Case DetailsProject Type Project TitleLocations Applicant NameSubmission DateDecision Date
MLA/2014/00001 - CompletedApplication - Construction, Removals (inc. Grab Samples) Marina Repairs Suffolk Yacht Harbour 03 Jan 201416 Apr 2014
MLA/2014/00002/1 - CompletedApplication - Emergency Work Fort Blockhouse - Emergency Sea Wall Rpairs Defence Infrastructure Organisation 03 Jan 201431 Jan 2014
MLA/2014/00003/4 - CompletedApplication - Dredged Material DisposalSoveregn Harbour Disposal of Dredged Material Premier Marinas (Eastbourne) Limited06 Jan 201402 Jun 2021
MLA/2014/00004/5 - CompletedApplication - Dredged Material Disposal, DredgingSPARKES MARINA MAINTENANCE DREDGING Marina Developments Limited 06 Jan 201421 Nov 2017
MLA/2014/00005 - CompletedApplication - Dredged Material DisposalHumber Gateway OWF - Offshore Substation Grouped under: Humber Gateway Offshore Wind Farm Showing 5 of 10 cases E.On Climate & Renewables Uk Humber Wind Limited06 Jan 201415 Apr 2014
MLA/2014/00007 - CompletedApplication - Emergency Work Siddick Sea Wall J. Murphy & Sons Limited08 Jan 201409 Jan 2014
MLA/2014/00009 - CompletedApplication - Emergency Work Flimby J. Murphy & Sons Limited09 Jan 201410 Jan 2014
MLA/2014/00010/1 - CompletedApplication - Emergency Work Millendreath beach storm sand clearance Espalier Developments (Millendreath) Limited09 Jan 201407 Feb 2014
MLA/2014/00011 - CompletedApplication - Construction Sands Lane, Bridlington - Outfall Pipe Yorkshire Water Limited 10 Jan 201424 Jan 2014
MLA/2014/00012/1 - CompletedApplication - Construction 251 - Durkan Ltd - Greenwich Wharf - Phase 1 Abwood Contract Support Limited 10 Jan 201402 Apr 2014
MLA/2014/00013 - CompletedApplication - Emergency Work Eastern Green,Penzance-Emergency revetment refurbishment works Cornwall Council14 Jan 201405 Feb 2014
MLA/2014/00014 - CompletedApplication - Construction Bradfords Quay Bradfords Quay Limited14 Jan 201409 Apr 2014
MLA/2014/00016 - CompletedApplication - Construction Pipeline for the reclamation of Liverpool2 Van Oord Dredging (Uk) Ltd15 Jan 201414 Mar 2014
MLA/2014/00017 - WithdrawnApplication - Construction Replacement seawall, hard standing and slipway Pasco'S Boatyard15 Jan 2014
MLA/2014/00018 - CompletedApplication - Emergency Work Nethertown J. Murphy & Sons Limited16 Jan 201417 Jan 2014
MLA/2014/00019/4 - CompletedApplication - Construction BT Fibre Optic Telecommunications Cables, The Solent RP_Cable, RPL_Cable, Portsmouth Harbour British Telecommunications Public Limited Company 16 Jan 201416 Sep 2016
MLA/2014/00020 - CompletedApplication - Construction Colley Lane Southern access Road, Bridgwater, Somerset (CLSAR) Somerset Bridge, Bridgwater, Somerset Somerset County Council 17 Jan 201429 Sep 2014
MLA/2014/00022/2 - CompletedApplication - Construction coast protection scheme , hopton on sea Bourne Leisure17 Jan 201431 Oct 2014
MLA/2014/00023 - CompletedApplication - Construction Brus Culvert Outfall remedial works Northumbrian Water Limited17 Jan 201413 Mar 2014
MLA/2014/00024 - CompletedApplication - Removals (inc. Grab Samples) CF046 Portland Bill SPS Outfall Repairs Wessex Water Limited20 Jan 201425 Mar 2014
MLA/2014/00025 - CompletedApplication - Construction Emergency Repair to Clevedon Sea Front Slip Way North Somerset Council21 Jan 201424 Jan 2014
MLA/2014/00026 - CompletedApplication - Emergency Work Caffa Mill SPS - cladding removal South West Water Limited21 Jan 201424 Jan 2014
MLA/2014/00027/7 - CompletedApplication - Construction Walney Offshore Wind Farm Operational Marine Licence - Phase 2 Export Cable Blue Transmission Walney 2 (Holdings) Limited 22 Jan 201401 Dec 2016
MLA/2014/00028/7 - CompletedApplication - Construction Walney Offshore Wind Farm Operational Marine Licence - Phase 1 Export Cable Blue Transmission Walney 1 (Holdings) Limited 22 Jan 201426 Jun 2024
MLA/2014/00030 - CompletedApplication - Construction Severn Outfalls - 4 sites Environment Agency - Midlands Region23 Jan 201424 Mar 2014
MLA/2014/00031 - CompletedApplication - Construction Gunfleet Sands Offshore Wind Farm Export Cable Grouped under: Gunfleet Sands OWF 1, 2, 3 Showing 3 of 15 cases GFS Export Cable OSS to Kp7.2 Tc Gunfleet Sands Ofto Limited23 Jan 201405 Mar 2015
MLA/2014/00032 - CompletedApplication - Construction Friarage - Surface Water Outfall Housing Hartlepool24 Jan 201427 Jun 2014
MLA/2014/00033/2 - CompletedApplication - Miscellaneous Disposal Operation Whale Big Wave Productions Limited24 Jan 201420 Aug 2015
MLA/2014/00034 - CompletedApplication - Construction Sandquay Slipway Repairs, BRNC Dartmouth Mr Stephen Bell 24 Jan 201425 Mar 2014
MLA/2014/00035 - CompletedApplication - Construction Dock Wall Repairs, Eagle Wharf, Ipswich Persimmon Homes Limited 27 Jan 201409 May 2014
MLA/2014/00038/2 - CompletedApplication - Construction Dolphin Quay Repair and Replacement, Dolphin Quays (North Shields) Ltd. Brannen And Partners28 Jan 201430 Jun 2015
