will be collected in order to demonstrate that the works set out in the remediation strategy in (3) are complete and identifying any requirements for longer-term monitoring of pollutant linkages, maintenance and arrangements for contingency action. Any changes to these components require the written consent of the MMO. The scheme shall be implemented as approved. **Reason** The land-based construction and riverbank excavation are noted in the EIA to have the potential to increase potential of mobilization of residual contamination, as the land is known to be contaminated through historic land-uses. These contaminants may ultimately migrate the estuary. The above condition will ensure that this will be investigated and, where necessary, remediated, to mitigate for this risk. Beyond this, we have the following informative comments: **Flood Risk - Advice to MMO** Due to the minimal flood risk associated with the proposed works; the Environment Agency will not be requesting the applicant to apply for an Environmental Permit under the Environmental Permitting Regulations 2016 in addition to the marine license for this section of work. Should you require any additional information, please don't hesitate to contact me. Yours sincerely, Ms Caitlin Newby, Planning Adviser, Direct dial 0207xxxxx, Direct e-mail The consultee included the following files with their response: [[this>Teesworks/Planning/MLA_2020_00506/EA%20MLA_2020_00506%2022%20February%202021%20OFFICIAL.pdf|EA MLA_2020_00506 22 February 2021 OFFICIAL .pdf]] ==== Crown Estate - Marine Estates ==== Consulted on 23 December 2020. Responded on 8 January 2021. The consultee was asked for their comments on an older version of this case (MLA/2020/00506). They responded: The Crown Estate is affected by the proposed works and landowner's consent is required. The applicant is requested to liaise with our Managing Agent for the area: Guy Harmer of Carter Jonas on 01904 558216, Guy.Harmer@carterjonas.co.uk regarding landowner's consent for the proposed activity. The Crown Estate is affected by the proposed disposal activity and landowner's consent is required. The applicant is requested to liaise with Mark Wrigley on 0207 851 5062, mark.wrigley@thecrownestate.co.uk regarding landowner's consent for the proposed disposal activity. ==== Historic England - Durham/Northumberland/Tees ==== Consulted on 23 December 2020. Responded on 22 January 2021. The consultee was asked for their comments on an older version of this case (MLA/2020/00506). They responded: Dear Sir/Madam, Please see our advice letter, dated 22/01/2021, submitted on behalf of my colleagues in our Yorkshire & North East Office Yours faithfully, Dr Christopher Pater, Head of Marine Planning, Historic England The consultee included the following files with their response: [[this>Teesworks/Planning/MLA_2020_00506/MLA%202020%2000506%20South%20Bank%20Phase%201%20%20MLA%202020%2000507%20Phase%202.pdf|MLA 2020 00506 South Bank Phase 1 MLA 2020 00507 Phase 2.pdf]] ==== Royal Yachting Association - Royal Yachting Association ==== Consulted on 23 December 2020. Responded on 18 January 2021. The consultee was asked for their comments on an older version of this case (MLA/2020/00506). They didn't have any comments. ==== Trinity House - Trinity House ==== Consulted on 23 December 2020. Responded on 15 January 2021. The consultee was asked for their comments on an older version of this case (MLA/2020/00506). They responded: Dear Team, Trinity House has no objections to the proposed application. There are no marking conditions required for licence. Applicants should liaise with P.D. Teesport as the Local Lighthouse authority for the area. Regards Martin Thomas | Navigation Support Officer | Trinity House, Tower Hill, London, EC3N 4DH ==== Inshore Fisheries and Conservation Authorities - North Eastern ==== Consulted on 23 December 2020. The consultee was asked for their comments on an older version of this case (MLA/2020/00506). They haven't submitted a response yet. ==== Ministry of Defence - Defence Estates Safeguarding ==== Consulted on 23 December 2020. Responded on 6 January 2021. The consultee was asked for their comments on an older version of this case (MLA/2020/00506). They didn't have any comments. ==== Royal Society for the Protection of Birds - North East ==== Consulted on 23 December 2020. The consultee was asked for their comments on an older version of this case (MLA/2020/00506). They haven't submitted a response yet. ==== Teesport Harbour Authority - Teesport Harbour Authority ==== Consulted on 23 December 2020. Responded on 22 January 2021. The consultee was asked for their comments on an older version of this case (MLA/2020/00506). They responded: I refer to document MLA_2020_00507-PC1084_RHD-ZZ-XX-RP-Z-1100_EIA_Report_mainbody-8. I support the point made on p27, section 4.2 Harbours Act. A Harbour Revision Order will be required if the application is developed to vary the boundary of the harbour area to incorporate the development. I refer to drawing PC1084-RHD-SB-ZZ-DR-CM-0004. The upriver dredged area adjacent to the North Tees mudflats will require a steep slope (in the order of 1:2) if habitat is not to be lost from the SSSI (highlighted on the submitted snapshot). I suggest that further study / evidence of the stability of this material is required. The consultee included the following files with their response: [[this>Teesworks/Planning/MLA_2020_00506/PC1084-RHD-SB-ZZ-DR-CM-0004%20snapshot.PNG|PC1084-RHD-SB-ZZ-DR-CM-0004 snapshot.PNG]] ==== Centre for Environment, Fisheries and Aquaculture Science - SEAL ==== Consulted on 23 December 2020. Responded on 8 February 2021. The consultee was asked for their comments on an older version of this case (MLA/2020/00506). They responded: Please see my advice attached. The consultee included the following files with their response: [[this>Teesworks/Planning/MLA_2020_00506/20210201%20MLA202000506%20MLA202000507%20Tees%20South%20Bank%20Phases%201%20and%202%20-%20EIA%20Licence%20Advice%20Minute%20-%20SEAL%20Advice%20v2+SJB.pdf|20210201 MLA202000506 MLA202000507 Tees South Bank Phases 1 and 2 - EIA Licence Advice Minute - SEAL Advice v2+SJB.docx]] ==== Centre for Environment, Fisheries and Aquaculture Science - Shellfish Advice ==== Consulted on 23 December 2020. Responded on 1 February 2021. The consultee was asked for their comments on an older version of this case (MLA/2020/00506). They responded: Please find attached the shellfish advice. Note as the documentation for both phases (1 and 2) are the same and the assessment of impacts for the two phases are not separated within the EIA, the responses given to the questions in the advice request to MLA/2020/00506 and MLA/2020/00507 are identical. The consultee included the following files with their response: [[this>Teesworks/Planning/MLA_2020_00506/20210128%20MLA202000507%20Tee%20south%20bank%20phase%202%20shellfish%20advice%20+%20JPQC.pdf|20210128 MLA202000507 Tee south bank phase 2 shellfish advice + JPQC.docx]] ==== Centre for Environment, Fisheries and Aquaculture Science - Fisheries Advice ==== Consulted on 23 December 2020. Responded on 8 February 2021. The consultee was asked for their comments on an older version of this case (MLA/2020/00506). They responded: Dear Emmanuel, In relation to MLA/2020/00506, please find my comments attached in my capacity as advisor on fish ecology and fisheries. If you have any further queries, please do not hesitate to contact me. Best regards, Maria Gamaza The consultee included the following files with their response: [[this>Teesworks/Planning/MLA_2020_00506/20210115%20MLA202000506%20South%20Bank%20Quay-phase%201%20-%20Fisheries%20advice%20MG%20GE%20+%20JPQC.pdf|20210115 MLA202000506 South Bank Quay-phase 1 - Fisheries advice MG GE + JPQC.docx]] ==== Centre for Environment, Fisheries and Aquaculture Science - Benthic Construction ==== Consulted on 23 