Tees CCPP

What happens next

A decision on the application for a Development Consent Order for Tees CCPP was taken on 05 April 2019 and has now been issued.

The period for legal challenge is defined in s118 of the Planning Act 2008. Further information about legal challenge can be found in the letter sent to all Interested Parties accompanying the Secretary of State’s decision and statement of reasons.

If you have any queries about the process please email the Planning Inspectorate at [email protected] or telephone the helpline on 0303 444 5000.

Timeline (42 items)

05 April 2019
Decision made by the Secretary of State
05 April 2019

Sembcorp Utilities (UK) Limited (Applicant) has responded to The Secretary of State for Business, Energy and Industrial Strategy’s request for further comments.

18 March 2019

The  Environment Agency and Sembcorp Utilities (UK) Limited (Applicant) have responded to The Secretary of State for Business, Energy and Industrial Strategy’s request for further comments.

25 February 2019
Recommendations given by the Planning Inspectorate
10 January 2019

An Additional submission from the Applicant has been accepted at the discretion of the Examining Authority on Wednesday 10 October 2018.

11 October 2018

An additional submission from the National Grid has been accepted at the discretion of the Examining Authority.

10 October 2018

An additional submission from the Applicant has been accepted at the discretion of the Examination Authority.

08 October 2018
05 October 2018

The Examining Authority has accepted two late submissions from the applicant for deadline 7.

28 September 2018
27 September 2018

An additional submission from the Environment Agency has been accepted at the discretion of the Examination Authority.

14 September 2018

An additional submission from the Environment Agency has been accepted at the discretion of the Examination Authority.

31 August 2018
23 August 2018

The Examining Authority has accepted a late submission from Natural England for deadline 5.

21 August 2018

The submissions for deadline 5 have been published.

10 August 2018
24 July 2018

The responses received for Deadline 4 (6 July 2018) have now been published.

10 July 2018

The Examination Authority has accepted the non-material change consultation report as an additional submission from the applicant.

29 June 2018
18 June 2018

The Examination Authority has issued a Rule 17 Letter requesting comments on the Deadline 2 Submission from the Applicant that was omitted from publication on 29 May 2018.

08 June 2018

The Accompanied Site Inspection Itinerary and Agendas for Hearings in June 2018 have been published. Please note that the date reserved for the Open Floor Hearing on the evening of 13 June 2018 is not taking place as we have received no requests for one to be held.

05 June 2018

The responses received for Deadline 3 (29 May 2018) have now been published.

31 May 2018
22 May 2018
01 May 2018

Read the letter

The Examination Timetable (Rule 8 letter) has been sent to Interested Parties

Procedural decision following Preliminary Meeting

18 April 2018
  • Preliminary Meeting takes place
  • Examination begins
10 April 2018

The notification of Preliminary Meeting (Rule 6 letter) has been sent Read the letter

The letter also includes the draft Examination Timetable and Initial Assessment of Principal Issues.

09 March 2018
Relevant representations published on the website
14 February 2018
Registration of interested parties closes
09 February 2018
Registration of interested parties begins
11 January 2018
Read the letter

The application has been accepted for examination

18 December 2017
Decision on whether or not to accept the application for examination
18 December 2017

This application was received by the Planning Inspectorate on 22 November 2017.

The application documents will be made available if the application is accepted for examination.

It is for the applicant to decide whether or not application documents can be published upon submission (see DCLG pre-application https://www.gov.uk/government/publications/guidance-on-the-pre-application-process-for-major-infrastructure-projects)

23 November 2017
Application received by the Planning Inspectorate
22 November 2017