MLA/2014/00041/3 - CompletedApplication - Construction Licence for two Yacht Racing Marker Buoys Arun Yacht Club Limited(The)29 Jan 201406 May 2014
MLA/2014/00042/1 - CompletedApplication - Emergency Work Seaton Sand Wall Emergency Works Cornwall Council30 Jan 201407 Feb 2014
MLA/2014/00044/1 - CompletedApplication - Construction, Removals (inc. Grab Samples) Tynemouth Outfall remediation work Northumbrian Water Limited31 Jan 201429 Apr 2014
MLA/2014/00045 - CompletedApplication - Construction Consrtruction of a New Jetty at 56 Pearce Avenue, Poole (APP13/01311/F) Dr Stephen Wood 31 Jan 201427 Mar 2014
MLA/2014/00046 - WithdrawnApplication - Emergency Work Port Solent Marina Dangerous Pile Premier Marinas Limited 03 Feb 2014
MLA/2014/00048 - CompletedApplication - Emergency Work Folkestone Warren Emergency Works Network Rail (Assets) Limited 03 Feb 201407 Feb 2014
MLA/2014/00050 - CompletedApplication - Dredging, Miscellaneous Disposal Desilting of sluice exit South Hall creek William Cullen Farms03 Feb 201430 Apr 2014
MLA/2014/00051 - CompletedApplication - Construction Babbacombe Pier Pontoon The Cary Arms 04 Feb 201402 May 2014
MLA/2014/00052 - CompletedApplication - Emergency Work Clovelly pumping station - emergency support South West Water Limited04 Feb 201404 Feb 2014
MLA/2014/00053 - CompletedApplication - Renewables Dudgeon CPT & BH Campaign Dudgeon Offshore Wind Limited 04 Feb 201407 Mar 2014
MLA/2014/00054/10 - Completed Application - Renewables Oceanus 2 Device at Wave Hub Seatricity Limited05 Feb 201430 Jul 2018
MLA/2014/00055 - CompletedApplication - Construction Rock armour maintenance work at Caldy Golf Club Caldy Golf Club 05 Feb 201424 Apr 2014
MLA/2014/00056 - CompletedApplication - Dredging ADM Erith Ltd Capital dredge Archer Daniels Midland Erith Limited06 Feb 201411 Jul 2014
MLA/2014/00057 - CompletedApplication - Construction Queenborough Harbour, new mooring pontoon Queenborough Yacht Club 06 Feb 201406 May 2014
MLA/2014/00058 - CompletedApplication - Construction, Removals (inc. Grab Samples) Bradwell Slipway Refurbishment Fred Van Der Tuijn07 Feb 201428 Apr 2014
MLA/2014/00059 - CompletedApplication - Construction Canvey Island Tidal Pool Castlemore Securities Limited 07 Feb 201404 Jul 2014
MLA/2014/00060 - CompletedApplication - Emergency Work Siddick/Flimby Emergency J. Murphy & Sons Limited07 Feb 201407 Feb 2014
MLA/2014/00062/3 - CompletedApplication - Removals (inc. Grab Samples) 1 Mbbl Crude Import Project - MSI Application Esso Petroleum Company,Limited07 Feb 201412 Jun 2014
MLA/2014/00063 - CompletedApplication - Emergency Work Dawlish Warren Sea Wall Network Rail07 Feb 201407 Feb 2014
MLA/2014/00064 - CompletedApplication - Removals (inc. Grab Samples) Cambois Outfall Pile Removal Northumbrian Water Limited07 Feb 201424 Mar 2014
MLA/2014/00065/2 - CompletedApplication - Construction, Dredged Material Disposal, DredgingHowdon Yard, Willington Quay, Wallsend Howdon Quay, Howdon Yard, Souter Point Outer, NORTH TYN (TY070) Port Of Tyne Public Limited Company 10 Feb 201410 Nov 2016
MLA/2014/00067 - CompletedApplication - Construction Portishead RNLI Lifeboat Station Rnli10 Feb 201407 Apr 2014
MLA/2014/00068 - CompletedApplication - Construction A12 Blythburgh Flood Alleviation Scheme Suffolk County Council10 Feb 201419 May 2014
MLA/2014/00069/4 - CompletedApplication - Dredged Material DisposalDisposal of Dredge MaterialSUNDERLAND (TY090)Port Of Sunderland11 Feb 201403 Apr 2018
MLA/2014/00070/1 - CompletedApplication - Construction Yacht Racing Marker Buoys Rye Harbour Sailing Club12 Feb 201411 Oct 2017
MLA/2014/00071/3 - CompletedApplication - Construction Slipway extension - Stokes Bay, Gosport Gosport Borough Council 13 Feb 201415 Jul 2015
MLA/2014/00072/2 - CompletedApplication - Removals (inc. Grab Samples) Monktonmead Brook - Removal of Sand from 'Ryde East Sands' Environment Agency (Southern Region)13 Feb 201423 Oct 2014
MLA/2014/00075/1 - CompletedApplication - Construction Commisioners Quay, Quay Road, Blyth Arch (Corporate Holdings) Limited 14 Feb 201420 May 2014
MLA/2014/00076 - CompletedApplication - Renewables TidalStream Scale model testing at Carrick Roads Mojo Maritime Limited 14 Feb 201426 Mar 2014
MLA/2014/00077 - CompletedApplication - Emergency Work St Michael's Mount Storm Damage Grouped under: St Aubyn Estate Showing 4 of 7 cases St Aubyn Estates17 Feb 201417 Feb 2014
MLA/2014/00078/2 - CompletedApplication - Dredged Material DisposalAnnual Dredging Reedham Marina Reedham Marina [2] (HU159)Reedham Marina Ltd17 Feb 201425 Mar 2020
MLA/2014/00080 - CompletedApplication - Construction NOS Bridges Repairs - Phase 2 - Channelsea Bridge Optimise17 Feb 201416 Apr 2014