December 2020. Responded on 22 January 2021. The consultee was asked for their comments on an older version of this case (MLA/2020/00506). They responded: Hi Emmanuel Please find attached my benthic ecology advice for this request. All the best Stef The consultee included the following files with their response: [[this>Teesworks/Planning/MLA_2020_00506/20210121%20MLA202000506%20Tees%20South%20Bank%20Quay%20Phase%20I%20Benthic%20ecology%20+%20JPQC.pdf|20210121 MLA202000506 Tees South Bank Quay Phase I Benthic ecology + JPQC.docx]] ==== Centre for Environment, Fisheries and Aquaculture Science - Coastal Processes ==== Consulted on 23 December 2020. Responded on 8 February 2021. The consultee was asked for their comments on an older version of this case (MLA/2020/00506). They responded: Please find coastal process comments in the attached document. The consultee included the following files with their response: [[this>Teesworks/Planning/MLA_2020_00506/20210119%20MLA202000506%20Tees%20South%20Bank%20Quay%20CP%20advice%20+%20JPQC.pdf|20210119 MLA202000506 Tees South Bank Quay CP advice + JPQC.docx]] ==== Centre for Environment, Fisheries and Aquaculture Science - Underwater Noise ==== Consulted on 23 December 2020. Responded on 8 February 2021. The consultee was asked for their comments on an older version of this case (MLA/2020/00506). They responded: Hi Emmanuel, Please see my comments attached for this case. I hope my comments address your questions but please do let me know if you require anything further. Please also note that I have submitted one advice minute covering both applications MLA/2020/00506 and MLA/2020/00507. Kind regards, Rebecca The consultee included the following files with their response: [[this>Teesworks/Planning/MLA_2020_00506/MLA202000506%20&%20MLA202000507%20Tees%20South%20Bank%20Quay%20Phases%201&2%20UWN%20advice%20+%20JPQC.pdf|MLA202000506 & MLA202000507 Tees South Bank Quay Phases 1&2 UWN advice + JPQC.docx]] ==== Centre for Environment, Fisheries and Aquaculture Science - SEAL ==== Consulted on 8 March 2021. Responded on 6 April 2021. The consultee was asked for their comments on an older version of this case (MLA/2020/00506). They responded: Please see attached advice minute Kind regards Jemma Lonsdale The consultee included the following files with their response: [[this>Teesworks/Planning/MLA_2020_00506/20210406%20MLA202000506%20Tees%20South%20Bank%20Phase%201%20Request%20to%20review%20interim%20analysis%20results%20SEAL%20Advice%20FINAL.pdf|20210406 MLA202000506 Tees South Bank Phase 1 Request to review interim analysis results SEAL Advice FINAL.docx]] ==== Centre for Environment, Fisheries and Aquaculture Science - SEAL ==== Consulted on 21 May 2021. Responded on 18 June 2021. The consultee was asked for their comments on an older version of this case (MLA/2020/00506). They responded: Please see my advice attached. The consultee included the following files with their response: [[this>Teesworks/Planning/MLA_2020_00506/20210615%20MLA202000506%20MLA202000507%20Tees%20South%20Bank%20Phases%201%20and%202%20-%20EIA%20_%20SEAL%20Advice%20Followup+SJB.pdf|20210615 MLA202000506 MLA202000507 Tees South Bank Phases 1 and 2 - EIA ~ SEAL Advice Followup+SJB.docx]] ==== Centre for Environment, Fisheries and Aquaculture Science - Fisheries Advice ==== Consulted on 24 May 2021. Responded on 15 June 2021. The consultee was asked for their comments on an older version of this case (MLA/2020/00506). They responded: Dear Emmanuel, In relation to MLA/2020/00506/7, please find my comments attached in my capacity as advisor on fish ecology and fisheries, if you have any further queries, please do not hesitate to contact me. Best regards, Maria Gamaza The consultee included the following files with their response: [[this>Teesworks/Planning/MLA_2020_00506/20210603%20MLA2020005067%20Tees%20South%20Bank%20Quay%20Supplementary%20Report%20Review%20Fisheries%20advice%20MG%20GE%20+%20JP.pdf|20210603 MLA2020005067 Tees South Bank Quay Supplementary Report Review Fisheries advice MG GE + JP.docx]] ==== Centre for Environment, Fisheries and Aquaculture Science - Underwater Noise ==== Consulted on 24 May 2021. Responded on 14 June 2021. The consultee was asked for their comments on an older version of this case (MLA/2020/00506). They responded: Hi Emmanuel Please see my comments attached for this consultation. Kind regards, Rebecca The consultee included the following files with their response: [[this>Teesworks/Planning/MLA_2020_00506/20210610%20MLA202000507%20Tees%20South%20Bank%20Quay%20Phases%201%20Follow-up%20UWN%20advice.pdf|20210610 MLA202000507 Tees South Bank Quay Phases 1 Follow-up UWN advice.docx]] ==== Natural England - 1 - Northumbria ==== Consulted on 21 May 2021. Responded on 5 July 2021. The consultee was asked for their comments on an older version of this case (MLA/2020/00506). They responded: Please find attached the supporting document. The consultee included the following files with their response: [[this>Teesworks/Planning/MLA_2020_00506/354204%20MLA_2020_00506%20-%20South%20Bank%20Wharf%20dredge%20Middlesbrough%205.07.2021.pdf|354204 MLA_2020_00506 - South Bank Wharf dredge Middlesbrough 5.07.2021.pdf]] ==== Environment Agency - North East Area ==== Consulted on 21 May 2021. Responded on 29 June 2021. The consultee was asked for their comments on an older version of this case (MLA/2020/00506). They responded: Fern Skeldon, Marine Management Organisation, PO Box 1275, Newcastle upon Tyne, NE99 5BN Our ref: NA/2021/115294/02-L01 Your ref: MLA/2020/00506 Date: 29 June 2021 Dear Fern SOUTH BANK QUAY - PHASE 1 WORKS COMPRISING OF DEMOLITION, CAPITAL DREDGING, OFFSHORE DISPOSAL OF DREDGED MATERIAL, PLACEMENT OF ROCK IN THE BERTH POCKET AND CONSTRUCTION AND OPERATION OF NEW QUAY. (ADDITIONAL INFORMATION RECEIVED 21/05/21). LAND AT SOUTH BANK WHARF, GRANGETOWN, LACKENBY. Thank you for re-consulting us on the above marine licence application which we received 21 May 2021. **Environment Agency position** We have reviewed the supplementary information received and wish to remove our objection, dated 22 February 2021, subject to a CONDITION. **Condition - Water Quality Monitoring** The piling and dredging activities approved by this licence may not commence until such a time as a scheme of monitoring has been submitted to, and approved in writing by, the Marine Management Organisation. The scheme shall include: * Baseline assessment prior to commencement. * Programme to monitor dissolved oxygen levels and turbidity * Programme of post-implementation monitoring The scheme shall be fully implemented and subsequently adhered to in accordance with the timing/phasing arrangements embodied within the scheme, or any details as may be subsequently agreed, in writing by, the MMO. **Reason** The applicant wishes for there to be no restrictions to piling and dredging operations. A condition to monitor impacts to water quality during construction would a suitable compromise. Atlantic Salmon are an internationally important protected species, which are currently at risk of decline. The EA has a duty to maintain, improve and develop all salmon, trout, lamprey, smelt and freshwater fisheries, under the Salmon and Freshwater Fishereis Act. 1975 (SFFA) as modified by the Marine and Coastal Access Act, 2009. We discharge these responsibilities alongside our overarching duties to further conservation, promote sustainable development and water based recreation. As temperature increases during the summer months, water becomes much less soluble to oxygen and as such the risk of hypoxia to fish increases. During the summer months, not only is this the most likely time for dissolved oxygen to be naturally low, but also when the salmon's metabolic rate is at its highest and demand is greatest. If at all possible the months of July and August should be avoided. This condition would also ensure that the