MLA/2014/00081/3 - CompletedApplication - Dredging Navigator Terminal Thames Berth Dredging Grouped under: VOPAK TERMINAL LONDON B.V. LIMITED Showing 3 of 6 cases Navigator Terminals Thames B.V. Ltd.18 Feb 201431 Jul 2024
MLA/2014/00082 - WithdrawnApplication - Dredged Material Disposal, DredgingAble Seaton Port Holding Basin partial deepening Ableuk.Ltd19 Feb 2014
MLA/2014/00084 - CompletedApplication - Construction Proposed Slipway at 54 Pearce Avenue, Poole Mr Hugh Roper 21 Feb 201430 Apr 2014
MLA/2014/00085 - CompletedApplication - Burial at Sea Mr Charles Lister 25 Feb 201427 Feb 2014
MLA/2014/00088/3 - CompletedApplication - Construction Navigation Marker Framework United Utilities Water Plc26 Feb 201410 Jul 2024
MLA/2014/00089 - CompletedApplication - Emergency Work Beesands - Rock armour works South Hams District Council 26 Feb 201428 Feb 2014
MLA/2014/00091/1 - CompletedApplication - Construction Jetty Repair and Maintenance Grouped under: VOPAK TERMINAL LONDON B.V. LIMITED Showing 3 of 6 cases Vopak Terminal London B.V. Limited27 Feb 201426 Aug 2014
MLA/2014/00092 - CompletedApplication - Miscellaneous Disposal Dawlish Sea Cliff spoil removal Network Rail Infrastructure Limited 27 Feb 201428 Feb 2014
MLA/2014/00096/1 - CompletedApplication - Construction, Removals (inc. Grab Samples) Proposed boat park and petrol storage tank Bembridge Sailing Club28 Feb 201403 Jun 2015
MLA/2014/00097/1 - CompletedApplication - Construction, Dredging, Removals (inc. Grab Samples) Carnsew Sluicing Channel, Tunnels and wall repairs Bowmer And Kirkland Limited 28 Feb 201416 Feb 2017
MLA/2014/00099 - CompletedApplication - Construction Foxfield Viaduct Story Contracting Limited 03 Mar 201430 Apr 2014
MLA/2014/00100/4 - CompletedApplication - Construction, Dredged Material Disposal, Dredging, Removals (inc. Grab Samples)TETNEY SEA-LINE REPLACEMENT PROJECT Crude Oil Terminals (Humber) Limited03 Mar 201416 Oct 2015
MLA/2014/00101 - CompletedApplication - Dredging Fleetwood RNLI Lifeboat pen, River Wyre plough dredge Fairway Clearance And Harbour Services Limited03 Mar 201408 Sep 2016
MLA/2014/00102/3 - CompletedApplication - Dredged Material Disposal, DredgingWhitstable Harbour DredgingWhitstable Harbour, WHITSTABLE C (TH073)Canterbury City Council 04 Mar 201415 Oct 2021
MLA/2014/00103 - CompletedApplication - Emergency Work Towan Beach Promenade Sea Defence Temporary Protection Works Cornwall Council05 Mar 201410 Mar 2014
MLA/2014/00104/1 - CompletedApplication - Construction Trippets Wall, Bosham West Sussex County Council05 Mar 201419 Jun 2014
MLA/2014/00105 - CompletedApplication - Construction Seaham North Pier Repair and Restoration Seaham North Pier Durham County Council 05 Mar 201416 Sep 2014
MLA/2014/00106/5 - CompletedApplication - Dredged Material Disposal, DredgingFowey Harbour Maintenance Dredging Fowey Harbour Commissioners 06 Mar 201407 Jun 2018
MLA/2014/00108/1 - CompletedApplication - Construction 62 Pearce Avenue Poole BH14 8EH Parsons And Joyce 07 Mar 201402 Jun 2014
MLA/2014/00109 - CompletedApplication - Construction Dagenham Jetty upgrade for Cemex UK Cemex Uk07 Mar 201427 Jun 2014
MLA/2014/00110 - CompletedApplication - Construction Boathouse 4 Portsmouth Naval Base Property Trust10 Mar 201413 Jun 2014
MLA/2014/00111 - CompletedApplication - Emergency Work Sovereign Harbour Navigational Hazard at the entrance Premier Marinas (Eastbourne) Limited10 Mar 201412 Mar 2014
MLA/2014/00112 - CompletedApplication - Miscellaneous Disposal Dawlish (Woodland Avenue landslide) Network Rail Infrastructure Limited 10 Mar 201411 Mar 2014
MLA/2014/00113 - CompletedApplication - Construction Wheatcroft Cascade - Repair Works Grouped under: Wheatcroft Long Sea Outfall Showing 2 of 7 cases Yorkshire Water Limited 11 Mar 201414 May 2014
MLA/2014/00114 - CompletedApplication - Construction Proposed Swinging Mooring Mr Shaun Smith11 Mar 201416 Apr 2014
MLA/2014/00115 - CompletedApplication - Construction Landing Berths Grouped under: Master case for construction of ladder Hartlepool Quay Showing 2 of 2 cases Hartlepool Fishco Ltd 11 Mar 201409 May 2014
MLA/2014/00116/2 - CompletedApplication - Construction Town Bridge, Bridgwater Somerset County Council 12 Mar 201411 Dec 2014
MLA/2014/00117/2 - CompletedApplication - Miscellaneous Disposal Greentide May 14 Oil Spill Response Limited14 Mar 201428 Oct 2014
MLA/2014/00118/2 - CompletedApplication - Construction BDUK BT PLC Subsea Telecoms Cable Scilly Islands British Telecommunications Public Limited Company 14 Mar 201429 Sep 2014
MLA/2014/00119/1 - CompletedApplication - Renewables PLAT-O Prototype - Initial trials at Yarmouth Grouped under: PLAT-O Prototype - Testing at Yarmouth Showing 3 of 3 cases Sustainable Marine Energy Limited 14 Mar 201407 Aug 2014
MLA/2014/00120 - CompletedApplication - Construction Seahouses Outfall Remedial Works Outfall upstream, Outfall downstream, Access routeNorthumbrian Water Limited17 Mar 201421 Nov 2014
MLA/2014/00121/2 - CompletedApplication - Construction Perranporth beach emergency river bank repairs Cormac Solutions Limited17 Mar 201428 Apr 2014
MLA/2014/00124/2 - CompletedApplication - Construction Sandsend Coastal Defence North Yorkshire County Council18 Mar 201416 Dec 2015
MLA/2014/00125/2 - CompletedApplication - Construction Exmouth Pier Head Sea Wall Improvements and Repairs Exmouth Dock Co 18 Mar 201411 Mar 2015
MLA/2014/00126/4 - CompletedApplication - Dredging Maintenance Dredging at Thames Oilport Morzine all sites Morzine Limited 19 Mar 201423 Mar 2020
MLA/2014/00128 - CompletedApplication - Construction, Removals (inc. Grab Samples) Hartopp Road Outfall Flap Valve Replacement South West Water Limited21 Mar 201414 May 2014
MLA/2014/00129/1 - CompletedApplication - Construction Pontoon Installations, Town Quay, Poole Poole Harbour Commissioners 21 Mar 201418 Jun 2014
MLA/2014/00130/1 - CompletedApplication - Construction Essex Yacht Club Environmental Improvement Scheme Essex Yacht Club21 Mar 201401 Oct 2014
MLA/2014/00132 - CompletedApplication - Dredging Routine dredging Custom Hse Gravesendpontoon (Thames)Customs Pontoon, Gravesend, Kent. Uk Border Force 24 Mar 201403 Dec 2014
MLA/2014/00133/3 - CompletedApplication - Miscellaneous Disposal AirSAR Aerospace Resources Ltd 25 Mar 201427 Oct 2014
MLA/2014/00134/3 - CompletedApplication - Construction Anchorsholme and Harrowside Site Investigation Work United Utilities Plc25 Mar 201429 Sep 2014
MLA/2014/00135/2 - CompletedApplication - Construction Ryde Canoe Lake Outfall Alterations Isle Of Wight Council 26 Mar 201423 Oct 2014
MLA/2014/00136/1 - CompletedApplication - Construction Alabama Way Marine Operations Facility Alabama Way Cammell Laird Shiprepairers & Shipbuilders Limited26 Mar 201428 May 2015
MLA/2014/00138 - CompletedApplication - Construction Hawkins Point Flood Defence Repairs Carter Jonas Llp26 Mar 201425 Jul 2014
MLA/2014/00139/1 - CompletedApplication - Miscellaneous Disposal Comparative Proof and Sentencing Conditions Qinetiq Mod Eskmeals26 Mar 201429 May 2014
MLA/2014/00141/5 - CompletedApplication - Aggregate Dredging, Removals (inc. Grab Samples) Area 515 Westminster Gravels Limited 27 Mar 201408 Dec 2021
MLA/2014/00143/3 - CompletedApplication - Removals (inc. Grab Samples) Dismantling, Demolition of Redundant No.1 Jetty at Sabic Petrochemicals UK Sabic Uk Petrochemicals Limited 27 Mar 201428 Apr 2016
MLA/2014/00144 - CompletedApplication - Construction Eastern Area Navigation MarkersWells next the Sea, Eccles to Winterton, Happisburg to Winterton, Waxham, Winterton, Southwold, Minsmere Outfall, Thorpness Sluice, Aldeburgh, Felixstowe Ferry, Felixstowe Town, Horsey Island, West Clacton, Jaywick, Brooklands, Jaywick, Seawick, Point Clear, Brightlingsea, Holland, Colne Barrier, St. Lawrence, Bradwell, Sales Point, Dengie, Deal Hall, Dengie, Holliwell Point, BurnhamEnvironment Agency - Anglian Region 28 Mar 201420 Oct 2014
MLA/2014/00145/1 - CompletedApplication - Dredged Material Disposal, DredgingSeaways Creek Plough Operation Seaways Creek Mr Michael Hobson 31 Mar 201414 Oct 2014
MLA/2014/00146/2 - CompletedApplication - Construction, Removals (inc. Grab Samples) Swan Hunter Quay Wall RepairsSwan Hunter Quay Wall, Wallsend [1] North Tyneside Council01 Apr 201423 Dec 2015
MLA/2014/00147/1 - CompletedApplication - Construction the Jetty-Project - Cone Tyne And Wear Building Preservation Trust Limited 01 Apr 201416 Jun 2014
MLA/2014/00149 - CompletedApplication - Construction Shellfish storage pontoon Wm Henry & Son01 Apr 201424 Jun 2014
MLA/2014/00150/1 - CompletedApplication - Construction Storm Repairs at Molojo, Restronguet Point. Mr Andy Harrison01 Apr 201420 Aug 2014
MLA/2014/00151 - CompletedApplication - Emergency Work Lympstone Foreshore sewer clearance and manhole replacement South West Water Limited03 Apr 201407 Apr 2014
MLA/2014/00152 - CompletedApplication - Construction Private Jetty95 Mudeford, Christchurch, Dorset.Mr Barry Van Danzig 03 Apr 201425 Aug 2015
MLA/2014/00153 - CompletedApplication - Emergency Work Portloe Sewer outfall South West Water Limited04 Apr 201408 Apr 2014
MLA/2014/00154 - CompletedApplication - Construction Tyne Tanker Berth, C1 Repairs and Bollard Upgrades (2014) Port Of Tyne Authority04 Apr 201411 Jun 2014
MLA/2014/00155/3 - CompletedApplication - Construction Barrow Offshore Wind Farm Operational Marine Licence - Array Cable Repair Barrow Offshore Wind Limited08 Apr 201408 Mar 2018
MLA/2014/00156/3 - CompletedApplication - Construction Gunfleet Sands I & II Offshore Wind Farm Operational Marine Licence - Array Grouped under: Gunfleet Sands OWF 1, 2, 3 Showing 3 of 15 cases Orsted08 Apr 201427 May 2020
MLA/2014/00158 - CompletedApplication - Construction 10 moorings for private pleasure boats and small pontoon on tidal creek T&S Nurseries 08 Apr 201402 Oct 2015