conclusions drawn in the supplementary report are realised in respect to elevated concentrations of suspended solids. Beyond this, we wish to offer the following additional comments: **Dissolved Oxygen monitoring - Advice to MMO/Applicant** We have suggested a condition that would allow the applicant to submit a bespoke programme for consideration. Our preference for dissolved oxygen monitoring, is that monitoring is carried out between 1 July and 1 September inclusive, where activities are being carried out, and this should be monitored prior to dredging activity and during dredging activity at regular intervals. We would respectfully request that this is shared with the Environment Agency as this would greatly help is build a better understanding of the impacts of dredging activity in the Tees. If a drop of 1mg/l of dissolved oxygen is observed, then operations causing that effect should temporarily pause for a period of 6 hours (a tidal cycle) or until the reading returns to the previously observed level. //'Loss of intertidal habitat and impacts to juvenile fish - Advice to MMO/Applicant// The supplementary information has acknowledged the project would result in a loss of habitat. We were pleased to see the level of work gone into this, particularly in the beam trawl and fyke nets which have shown the importance of the intertidal zone and the importance of the wooden structures for juvenile fish. It is important to note that the survey was completed in November and during the summer months it is likely that it would show other fish species utilise the area. We understand, with exception to the inclusion of vertipools, that it is not likely that further on-site mitigation can be achieved to compensation for this loss of habitat. It would be preferable if the MMO were able to condition the requirement of mitigation off-site but we appreciate that there may be no mechanism for this in the marine planning system. We are aware that the wider losses of habitat linked to the development in the South Tees area would be included in the South Tees Environment and Biodiversity Strategy. The requirement for this is already conditioned to the terrestrial application for this development; on this basis we are happy to defer this matter to this condition and will work closely with the applicant to ensure this is achieved. **Flood Risk - Advice to MMO** Due to the minimal flood risk associated with the proposed works; the Environment Agency will not be requesting the applicant to apply for an Environmental Permit under the Environmental Permitting Regulations 2016 in addition to the marine license for this section of work. Should you require any additional information please don't hesitate to contact me. Yours faithfully Ms Caitlin Newby, Planning Adviser, Direct dial 0207xxxxxx, Direct e-mail The consultee included the following files with their response: [[this>Teesworks/Planning/MLA_2020_00506/EA%20MLA_2020_00506%20v2%2029%20June%202021%20OFFICIAL.pdf|EA MLA_2020_00506 v2 29 June 2021 OFFICIAL.pdf]] ==== Centre for Environment, Fisheries and Aquaculture Science - SEAL ==== Consulted on 15 July 2021. Responded on 29 July 2021. The consultee was asked for their comments on an older version of this case (MLA/2020/00506). They responded: Please see my advice attached. The consultee included the following files with their response: [[this>Teesworks/Planning/MLA_2020_00506/20210729%20MLA202000506%20Tees%20South%20Bank%20-%20Further%20Proposed%20Sampling%20to%20delineate%20an%20exclusion%20zone+SJB.pdf|20210729 MLA202000506 Tees South Bank - Further Proposed Sampling to delineate an exclusion zone+SJB.docx]] ==== Centre for Environment, Fisheries and Aquaculture Science - SEAL ==== Consulted on 18 May 2022. Responded on 10 June 2022. The consultee was asked for their comments on an older version of this case (MLA/2020/00506/1). They responded: Dear Ashley, I have provided the comments on the above application without sight of the requested documents. If you have any questions please let me know. Kind regards, Sylvia The consultee included the following files with their response: [[this>Teesworks/Planning/MLA_2020_00506/20220608%20MLA2020005061%20L20121003331%20Cefas%20advice%20Final.pdf|20220608 MLA2020005061 L20121003331 Cefas advice Final.docx]] ==== Natural England - 1 - Northumbria ==== Consulted on 18 May 2022. Responded on 15 June 2022. The consultee was asked for their comments on an older version of this case (MLA/2020/00506/1). They responded: Please see attached document. The consultee included the following files with their response: [[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506_1%20South%20Bank%20Wharf%20Variation%20Response%20FINAL%20392938.pdf|MLA_2020_00506_1 South Bank Wharf Variation Response FINAL 392938.pdf]] ==== Environment Agency - North East Area ==== Consulted on 18 May 2022. Responded on 20 July 2022. The consultee was asked for their comments on an older version of this case (MLA/2020/00506/1). They responded: Hi, attached are the EA's comments. Please accept my apologies for the delay in responding to the consultation. Many thanks Lucy The consultee included the following files with their response: [[this>Teesworks/Planning/MLA_2020_00506/EA_MLA2020005061_VAR_OFFICIAL200722.pdf|EA_MLA2020005061_VAR_OFFICIAL200722.pdf]] ==== MMO Coastal Offices & MCT - North East Marine Area ==== Consulted on 18 May 2022. Responded on 15 June 2022. The consultee was asked for their comments on an older version of this case (MLA/2020/00506/1). They responded: Please find attached consultation response. Lindsey Newlyn, North East Marine Team. The consultee included the following files with their response: [[this>Teesworks/Planning/MLA_2020_00506/MLA.2020.00506.1%20%20South%20Bank%20Quay%20%20Phase%201%20Variation%20Request.pdf|MLA.2020.00506.1 South Bank Quay Phase 1 Variation Request.docx]] ==== Maritime and Coastguard Agency - Navigational Safety Branch ==== Consulted on 18 May 2022. Responded on 10 June 2022. The consultee was asked for their comments on an older version of this case (MLA/2020/00506/1). They responded: Dear Ashley, Thank you for the opportunity to comment on the Marine Licence variation of South Bank Quay project at Tees Dock, Middlesbrough . The UK Technical Services Navigation team of the Maritime and Coastguard Agency has reviewed the documents received and would like to comment as follows: We note that the works fall within the jurisdiction of a Statutory Harbour Authority (SHA) - Port of Tyne Authority and therefore they are responsible for the safety of navigation within their waters. Therefore, on this occasion, the MCA has no objection to consent being granted provided all maritime safety legislation is followed, the original conditions of consent are adhered to. UK Technical Services Navigation ==== Trinity House - Trinity House ==== Consulted on 18 May 2022. Responded on 8 June 2022. The consultee was asked for their comments on an older version of this case (MLA/2020/00506/1). They responded: Good afternoon, Trinity House has no objections. Applicants to confirm any marking requirements with PD Teesport as the LLA for the area. regards, Trevor ==== Teesport Harbour Authority - Teesport Harbour Authority ==== Consulted on 18 May 2022. The consultee was asked for their comments on an older version of this case (MLA/2020/00506/1). They haven't submitted a response yet. ===== Document Consultation Responses ===== ==== Natural England (1 - Northumbria) ==== Consulted on 19 July 2021. Responded on 30 July 2021. The consultee was asked for their comments on [[this>Teesworks/Planning/MLA_2020_00506/MLA202000506%20and%20MLA202000507%20%20Draft%20HRA%20%20(2).pdf|MLA202000506 and MLA202000507 Draft HRA (2).docx]] . They responded: Please see attached the supporting document. The consultee included the following files with their response: [[this>Teesworks/Planning/MLA_2020_00506/360368%20NE%20response%20to%20MMO%20MLA202000506%20and%20MLA202000507%20HRA%2030.07.2021.pdf|360368 NE response to MMO MLA202000506 and MLA202000507 HRA 30.07.2021.pdf]] ==== NE (1 - Northumbria) ==== Consulted on 18 June 2021. Responded on 5 July 2021. The consultee was asked for their comments on [[this>Teesworks/Planning/MLA_2020_00506/MLA202000506%20and%20MLA202000507%20%20Draft%20HRA.pdf|MLA202000506 and MLA202000507 Draft HRA .docx]] . They responded: Please find attached Natural England's advice. The consultee included the following files with their response: [[this>Teesworks/Planning/MLA_2020_00506/354204%20MLA_2020_00506%20-%20South%20Bank%20Wharf%20dredge%20Middlesbrough%205.07.2021%20(1).pdf|354204 MLA_2020_00506 - South Bank Wharf dredge Middlesbrough 5.07.2021.pdf]] ==== Natural England (1 - Northumbria) ==== Consulted on 23 December 2020. Responded on 29 January 2021. The consultee was asked for their comments on [[this>Teesworks/Planning/MLA_2020_00506/MLA202000506%20and%20MLA202000507%20%20Draft%20HRA%20phase%201%20and%202.pdf|MLA202000506 and MLA202000507 Draft HRA phase 1 and 2.pdf]] . They responded: Dear Emmanuel, Please fine NE's formal advice letter uploaded to MCMS. Please note it is the same advice letter for all 4 consultations. Thanks, Josh The consultee included the following files with their response: [[this>Teesworks/Planning/MLA_2020_00506/338486%20-%20338489,%20NE%20formal%20response%20to%20SBW%20MLA,%2029.01.21%20(1).pdf|338486 - 338489, NE formal response to SBW MLA, 29.01.21.pdf]] ===== Return Consultation Responses ===== ==== EA (North East Area) ==== R8.2 Consulted on 6 June 2022. Responded on 3 August 2022. The consultee was asked for their comments on these documents: [[this>Teesworks/Planning/MLA_2020_00506/PC1084-RHD-SB-EN-NT-EV-1124%20Updated%20Scheme%20of%20Monitoring%20-%20May%202022.pdf|PC1084-RHD-SB-EN-NT-EV-1124 Updated Scheme of Monitoring - May 2022.pdf]] [[this>Teesworks/Planning/MLA_2020_00506/PC1084-RHD-SB-EN-NT-EV-1127%20MLA.2020.00506.R8%20Response%20to%20Consultation%20Comments%20on%20Scheme%20of%20Monitoring.pdf|PC1084-RHD-SB-EN-NT-EV-1127 MLA.2020.00506.R8 Response to Consultation Comments on Scheme of Monitoring.pdf]] They responded: attached is the EA's response to this application. Regards Lucy The consultee included the following files with their response: [[this>Teesworks/Planning/MLA_2020_00506/EA_MLA2020005061_OFFICIAL_030822.pdf|EA_MLA2020005061_OFFICIAL_030822.pdf]] ==== CEFAS (SEAL) ==== R8.2 Consulted on 6 June 2022. Responded on 20 June 2022. The consultee was asked for their comments on these documents: [[this>Teesworks/Planning/MLA_2020_00506/PC1084-RHD-SB-EN-NT-EV-1124%20Updated%20Scheme%20of%20Monitoring%20-%20May%202022.pdf|PC1084-RHD-SB-EN-NT-EV-1124 Updated Scheme of Monitoring - May 2022.pdf]] [[this>Teesworks/Planning/MLA_2020_00506/PC1084-RHD-SB-EN-NT-EV-1127%20MLA.2020.00506.R8%20Response%20to%20Consultation%20Comments%20on%20Scheme%20of%20Monitoring.pdf|PC1084-RHD-SB-EN-NT-EV-1127 MLA.2020.00506.R8 Response to Consultation Comments on Scheme of Monitoring.pdf]] They responded: I defer comments to the fisheries team. ==== Fisheries Advice ==== R8.2 Consulted on 7 June 2022. Responded on 20 June 2022. The consultee was asked for their comments on these documents: [[this>Teesworks/Planning/MLA_2020_00506/PC1084-RHD-SB-EN-NT-EV-1124%20Updated%20Scheme%20of%20Monitoring%20-%20May%202022.pdf|PC1084-RHD-SB-EN-NT-EV-1124 Updated Scheme of Monitoring - May 2022.pdf]] [[this>Teesworks/Planning/MLA_2020_00506/PC1084-RHD-SB-EN-NT-EV-1127%20MLA.2020.00506.R8%20Response%20to%20Consultation%20Comments%20on%20Scheme%20of%20Monitoring.pdf|PC1084-RHD-SB-EN-NT-EV-1127 MLA.2020.00506.R8 Response to Consultation Comments on Scheme of Monitoring.pdf]] They responded: Dear Fern, Please find attached fisheries advisors' comments for your consideration, With thanks and regards, Maria The consultee included the following files with their response: [[this>Teesworks/Planning/MLA_2020_00506/20220615%20MLA2020005061%20L2021003331%20Tees%20South%20Bank%20(phase%201)%20Revised%20Scheme%20of%20Monitoring%20Review%20Fisheries%20advice%20FINAL.pdf|20220615 MLA2020005061 L2021003331 Tees South Bank (phase 1) Revised Scheme of Monitoring Review Fisheries advice FINAL.docx]] ==== CEFAS (SEAL) ==== MLA/2020/00506/R13 Consulted on 4 May 2022. Responded on 1 June 2022. The consultee was asked for their comments on [[this>Teesworks/Planning/MLA_2020_00506/PC1084-RHD-SB-XX-NT-Z-0001-South%20Bank%20SSC%20monitoring%20plan%20V3.pdf|PC1084-RHD-SB-XX-NT-Z-0001-South Bank SSC monitoring plan V3.pdf]] . They responded: As SEAL advisor for dredge and disposal, I have consulted with the Fisheries team and hereby defer comments to their advice. Joe ==== Fisheries Advice ==== MLA/2020/00506/R13 Consulted on 4 May 2022. Responded on 1 June 2022. The consultee was asked for their comments on [[this>Teesworks/Planning/MLA_2020_00506/PC1084-RHD-SB-XX-NT-Z-0001-South%20Bank%20SSC%20monitoring%20plan%20V3.pdf|PC1084-RHD-SB-XX-NT-Z-0001-South Bank SSC monitoring plan V3.pdf]] . They responded: Dear Fern, Please find fisheries advisors comments attached for your consideration. I hope you have a lovely bank holiday weekend, Best regards, Maria The consultee included the following files with their response: [[this>Teesworks/Planning/MLA_2020_00506/20220518%20MLA202000506%20L2021003331Tees%20South%20Bank%20(phase%201)%20Monitoring%20Plan%20Fisheries%20advice%20FINAL.pdf|20220518 MLA202000506 L2021003331Tees South Bank (phase 1) Monitoring Plan Fisheries advice FINAL.docx]] ==== EA (North East Area) ==== MLA/2020/00506/R13 Consulted on 4 May 2022. Responded on 6 July 2022. The consultee was asked for their comments on [[this>Teesworks/Planning/MLA_2020_00506/PC1084-RHD-SB-XX-NT-Z-0001-South%20Bank%20SSC%20monitoring%20plan%20V3.pdf|PC1084-RHD-SB-XX-NT-Z-0001-South Bank SSC monitoring plan V3.pdf]] . They haven't submitted a response yet. ==== EA (North East Area) ==== R8 Consulted on 18 March 2022. Responded on 21 April 2022. The consultee was asked for their comments on [[this>Teesworks/Planning/MLA_2020_00506/PC1084-RHD-SB-EN-NT-EV-1124%20P03%20South%20Bank%20Phase%201%20Scheme%20of%20Monitoring.pdf|PC1084-RHD-SB-EN-NT-EV-1124 P03 South Bank Phase 1 Scheme of Monitoring.pdf]] . They responded: Dear Sir/Madam, Please see attached EA comments on MMO consultation ref MLA/2020/00506/1. If you have any questions regarding the comments, please contact me. Kind regards, Louise Tait The consultee included the following files with their response: [[this>Teesworks/Planning/MLA_2020_00506/210422%20EA%20response%20to%20MMO%20ref%20MLA202000506.pdf|210422 EA response to MMO ref MLA202000506.pdf]] ===== Returns ===== ==== Notification of commencement ==== MLA/2020/00506/R1 Discharged The MMO must be notified prior to the commencement of the first instance of any licensed activity. This notice must be received by the MMO no less than five working days before the commencement of that licensed activity. Deadline: no less that five working days before the commencement of any licensed activity Date received: 16 Mar 2022 Date discharged: 01 Apr 2022 Licence holder comments Demolition due to commence on 21st March 2022. ==== UK Hydrographic Office-Completion ==== MLA/2020/00506/R10 Open A notification must be sent to The Source Data Receipt team, UK Hydrographic Office, Taunton, Somerset, TA1 2DN (Email: sdr@ukho.gov.uk; Tel: 01823 337900) of completion of the licensed activities, no later than 7 days after their completion. A copy of the notification must be sent to the MMO within one week of the notification being sent. Deadline: No later than 7 days after there completion ==== Harbour Authority- Notification ==== MLA/2020/00506/R11 Open A local notification must be sent to the Harbour Authority on completion of the work. Any change data including engineering drawings, hydrographic surveys, details of new or changed aids to navigation must then be sent to the Harbour Authority with the instruction to pass onto the UKHO as per guidance in 'Harbour Master's Guide to Hydrographic and Maritime Information Exchange' published on the UKHO website Deadline: No later than 7 days after there completion ==== Disposal Site Use ==== MLA/2020/00506/R12 Discharged The applicant will liaise with Northern Gateway Container Terminal (NGCT) no later than 6 months in advance of the proposed start date of capital dredging and disposal for South Bank Quay and, subject to the outcome of that discussion, will provide either of the following to the MMO no later than 3 months in advance of the proposed start date of capital dredging and disposal: • Written confirmation that disposal of dredged material from the South Bank Quay project will not temporally coincide with that arising from the NGCT project (meaning that no single phase of the capital dredging and disposal for the two projects would occur at the same time); or, • Written confirmation that the total (aggregated) quantity of dredged material to be disposed would not exceed 1.34 million m3 per month (the peak monthly volume assessed within the EIA), should it be apparent that the dredging and disposal from South Bank Quay could temporally coincide (meaning that any phase of the capital dredging and disposal for the two projects could occur at the same time); or, • Further environmental assessment information (the scope of which would be agreed with the MMO) to analyse the potential nature of the cumulative environmental impact associated with offshore disposal should it be apparent that the dredging and disposal programmes for NGCT and the South Bank Quay project could (i) temporally coincide and (ii) the total (aggregated) quantity of dredged material to be disposed could exceed 1.34 million m3 per month, with a detailed programme of environmental monitoring to verify the predicted cumulative environmental impacts of disposal of dredged material. Deadline: Months in advance of the dredging campaign Date received: 24 May 2022 Date discharged: 14 Jul 2022 Licence holder comments Please find attached a letter providing written confirmation to discharge Return 12 / condition 5.2.13 of the marine licence for Phase 1 of the South Bank Quay project (L/2021/00333/1). ==== Dredging permission ==== MLA/2020/00506/R13 Rejected No dredging not covered under statutory harbour authority powers can be conducted during the period from 1st July to 31st August (inclusive) without written permission from the MMO. Permission will only be granted if agreement has been reached that only 1 dredge campaign is taking place at this time. No other dredging will take place on the River Tees during this period. Deadline: In advance of July of any given year Date received: 30 Mar 2022 Licence holder comments Hi Fern / Chris As discussed at our meeting (17/02/2022) on and in response to your email (17/02/2022), we have developed a monitoring plan. This monitoring plan aims to present alternative mitigation for consideration by the MMO to allow both maintenance and non-maintenance dredging to proceed during the months of July and August (i.e. it seeks to provide alternative acceptable mitigation to that stipulated in Condition 5.2.8 and replace that required for Condition 5.2.9). Many thanks Erin [[this>Teesworks/Planning/MLA_2020_00506/PC1084-RHD-SB-XX-NT-Z-0001-South%20Bank%20SSC%20monitoring%20plan%20V3.pdf|PC1084-RHD-SB-XX-NT-Z-0001-South Bank SSC monitoring plan V3.pdf]] 426 KB Created By: Miss Erin Snaith 30-MAR-2022 17:21:01 ==== Oxygen level monitoring ==== MLA/2020/00506/R14 Open If permission is granted by the MMO to undertake dredging operation during 1st July to 31st August (inclusive), dissolved oxygen levels must be monitored prior to the dredging activity, as a minimum, monitored every hour during the dredging activity. If a drop of 1m/g of dissolved oxygen is observed, than the dredging activity must temporarily pause for a period of 6 hours (a tidal cycle) or until the reading returns to the previously observed level. Recorded data must be shared with the Environment Agency upon completion of the licensed activities, no later than 10 working days after their completion. The MMO must be sent a copy within 7 days of the data being issue Deadline: Within 7 days of completing monitoring ==== Exclusion Zone ==== MLA/2020/00506/R15 Open Material from the area bounded by the coordinates detailed in schedule 8 must be excluded from disposal at sea. An enclosed bucket removal must be used to remove this material for disposal to a recognised contaminated disposal site. The enclosed bucket must be used until glacial till is reached. Once the area bounded by Schedule 8 has been dredged, surface grabs for samples within the area adjacent to the dredged area must been taken to ensure there has been no movement of contaminated sediment outside of the area bounded by Schedule 8. Any movement of contaminated sediment must be removed using an enclosed bucket and material sent for disposal to a recognised contaminated disposal site. A report detailing the results of surface grabs and any remedial action undertaken must be submitted to the MMO within one week of the completion of any remedial dredging. The exclusion zone may be reduced or removed if further evidence is presented to the MMO showing minimised areas of contamination. Written permission will be required to commence sea disposal operations. [[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-PC1084-RHD-SB-EN-ME-EV-1145-Condition%205.2.11%20Note%20P03.pdf|PC1084-RHD-SB-EN-ME-EV-1145-Condition 5.2.11 Note P03.pdf]] 2 MB [[this>Teesworks/Planning/MLA_2020_00506/Tabula-PC1084-RHD-SB-EN-ME-EV-1145-Condition 5.2.11 Note P03.xlsx|Tables from PC1084-RHD-SB-EN-ME-EV-1145-Condition 5.2.11 Note P03.xlsx]] Data reformatted in correct MMO template format: [[this>Teesworks/Planning/MLA_2020_00506/220822-MLA_2020_00506-Predredge-PC1084-RHD-SB-EN-ME-EV-1145-Condition 5.2.11 Note P03.xlsx|220822-MLA_2020_00506-Predredge-PC1084-RHD-SB-EN-ME-EV-1145-Condition 5.2.11 Note P03.xlsx]] [[this>Teesworks/Planning/MLA_2020_00506/221122-MLA_2020_00506-Postdredge-PC1084-RHD-SB-EN-ME-EV-1145-Condition 5.2.11 Note P03.xlsx|221122-MLA_2020_00506-Postdredge-PC1084-RHD-SB-EN-ME-EV-1145-Condition 5.2.11 Note P03.xlsx]] [[this>Teesworks/Planning/MLA_2020_00506/230328-MLA_2020_00506-Postremedial-PC1084-RHD-SB-EN-ME-EV-1145-Condition 5.2.11 Note P03.xlsx|230328-MLA_2020_00506-Postremedial-PC1084-RHD-SB-EN-ME-EV-1145-Condition 5.2.11 Note P03.xlsx]] Created By: Mr Matthew Greaves 02-MAY-2023 13:55:28 **Subreturns** Ref: R15.1 Discharged: Deadline: Remedial action report within one week of completion of any remedial dredging Date received: 02 May 2023 Date discharged: 24 May 2023 Licence holder comments Please find attached [[this>Teesworks/Planning/MLA_2020_00506/MLA_2020_00506-PC1084-RHD-SB-EN-ME-EV-1145-Condition%205.2.11%20Note%20P03.pdf|PC1084-RHD-SB-EN-ME-EV-1145-Condition 5.2.11 Note P03.pdf]] 2 MB [[this>Teesworks/Planning/MLA_2020_00506/Tabula-PC1084-RHD-SB-EN-ME-EV-1145-Condition 5.2.11 Note P03.xlsx|Tables from PC1084-RHD-SB-EN-ME-EV-1145-Condition 5.2.11 Note P03.xlsx]] Created By: Mr Matthew Greaves 02-MAY-2023 13:55:28 Ref: R15.2 Open: Deadline: Changes to exclusion zone only upon receipt and consultation on updated Sampling ==== Vessels ==== MLA/2020/00506/R16 Open The MMO must be notified in writing of any vessel being used to carry on any licensed activity listed in section 4 of this licence on behalf of the licence holder. Such notification must be received by the MMO no less than 24 hours before the commencement of the licensed activity. Notification must include the master's name, vessel type, vessel IMO number and vessel owner or operating company. A copy of this licence and any subsequent revisions or amendments