MLA/2014/00159/2 - CompletedApplication - Renewables Gunfleet Sands (OFTO) Remedial Works Grouped under: Gunfleet Sands OWF 1, 2, 3 Showing 3 of 15 cases Tc Gunfleet Sands Ofto Limited08 Apr 201420 Mar 2015
MLA/2014/00160 - CompletedApplication - Burial at Sea Mr Charles Lister 08 Apr 201411 Apr 2014
MLA/2014/00162/1 - CompletedApplication - Construction Repairs and Maintenance to Dunston Staiths Tyne And Wear Building Preservation Trust Limited 09 Apr 201413 Oct 2014
MLA/2014/00163 - CompletedApplication - Dredged Material DisposalHumber Gateway Offshore Wind Farm - Drill Arising Disposal Grouped under: Humber Gateway Offshore Wind Farm Showing 5 of 10 cases E.On Climate & Renewables Uk Humber Wind Limited09 Apr 201420 Jun 2014
MLA/2014/00164 - CompletedApplication - Construction Roa Island Jetty Reconstruction Barrow Borough Council11 Apr 201412 Aug 2014
MLA/2014/00165/1 - CompletedApplication - Emergency Work Hopton on Sea coast protection Mr Alastair Tindle11 Apr 201423 Apr 2014
MLA/2014/00166 - CompletedApplication - Construction Metropolitan Police Service - Wapping Boat Yard and Police Station Wapping, London Metropolitan Police Service 11 Apr 201430 Apr 2015
MLA/2014/00167/2 - CompletedApplication - Construction Leamouth North City Island Ballymore Properties Ltd14 Apr 201404 Nov 2015
MLA/2014/00168/1 - CompletedApplication - Emergency Work Whitby Harbour - Bank Stabilisation Works Yorkshire Water Services Limited14 Apr 201409 Jun 2014
MLA/2014/00169/1 - CompletedApplication - Construction North Headland Hartlepool outfall remedial works Northumbrian Water Limited14 Apr 201402 Jul 2014
MLA/2014/00170/2 - CompletedApplication - Construction Tees (Newport) Bridge Painting Stockton-On-Tees Borough Council15 Apr 201428 Jan 2015
MLA/2014/00171/2 - CompletedApplication - Construction Lepe sea wall repairs additional repairs Hampshire County Council15 Apr 201407 Oct 2014
MLA/2014/00172 - CompletedApplication - Burial at Sea Mr Steven Tapper15 Apr 201423 Apr 2014
MLA/2014/00173 - CompletedApplication - Construction South Milton Sands Slipway National Trust Plc15 Apr 201420 Jun 2014
MLA/2014/00174 - CompletedApplication - Construction HOLBEACH RIVER SLUICE REFURBISHMENT South Holland Drainage Board15 Apr 201430 Jun 2014
MLA/2014/00175 - CompletedApplication - Construction Rochester WTS Riverside Works Viridor Waste Management16 Apr 201429 Aug 2014
MLA/2014/00177 - CompletedApplication - Construction Barge Lane, Wootton, IOW Shorefix (I.O.W.) Ltd 16 Apr 201422 Jul 2014
MLA/2014/00178 - CompletedApplication - Construction Steart Coastal Management Project ****REF PREVIOUS CONSENT- MLA/2012//00240/1*** Environment Agency - South West Region17 Apr 201430 Jun 2014
MLA/2014/00179/1 - CompletedApplication - Construction, Removals (inc. Grab Samples) Hayle South Quay- Ground Investigation for Penpol Bridge Bowmer And Kirkland Limited 22 Apr 201418 Jul 2014
MLA/2014/00181 - CompletedApplication - Emergency Work Darthaven Marina Quay Remedial Works Balfour Beatty Civil Engineering Limited23 Apr 201428 Apr 2014
MLA/2014/00182/1 - CompletedApplication - Renewables Research & Development of Wave & Tidal Renewable Energy DevicesSouth of Maryport PierMpm North West Limited23 Apr 201406 Oct 2015
MLA/2014/00183/2 - CompletedApplication - Dredged Material Disposal, DredgingKeadby Power station intake & outfall dredging Sse Keadby Power Station23 Apr 201431 Aug 2017
MLA/2014/00184 - CompletedApplication - Construction Repair of walls to marina and inserting pilesport Werburgh Residential Marine Ltd. 24 Apr 201409 Mar 2015
MLA/2014/00185/1 - CompletedApplication - Construction Slipway resurfacing Hythe Sailing Club24 Apr 201413 May 2014
MLA/2014/00187 - CompletedApplication - Construction Rosebank Poulton Remedial Services Ltd 28 Apr 201422 Jul 2014
MLA/2014/00188 - CompletedApplication - Construction, Removals (inc. Grab Samples) Quay wall repairs, Paynes & Borthwick Wharf, Paynes & Borthwick Llp29 Apr 201423 Jul 2014
MLA/2014/00189 - CompletedApplication - Dredged Material DisposalBedhampton Quay Silt DisposalNAB TOWER (WI060) Lafarge Tarmac Limited29 Apr 201409 Oct 2014
MLA/2014/00190 - CompletedApplication - Dredged Material DisposalMarchwood Wharf Silt DisposalNAB TOWER (WI060) Raymond Brown Aggregates Ltd29 Apr 201418 Nov 2014
MLA/2014/00191/1 - CompletedApplication - Construction Mooring Buoy alongside No Man's Land Fort, Solent Grouped under: No Man's Land Island mooring Showing 2 of 2 cases Clarenco Llp29 Apr 201419 Jun 2014
MLA/2014/00192/5 - CompletedApplication - Construction Humber Gateway Offshore Wind Farm Grouped under: Humber Gateway Offshore Wind Farm Showing 5 of 10 cases E.On Climate & Renewables Uk Humber Wind Limited29 Apr 201427 Jul 2020
MLA/2014/00193/2 - CompletedApplication - Construction, Removals (inc. Grab Samples) Jetty replacement Mrs Harriet Ellis 29 Apr 201409 Oct 2015
MLA/2014/00194/1 - CompletedApplication - Construction Replacement of domestic Sea Defence Wall Mr Paul Hayes 29 Apr 201404 Nov 2015
MLA/2014/00195 - CompletedApplication - Construction Demolition of crispins house Mr Phil Pillar01 May 201415 May 2014
MLA/2014/00196/6 - CompletedApplication - Dredging Oikos No1 Jetty Oikos Storage Limited 02 May 201421 Aug 2023
MLA/2014/00197 - CompletedApplication - Construction Newhaven Swing Bridge Mechanical and Electrical Refurbishment East Sussex County Council02 May 201415 Jul 2014
MLA/2014/00198 - CompletedApplication - Removals (inc. Grab Samples) Port of Garston, Partial Removal of Storm Damaged Jetty Associated British Ports Holdings Limited 02 May 201407 Jul 2014
MLA/2014/00199/1 - CompletedApplication - Dredging Tate and Lyle Outer berth Grouped under: Tate and Lyle Sugars Showing 2 of 3 cases T&L Sugars Limited02 May 201405 Sep 2014
MLA/2014/00200 - CompletedApplication - Emergency Work Fraser Range Sea Wall Repairs Southsea Qinetiq Group Plc 06 May 201409 Jun 2014
MLA/2014/00201/2 - CompletedApplication - Construction Isle of Man Interconnector Cable - Cable Protection Remedial Works Manx Cable Company Limited07 May 201424 Mar 2018
MLA/2014/00202 - CompletedApplication - Emergency Work Millbay Docks flapvalves South West Water Limited07 May 201409 May 2014
MLA/2014/00203/6 - CompletedApplication - Construction Riverlight - Remedaial works to Riverwall St James Group Limited08 May 201415 Feb 2016
MLA/2014/00204 - CompletedApplication - Emergency Work Portloe Sewer Outfall 2 South West Water Limited08 May 201409 May 2014
MLA/2014/00205/1 - CompletedApplication - Construction, Removals (inc. Grab Samples) Redcar SO7 Northumbrian Water Limited09 May 201409 Oct 2014
MLA/2014/00206/3 - CompletedApplication - Dredged Material Disposal, DredgingRoyal Norfolk & Suffolk Yacht Club - Maintenance Dredge & Material Disposal Royal Norfolk & Suffolk Yacht Club12 May 201426 Sep 2022
MLA/2014/00207 - CompletedApplication - Construction, Removals (inc. Grab Samples) New Tuckton Revetments Bournemouth Borough Council 13 May 201429 Aug 2014
MLA/2014/00208/1 - CompletedApplication - Dredged Material Disposal, DredgingShamrock Quay - Maintenance Dredging Shamrock Quay Marina, NAB TOWER (WI060) Marina Developments Limited 13 May 201412 Feb 2015
MLA/2014/00209/1 - CompletedApplication - Emergency Work Berths 1 & 2 maintenace dredging Grouped under: VOPAK TERMINAL LONDON B.V. LIMITED Showing 3 of 6 cases Vopak Terminals London Ltd13 May 201415 May 2014
MLA/2014/00210/2 - CompletedApplication - Dredged Material Disposal, DredgingOcean Village Marina - Maintenance DredgingOcean Village Marina (limits), NAB TOWER (WI060)Marina Developments Limited 13 May 201407 Jan 2015
MLA/2014/00212 - CompletedApplication - Dredging Maintenance Dredging at the C.RO Ports Purfleet Berths Grouped under: C.RO Ports Purfleet terminal Showing 3 of 5 cases Cdmr Purfleet Limited 13 May 201426 Aug 2014
MLA/2014/00213 - CompletedApplication - Emergency Work Maintenance dredging at Thames Oilport Morzine Limited 14 May 201415 May 2014
MLA/2014/00214 - CompletedApplication - Emergency Work Tate And Lyle Outer Berth Grouped under: Tate and Lyle Sugars Showing 2 of 3 cases T&L Sugars Limited14 May 201415 May 2014
MLA/2014/00215/1 - CompletedApplication - Emergency Work Oikos Storage Oikos Storage Limited 14 May 201424 Jun 2014
MLA/2014/00216 - CompletedApplication - Emergency Work Maintenance Dredging at the C.RO Ports Purfleet Berths Grouped under: C.RO Ports Purfleet terminal Showing 3 of 5 cases Cdmr Purfleet Limited 14 May 201422 May 2014
MLA/2014/00217/1 - CompletedApplication - Emergency Work Dredging shallow channel, Marazion Beach Grouped under: St Aubyn Estate Showing 4 of 7 cases St Aubyn Estates14 May 201406 Oct 2014
MLA/2014/00218 - CompletedApplication - Burial at Sea Mr Charles Lister 15 May 201415 May 2014
MLA/2014/00219 - CompletedApplication - Emergency Work BP Isle of Grain No 1 Jetty Bp Oil Uk Ltd 15 May 201430 May 2014
MLA/2014/00220/5 - CompletedApplication - Construction, Miscellaneous Disposal, Removals (inc. Grab Samples) Dawlish Sea Wall Emergency Network Rail Limited15 May 201430 Jul 2015
MLA/2014/00221 - CompletedApplication - Emergency Work Dredging Border Force Pontoon Custom Hse River thames Border Force15 May 201420 May 2014
MLA/2014/00222 - CompletedApplication - Construction, Removals (inc. Grab Samples) Knott End Sea Defence Bourne May Road Slipway Environment Agency (Warrington) 15 May 201401 Jul 2014
MLA/2014/00223/1 - CompletedApplication - Construction Reinstatement Of Medway Viaduct Piers 10 and 11 Rock Revetment Network Rail (High Speed) 15 May 201401 Aug 2014
MLA/2014/00224/3 - CompletedApplication - Dredged Material Disposal, DredgingOffshore Technology Park DredgeMaintenance Dredging, SOUTER POINT (OUTER) (TY081), NORTH TYN (TY070) Shepherd Offshore Services Limited16 May 201412 May 2015