must be read and understood by the masters of any vessel being used to carry on any licensed activity listed in section 4 of this licence, and that a copy of this licence must be held on board any such vessel. **Subreturns** Ref: R16.1 Discharged; Deadline: No less than 24 hours before the commencement of the licenced activity Date received: 07 Jul 2022 Date discharged: 12 Jul 2022 Licence holder comments 1 no. flat top barge: Vessel name: Tara Marie; Master's name: N/A (not operated plant); Vessel IMO: 9889241; Vessel owner: Foyle and Marine Dredging 2 no. tugs: Vessel names: Seal Carr and Afon Lligwy; Master's names: Alan Barker/ Michael Hargan / Keith Gillie; Vessel IMOs: 8208828 and 9266384; Vessel owner: Foyle and Marine Dredging 1 no. Backhoe dredger: Vessel name: Dinopotes; Master's name: N/A (not operated plant); Vessel IMO: 7909712; Vessel owner: Foyle and Marine Dredging 1 no. safety / work boat: Vessel name: Smartwave; Master's name: Alan Barker/ Michael Hargan / Keith Gillie; Vessel IMO: N/A; Vessel owner: Foyle and Marine Dredging Ref: R16.2 Discharged; Deadline: No less than 24 hours before the commencement of the licenced activity Date received: 26 Aug 2022 Date discharged: 23 Sep 2022 Licence holder comments The following additional vessels will be used in the upcoming dredge campaign due to commence in September: 2 no. hopper barges: Vessel names: ACB Phoebe and ACB Zeus; Master's names: N/A (not operated plant); Vessel IMOs: N/A; Vessel owners: Alan C. Bennett & Sons Ltd. Ref: R16.3 Discharged; Deadline: No less than 24 hours before the commencement of the licenced activity Date received 21 Dec 2022: Date discharged 29 Dec 2022: Licence holder comments The following additional vessel will be used in dredging activities in January 2023: 1 no. hopper barge: Vessel name: B305 Split Hopper Barge; Master's name: N/A (not operated plant); Vessel IMO: N/A; Vessel owner: Holding A. Baars Azn B.V Ref: R16.4 Discharged; Deadline: No less than 24 hours before the commencement of the licenced activity Date received: 19 Jan 2023 Date discharged: 25 Jan 2023 Licence holder comments The following additional vessel will be involved in remedial dredging activities in January 2023: Vessel Name: B113; Master Name: N/A (Not Operated); Vessel Type: Split Hopper Barge; IMO Number: N/A; Vessel Owner/ Operating Company: Holding A. Baars Azn B.V Ref: R16.5 Dischared; Deadline: No less than 24 hours before the commencement of the licenced activity Date received 19 Jan 2023 Date discharged 25 Jan 2023 Licence holder comments The following additional vessels will be involved in dredging activities commencing on 30/01/2023: Vessel Name: Athena; Master Name: Wernie Griffioen / Peter Doelman; Vessel Type: Cutter Suction Dredger, self-propelled; IMO Number: 9548603; Vessel Owner/ Operating Company: Van Oord Vessel Name: Cronus; Master Name: Rob Bregman / Ronny van der Net; Vessel Type: Multicat; IMO Number: 9639971; Vessel Owner/ Operating Company: Van Oord Vessel Name: Buzzard + Sand Carrier 105; Master Name: Justiniano Saberon; Vessel Type: Tug / Pushboat + Hopper Barge; IMO Number: 9524528; Vessel Owner/ Operating Company: Van Oord Vessel Name: Kingfisher + Sand Carrier 104; Master Name: Alvin Tano; Vessel Type: Tug / Pushboat + Hopper Barge; IMO Number: 9548885; Vessel Owner/ Operating Company: Van Oord Vessel Name: Duchess; Master Name: Ben Kamp / Ton Benning; Vessel Type: Tug / Workboat; IMO Number: 9928944; Vessel Owner/ Operating Company: Landfall Marine Contracts bv Vessel Name: Gouwestroom; Master Name: Jan Grunefeld / Toin Nieuwenhuizen; Vessel Type: Tug / Workboat; IMO Number: 8943569; Vessel Owner/ Operating Company: Van Wijngaarden Marine Services bv Ref: R16.6 Open; Deadline: No less than 24 hours before the commencement of the licenced activity Ref: R16.7 Open; Deadline: No less than 24 hours before the commencement of the licenced activity ==== Agents / contractors / sub-contractors ==== MLA/2020/00506/R17 Open The MMO must be notified in writing of any agents, contractors or sub-contractors that will carry on any licensed activity listed in section 4 of this licence on behalf of the licence holder. Such notification must be received by the MMO no less than 24 hours before the commencement of the licensed activity. A copy of this licence and any subsequent revisions or amendments must be provided to, read and understood by any agents, contractors or sub-contractors that will carry on any licensed activity listed in section 4 of this licence on behalf of the licence holder. **Subreturns** Ref: R17.1 Discharged; Deadline: No less than 24 hours before the commencement of the licenced activities Date received: 19 Jan 2023 Date discharged: 25 Jan 2023 Licence holder comments Van Oord will be involved as a subcontractor for dredging activities commencing on 30/01/2023. Ref: R17.2 Open; Deadline: No less than 24 hours before the commencement of the licenced activities Ref: R17.3 Open; Deadline: No less than 24 hours before the commencement of the licenced activities ==== Agents, contractors and sub-contractors ==== MLA/2020/00506/R18 Open The MMO must be notified in writing of any agents, contractors or sub-contractors that will carry on any licensed activity listed in section 4 of this licence on behalf of the licence holder. Such notification must be received by the MMO no less than 24 hours before the commencement of the licensed activity. A copy of this licence and any subsequent revisions or amendments must be provided to, read and understood by any agents, contractors or sub-contractors that will carry on any licensed activity listed in section 4 of this licence on behalf of the licence holder. **Subreturns** Ref: R18.1 Open; Deadline: 24 hours before the commencement of the licensed activity. Ref: R18.2 Open; Deadline: 24 hours before the commencement of the licensed activity. ==== Vessels ==== MLA/2020/00506/R19 Open The MMO must be notified in writing of any vessel being used to carry on any licensed activity listed in section 4 of this licence on behalf of the licence holder. Such notification must be received by the MMO no less than 24 hours before the commencement of the licensed activity. Notification must include the master's name, vessel type, vessel IMO number and vessel owner or operating company. A copy of this licence and any subsequent revisions or amendments must be read and understood by the masters of any vessel being used to carry on any licensed activity listed in section 4 of this licence, and that a copy of this licence must be held on board any such vessel. **Subreturns** Ref: R19.1 Open; Deadline: no less than 24 hours before the commencement of the licensed activity. Ref: R19.2 Open; Deadline: no less than 24 hours before the commencement of the licensed activity. ==== Agents / contractors / sub-contractors ==== MLA/2020/00506/R2 Discharged The MMO must be notified in writing of any agents, contractors or sub-contractors that will carry on any licensed activity listed in section 4 of this licence on behalf of the licence holder. Such notification must be received by the MMO no less than 24 hours before the commencement of the licensed activity. A copy of this licence and any subsequent revisions or amendments must be provided to, read and understood by any agents, contractors or sub-contractors that will carry on any licensed activity listed in section 4 of this licence on behalf of the licence holder. Deadline: No less than 24 hours before the commencement of the licenced activities Date received: 16 Mar 2022 Date discharged: 01 Apr 2022 Licence holder comments Principal Contractor – John Graham Construction Demolition Subcontractor – Foyle and Marine Dredging ==== Disposal Activity ==== MLA/2020/00506/R20 Open During the course of disposal, material must be distributed evenly over the Tees Bay C (TY150) disposal site. A report demonstrating the location of each disposal activity must be submitted to the MMO within one week of completion of Activity 1.1. This report must, as a minimum, include a diagram of the Tees Bay C disposal site separated into grids, with the location of each daily disposal clearly plotted. **Subreturns** Ref: R20.1 Open: Deadline: Within one week of completion of Activity 1.1. Ref: R20.2 Open: Deadline: Within one week of completion of Activity 1.1. ==== Vessels ==== MLA/2020/00506/R3 Discharged The MMO must be notified in writing of any vessel being used to carry on any licensed activity listed in section 4 of this licence on behalf of the licence holder. Such notification must be received by the MMO no less than 24 hours before the commencement of the licensed activity. Notification must include the master's name, vessel type, vessel IMO number and vessel owner or operating company. A copy of this licence and any subsequent revisions or amendments must be read and understood by the masters of any vessel being used to carry on any licensed activity listed in section 4 of this licence, and that a copy of this licence must be held on board any such vessel. Deadline: No less than 24 hours before the commencement of the licenced activity Date received: 16 Mar 2022 Date discharged: 01 Apr 2022 Licence holder comments * 2 no. 12m*4m flat top barges: Master’s Name: N/A (Not operated plant); Vessel Type: Flat top barge/ pontoon; Vessel IMO: N/A; Vessel Owner: Foyle and Marine Dredging * 1 no. Safety/ Workboat: Master’s Name: Stephen McCormick; Vessel Type: Safety/ Workboat; Vessel IMO: N/A Vessel Owner: Foyle and Marine Dredging; Vessel Owner: Foyle and Marine Dredging ==== HM Coastguard ==== MLA/2020/00506/R4 Discharged HM Coastguard (mailto: zone7@hmcg.gov.uk) must be notified prior to commencement of activities. The MMO must be sent a copy within 7 days of the issue of this notification. Deadline: WIthin 7 days of the issue of this notification Date received: 16 Mar 2022 Date discharged: 01 Apr 2022 Licence holder comments Please see the email attached sent to the HMCG with a notification for the start of works. [[this>Teesworks/Planning/MLA_2020_00506/MLA202000506%20commencement%20of%20activities%20-%20HMCG.msg|MLA202000506 commencement of activities - HMCG.msg]] 64 KB Created By: Miss Erin Snaith 16-MAR-2022 09:24:11 ==== Biosecurity Plan ==== MLA/2020/00506/R5 Discharged A biosecurity plan and ballast water management plan will be developed and implemented for the project. This must be approved by the MMO before the works can commence. Deadline: 6 weeks prior to the works commencing Date received: 12 Jan 2022 Date discharged: 19 Jan 2022 Licence holder comments A biosecurity plan was issued to the MMO to discharge this condition prior to the marine licence formally being issued by the MMO. It is understood that the EA has responded to the MMO to confirm that the biosecurity plan is appropriate and therefore we request that this condition is shown as discharged. ==== UK Hydrographic Office ==== MLA/2020/00506/R6 Discharged A notification of works must be sent to the UK Hydrographic Office at least two weeks prior to the commencement of the works. The MMO must be sent a copy of the notification within 24 hours of issue. Deadline: Within 24 hours of issue Date received: 16 Mar 2022 Date discharged: 01 Apr 2022 Licence holder comments Please see the email attached sent to the UKHO with a notification for the start of works. [[this>Teesworks/Planning/MLA_2020_00506/MLA202000506%20commencement%20of%20activities%20-%20UKHO.msg|MLA202000506 commencement of activities - UKHO.msg]] 94 KB Created By: Miss Erin Snaith 16-MAR-2022 09:25:11 ==== WSI ==== MLA/2020/00506/R7 Discharged An archaeological protocol is submitted to and approved by the MMO, 6 weeks prior to any works commencing, as an archaeological written scheme of investigation (WSI). Deadline: 6 weeks prior to the commencement of any works Date received: 06 Jan 2022 Date discharged: 01 Apr 2022 Licence holder comments The WSI is attached in support of this return. It should be noted that the condition on the marine licence was amended in the final version so that the focus of the WSI and PAD was on the dredging only, rather than 'any works'. Please note this when issuing the report to consultees. [[this>Teesworks/Planning/MLA_2020_00506/PC1084-RHD-SB-EN-RP-EV-1123%20Written%20Scheme%20of%20Investigation.pdf|PC1084-RHD-SB-EN-RP-EV-1123 Written Scheme of Investigation.pdf]] 9 MB Created By: Mr Steven Rayner 06-JAN-2022 17:04:13 ==== Scheme of Monitoring ==== MLA/2020/00506/R8 Responded The dredging activities approved by this licence may not commence until such a time as a scheme of monitoring has been submitted to, and approved in writing by, the Marine Management Organisation. This must be submitted at least 10 weeks prior to the commencement of activities. The scheme shall include: Baseline assessment prior to commencement. Programme to monitor dissolved oxygen levels and turbidity (where appropriate) Programme of post-implementation monitoring. The scheme must be fully implemented and subsequently adhered to, in accordance with the timing/phasing arrangements embodied within the scheme, or any details as may be subsequently agreed, in writing by, the MMO. If it is deemed that any parts of this scheme are no longer required, written representation must be submitted to MMO for written confirmation prior to dredging works commencing. **Subreturns** Ref: R8.1 Rejected: Deadline: 6 weeks prior to the commencement of activities. Date received: 03 Mar 2022: Licence holder comments A scheme of monitoring has been attached in support of this return. The scheme of monitoring also details how dissolved oxygen will be monitored in July and August in relation to condition 5.2.9 **Ref: R8.2 Discharged** Deadline: 31 May 2022 Date received: 18 May 2022 Date discharged: 23 Aug 2022 Licence holder comments Following receipt of comments from Cefas and the Environment Agency, an updated Scheme of Monitoring has been prepared and is attached to this response together with a note responding to the specific consultation comments received. Specifically, the updated Scheme of Monitoring removes reference to monitoring in relation to marine licence condition 5.2.9 (i.e. monitoring within the seasonally restricted months of July-August). [[this>Teesworks/Planning/MLA_2020_00506/PC1084-RHD-SB-EN-NT-EV-1124 Updated Scheme of Monitoring - May 2022.pdf|PC1084-RHD-SB-EN-NT-EV-1124 Updated Scheme of Monitoring - May 2022.pdf]] - 403 KB Created By: Mr Blair Davies 18-MAY-2022 17:27:15 [[this>Teesworks/Planning/MLA_2020_00506/PC1084-RHD-SB-EN-NT-EV-1127 MLA.2020.00506.R8 Response to Consultation Comments on Scheme of Monitoring.pdf|PC1084-RHD-SB-EN-NT-EV-1127 MLA.2020.00506.R8 Response to Consultation Comments on Scheme of Monitoring.pdf]] - 253 KB Created By: Mr Blair Davies 18-MAY-2022 17:27:58 ==== Bathymetric Surveys ==== MLA/2020/00506/R9 Open Pre and post bathymetric dredge surveys must be submitted, together with an interpretation of the difference between the survey results and a volume calculation within 4 weeks of completion of each dredge campaign. **Subreturns** Ref: R9.1 Open; Deadline; Within 4 weeks of completion of each dredge campaign Ref: R9.2 Open; Deadline; Within 4 weeks of completion of each dredge campaign Ref: R9.3 Open; Deadline; Within 4 weeks of completion of each dredge campaign ===== Associated applications and consents ===== [[MLA-2020-00507|MLA/2020/00507]]/2 [[ENQ-2021-00205|ENQ/2021/00205]] ===== Original Sampling Spreadsheets ===== [[this>Teesworks/Planning/MLA_2020_00506/Sampling/MLA_2020_00506-MMO Results_Template MAR00356_1 V2-1.xlsx|MLA_2020_00506-MMO Results_Template MAR00356_1 V2-1.xlsx]] [[this>Teesworks/Planning/MLA_2020_00506/Sampling/MLA_2020_00506-MMO Results_Template MAR00356_1 V2-6.xlsx|MLA_2020_00506-MMO Results_Template MAR00356_1 