MLA/2014/00225/1 - CompletedApplication - Construction, Removals (inc. Grab Samples) Bembridge Coast Hotel Groyne Refurbishment Bourne Leisure Limited16 May 201421 Aug 2014
MLA/2014/00227 - CompletedApplication - Construction Bournemouth Pier Zip Line Openwide International Ltd20 May 201427 Jun 2014
MLA/2014/00228 - CompletedApplication - Construction, Removals (inc. Grab Samples) Quayside pontoon and replacement piles Quayside Marina, Quayside existing mooring pile replacement Quayside Marina 20 May 201414 Oct 2014
MLA/2014/00229 - CompletedApplication - Emergency Work Berth Dredging Shell Uk Oil Products Ltd 20 May 201428 May 2014
MLA/2014/00230 - CompletedApplication - Construction Tyne and Wear aquifer Protection SchemeDirectional drilling launch pit, Discharge point - Outfall diffuser, Discharge pipe directionally drilled The Coal Authority20 May 201401 May 2015
MLA/2014/00231 - CompletedApplication - Removals (inc. Grab Samples) Removal of items from North Sea ship wrecksChandris, Ferryhill, Jolly Girls, Mollusc, Muristan, Pandora, Richard DeLarrinaga Mr William Pocklington21 May 201415 Jul 2015
MLA/2014/00233 - CompletedApplication - Construction Floating yacht club at Brighton Marina Grouped under: Brighton Marina Master Case Showing 4 of 10 casesFloating Yacht Club permanent location, Pontoon pile 1, Pontoon pile 2, Temporary works areaBrighton Marina Company Limited(The)21 May 201427 Oct 2014
MLA/2014/00234 - CompletedApplication - Construction Cosmetic stone facing, small stone face dwarf wall & stone buttress. Pasco's BoatyardPasco'S Boatyard21 May 201410 Sep 2014
MLA/2014/00235/1 - CompletedApplication - Construction Amble Development, The Seafood TownAmble CSBT, Amble Seafood CentreAffordable Architecture Ltd 22 May 201422 Jul 2015
MLA/2014/00236 - CompletedApplication - Construction OWA Universal Foundations Trial Installations - Dogger Bank Zone Statoil Asa 22 May 201406 Aug 2014
MLA/2014/00237 - CompletedApplication - Dredged Material Disposal, DredgingEast Halton Haven Dredging WorkEast Halton Haven, East Halton (HU035)Environment Agency - Midlands Region22 May 201406 Nov 2014
MLA/2014/00239 - CompletedApplication - Emergency Work Bere Ferrers Quay Outfall South West Water Limited22 May 201429 May 2014
MLA/2014/00240/1 - CompletedApplication - Construction 50 Market Street, Falmouth Rtp Surveyors Limited 23 May 201431 Jul 2014
MLA/2014/00241/5 - CompletedApplication - Construction GSK Worthing Outfall Maintenance GSK Outfall Pipe Works Area J.T.Mackley & Co.Limited23 May 201416 Mar 2021
MLA/2014/00242/1 - CompletedApplication - Renewables TRIDENT-AQUASAIL™ TIDAL ENERGY TURBINE SYSTEM (PROOF OF CONCEPT TRIALS)Tidal Energy Device - Yarmouth Pier, Yarmouth Harbour, Isle of WightTrident Renewable Energy Systems Ltd23 May 201417 May 2018
MLA/2014/00243 - CompletedApplication - Emergency Work GSK Worthing Outfall Pipe Mattress Repairs J.T.Mackley & Co.Limited23 May 201430 May 2014
MLA/2014/00244/2 - CompletedApplication - Construction Pontoon Mooring at 47-57 River Rd Littlehampton BN17 5BZ 47-57 River RdBrownfield Estates Limited23 May 201424 Mar 2015
MLA/2014/00245/1 - CompletedApplication - Removals (inc. Grab Samples) Race Bank Offshore Wind Farm - Intertidal Geotechnical Investigation Grouped under: Race Bank Offshore Wind Farm Showing 2 of 11 cases Dong Energy Rb (Uk) Limited 23 May 201405 Aug 2014
MLA/2014/00246 - CompletedApplication - Removals (inc. Grab Samples) Race Bank Offshore Wind Farm - Marine Geotechnical Investigation Grouped under: Race Bank Offshore Wind Farm Showing 2 of 11 cases Dong Energy Rb (Uk) Limited 23 May 201404 Aug 2014
MLA/2014/00249 - CompletedApplication - Construction Southern Ashfield Rewetting Scheme Southern Ashfield Goodman 23 May 201423 Oct 2014
MLA/2014/00250 - CompletedApplication - Construction OWA Universal Foundations Trial Installations - Hornsea Zone Statoil Asa 27 May 201408 Aug 2014
MLA/2014/00252 - CompletedApplication - Construction OWA Universal Foundations Trial Installations - Dudgeon Statoil Asa 28 May 201408 Aug 2014
MLA/2014/00253/2 - CompletedApplication - Aggregate Dredging, Removals (inc. Grab Samples) Area 514 Area 514 [1]Cemex Uk Marine Limited 28 May 201407 Jul 2017
MLA/2014/00254/2 - CompletedApplication - Removals (inc. Grab Samples) RNLI Bridlington: Sea Wall Trial Pits Alan Wood & Partners28 May 201412 Sep 2014
MLA/2014/00255 - CompletedApplication - Burial at Sea Lodge Bros. (Funerals) Limited30 May 201409 Jun 2014
MLA/2014/00256 - CompletedApplication - Miscellaneous Disposal The hydrodynamics of a transient shelf sea front in the Celtic Sea. Mr Marcus Zanacchi30 May 201421 Aug 2014
MLA/2014/00257 - CompletedApplication - Construction, Dredged Material Disposal, DredgingPort of Poole Development Phases 1-3 Phase 1, Phase 2, Phase 3, SWANAGE BAY (WI110)Poole Harbour Commissioners 30 May 201412 Jun 2015