V2-6.xlsx]] [[this>Teesworks/Planning/MLA_2020_00506/Sampling/MLA_2020_00506-MMO Results_Template MAR00356_2 V2-2.xlsx|MLA_2020_00506-MMO Results_Template MAR00356_2 V2-2.xlsx]] [[this>Teesworks/Planning/MLA_2020_00506/Sampling/MLA_2020_00506-MMO Results_Template MAR00356_2 V2-7.xlsx|MLA_2020_00506-MMO Results_Template MAR00356_2 V2-7.xlsx]] [[this>Teesworks/Planning/MLA_2020_00506/Sampling/MLA_2020_00506-MMO_Results_Template - MAR00825 Interim 2-20.xlsx|MLA_2020_00506-MMO_Results_Template - MAR00825 Interim 2-20.xlsx]] [[this>Teesworks/Planning/MLA_2020_00506/Sampling/MLA_2020_00506-MMO_Results_Template - MAR00825 Interim 2-21.xlsx|MLA_2020_00506-MMO_Results_Template - MAR00825 Interim 2-21.xlsx]] [[this>Teesworks/Planning/MLA_2020_00506/Sampling/MLA_2020_00506-MMO_Results_Template - MAR00825_with coords-27.xlsx|MLA_2020_00506-MMO_Results_Template - MAR00825_with coords-27.xlsx]] [[this>Teesworks/Planning/MLA_2020_00506/Sampling/MLA_2020_00506-MMO_Results_Template - MAR00825_with coords-35.xlsx|MLA_2020_00506-MMO_Results_Template - MAR00825_with coords-35.xlsx]] [[this>Teesworks/Planning/MLA_2020_00506/Sampling/MLA_2020_00506-MMO_Results_Template - MAR00829 Interim (1)-24.xlsx|MLA_2020_00506-MMO_Results_Template - MAR00829 Interim (1)-24.xlsx]] [[this>Teesworks/Planning/MLA_2020_00506/Sampling/MLA_2020_00506-MMO_Results_Template - MAR00829 Interim-17.xlsx|MLA_2020_00506-MMO_Results_Template - MAR00829 Interim-17.xlsx]] [[this>Teesworks/Planning/MLA_2020_00506/Sampling/MLA_2020_00506-MMO_Results_Template - MAR00829_with coords-28.xlsx|MLA_2020_00506-MMO_Results_Template - MAR00829_with coords-28.xlsx]] [[this>Teesworks/Planning/MLA_2020_00506/Sampling/MLA_2020_00506-MMO_Results_Template - MAR00829_with coords-36.xlsx|MLA_2020_00506-MMO_Results_Template - MAR00829_with coords-36.xlsx]] [[this>Teesworks/Planning/MLA_2020_00506/Sampling/MLA_2020_00506-MMO_Results_Template - MAR00856 Interim 2-18.xlsx|MLA_2020_00506-MMO_Results_Template - MAR00856 Interim 2-18.xlsx]] [[this>Teesworks/Planning/MLA_2020_00506/Sampling/MLA_2020_00506-MMO_Results_Template - MAR00856 Interim 2-23.xlsx|MLA_2020_00506-MMO_Results_Template - MAR00856 Interim 2-23.xlsx]] [[this>Teesworks/Planning/MLA_2020_00506/Sampling/MLA_2020_00506-MMO_Results_Template - MAR00856_with coords-29.xlsx|MLA_2020_00506-MMO_Results_Template - MAR00856_with coords-29.xlsx]] [[this>Teesworks/Planning/MLA_2020_00506/Sampling/MLA_2020_00506-MMO_Results_Template - MAR00856_with coords-37.xlsx|MLA_2020_00506-MMO_Results_Template - MAR00856_with coords-37.xlsx]] [[this>Teesworks/Planning/MLA_2020_00506/Sampling/MLA_2020_00506-MMO_Results_Template - MAR00874 Interim-19.xlsx|MLA_2020_00506-MMO_Results_Template - MAR00874 Interim-19.xlsx]] [[this>Teesworks/Planning/MLA_2020_00506/Sampling/MLA_2020_00506-MMO_Results_Template - MAR00874 Interim-22.xlsx|MLA_2020_00506-MMO_Results_Template - MAR00874 Interim-22.xlsx]] [[this>Teesworks/Planning/MLA_2020_00506/Sampling/MLA_2020_00506-MMO_Results_Template - MAR00874_with coords-30.xlsx|MLA_2020_00506-MMO_Results_Template - MAR00874_with coords-30.xlsx]] [[this>Teesworks/Planning/MLA_2020_00506/Sampling/MLA_2020_00506-MMO_Results_Template - MAR00874_with coords-38.xlsx|MLA_2020_00506-MMO_Results_Template - MAR00874_with coords-38.xlsx]] ===== Separated Location Spreadsheets from Original Sampling ===== [[this>Teesworks/Planning/MLA_2020_00506/Sampling/BH-08.xlsx|BH-08.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/BH-09.xlsx|BH-09.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/BH-10.xlsx|BH-10.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/BH-11.xlsx|BH-11.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/BH-12.xlsx|BH-12.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/BH-13.xlsx|BH-13.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/BH-30.xlsx|BH-30.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/BH-31.xlsx|BH-31.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/BH-32.xlsx|BH-32.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/BH-33.xlsx|BH-33.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/BH-34.xlsx|BH-34.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/A1.xlsx|A1.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/A2.xlsx|A2.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/A3.xlsx|A3.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/A4.xlsx|A4.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/B1.xlsx|B1.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/B2.xlsx|B2.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/B3.xlsx|B3.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/B4.xlsx|B4.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/B5.xlsx|B5.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/B6.xlsx|B6.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/C1.xlsx|C1.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/C2.xlsx|C2.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/C3.xlsx|C3.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/C4.xlsx|C4.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/C5.xlsx|C5.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/C6.xlsx|C6.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/C7.xlsx|C7.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/C8.xlsx|C8.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/C9.xlsx|C9.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/C10.xlsx|C10.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/C11.xlsx|C11.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/C12.xlsx|C12.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/D1.xlsx|D1.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/D2.xlsx|D2.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/D3.xlsx|D3.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/E1.xlsx|E1.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/E2.xlsx|E2.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/E3.xlsx|E3.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/E4.xlsx|E4.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/E5.xlsx|E5.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/F1.xlsx|F1.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/G1.xlsx|G1.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/G2.xlsx|G2.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/G3.xlsx|G3.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/G4.xlsx|G4.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/G5.xlsx|G5.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/G6.xlsx|G6.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/VC-01.xlsx|VC-01.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/VC-02.xlsx|VC-02.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/VC-03.xlsx|VC-03.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/VC-04.xlsx|VC-04.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/VC-05.xlsx|VC-05.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/VC-06.xlsx|VC-06.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/VC-07.xlsx|VC-07.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/VC-08B.xlsx|VC-08B.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/VC-09.xlsx|VC-09.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/VC-10.xlsx|VC-10.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/VC-11.xlsx|VC-11.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/VC-12.xlsx|VC-12.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/VC-13.xlsx|VC-13.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/VC-14.xlsx|VC-14.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/VC-15A.xlsx|VC-15A.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/VC-16.xlsx|VC-16.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/VC-17.xlsx|VC-17.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/VC-18.xlsx|VC-18.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/VC-19.xlsx|VC-19.xlsx]], [[this>Teesworks/Planning/MLA_2020_00506/Sampling/VC-20.xlsx|VC-20.xlsx]]