MLA/2014/00258 - CompletedApplication - Dredging Dagenham Jetty upgrade for Cemex UKdredge boxCemex Uk30 May 201413 Jun 2016
MLA/2014/00259/1 - CompletedApplication - Dredged Material DisposalLymington Harbour - Maintenence Dredging DisposalHURST FORT (WI080)Lymington Harbour Commissioners 02 Jun 201428 Sep 2017
MLA/2014/00260 - CompletedApplication - Miscellaneous Disposal Mersey Wavebuoy Sefton Mbc02 Jun 201412 Aug 2014
MLA/2014/00261 - CompletedApplication - Dredged Material Disposal, DredgingCompletion of Replacement Quay dredging A.V.Dawson Limited02 Jun 201431 Jul 2014
MLA/2014/00262/2 - CompletedApplication - Alternative Use of Dredged Material, Construction, DredgingHinkley Point B Seawall Works Grouped under: Hinkley Point Seawall Applications Showing 2 of 2 cases Excavation Area, General location of seawall, Placement AreaEdf Energy Nuclear Generation Limited 03 Jun 201420 Sep 2017
MLA/2014/00263/1 - CompletedApplication - Removals (inc. Grab Samples) Removal of disused intake pipe, Bincleaves Qinetiq Limited 04 Jun 201412 Aug 2014
MLA/2014/00265/3 - CompletedApplication - Construction Portsmouth Harbour strengthen & repair Portsmouth Harbour Pier Network Rail Infrastructure Limited 04 Jun 201429 Sep 2015
MLA/2014/00266/1 - CompletedApplication - Construction Boardwalk and river access at Railway Quay Newhaven Kier Southern Limited 06 Jun 201431 Jul 2015
MLA/2014/00267/1 - CompletedApplication - Dredged Material Disposal, DredgingMarazion beach maintenance and landing point access Grouped under: St Aubyn Estate Showing 4 of 7 casesMarazion Beach - Channel dredging, Marazion dredge disposal siteSt Aubyn Estates09 Jun 201420 May 2019
MLA/2014/00269/1 - CompletedApplication - Construction Heysham Forebay Structure Repairs Edf Energy10 Jun 201417 Sep 2014
MLA/2014/00270 - CompletedApplication - Construction Mill Road, Exeter DG5 South West Water Limited10 Jun 201405 Aug 2014
MLA/2014/00271/1 - CompletedApplication - Construction Installation of Cathodic Protection Systems 2014 to Quay Wall 006 Dover Harbour Board 10 Jun 201416 Apr 2015
MLA/2014/00272 - CompletedApplication - Construction Chelmsford Effluent Pipeline Essex & Suffolk Water 10 Jun 201424 Jun 2014
MLA/2014/00273 - CompletedApplication - Renewables Tyre Filled Net Scour Remediation Installation Scroby Sands OWFEon 11 Jun 201427 Feb 2015
MLA/2014/00274 - CompletedApplication - Removals (inc. Grab Samples) Redcar Beach rubble removal Environment Agency11 Jun 201407 Jul 2014
MLA/2014/00275 - CompletedApplication - Construction Skern CSO Outfall Works South West Water Limited11 Jun 201401 Jul 2014
MLA/2014/00276/2 - CompletedApplication - Renewables Lincs Offshore Wind Farm O&M Licence Grouped under: Lincs, Lynn and Inner Dowsing Offshore Wind Farm Showing 2 of 7 casesLincs Offshore Wind FarmLincs Wind Farm Limited 12 Jun 201424 Sep 2020
MLA/2014/00277 - CompletedApplication - Miscellaneous Disposal help our local heroes/memorial for vetrans who didnt return from normandy Borough Council Of King'S Lynn & West Norfolk 12 Jun 201419 Jun 2014
MLA/2014/00280/2 - CompletedApplication - Removals (inc. Grab Samples) EDF Energy, Sizewell C Offshore Investigations SZC 2014 Offshore InvestigationsNnb Generation Company Limited13 Jun 201428 Apr 2015
MLA/2014/00281 - CompletedApplication - Construction Greatham Bridge Repair and Strengthening WorkGreatham Bridge. Located 2 miles south of Pullborough, West Sussex. The Greatham Bridge carries the C23 (Brook Lane) over the River Arun. West Sussex County Council13 Jun 201411 Mar 2016
MLA/2014/00282/2 - CompletedApplication - Alternative Use of Dredged Material, DredgingFolkestone Seafront Beach Management Folkestone Beach Management Folkestone Harbour (Gp) Limited 13 Jun 201403 Feb 2017
MLA/2014/00283/1 - CompletedApplication - Construction Repairs and Maintenance to Mulberry Quays Falmouth Mulberry Quay, Falmouth Mulberry Quay Management Company Limited16 Jun 201418 Nov 2014
MLA/2014/00284 - CompletedApplication - Construction Strand on The Green River Bank Wall,Chiswick,TQ 19398 77780 Ringway Hounslow Highways Limited 16 Jun 201420 Jun 2014
MLA/2014/00285 - CompletedApplication - Miscellaneous Disposal Wave diffusion at North Sunderland Harbour Rock placement area North Sunderland Harbour Commissioners16 Jun 201429 Jan 2016
MLA/2014/00287 - CompletedApplication - Construction RM Poole The Hard: Piling Remedial work (Single Pile) of new Mooring Pontoons Defence Infrastructure Organisation 19 Jun 201407 Jul 2014
MLA/2014/00288/1 - CompletedApplication - Construction, Dredged Material Disposal, DredgingNorthney Marina - Maintenance Dredging Northney Marina - Construction, Northney Marina - Dredging, NAB TOWER (WI060) Marina Developments Limited 19 Jun 201409 Jun 2015
MLA/2014/00289 - WithdrawnApplication - Construction Penpol Bridge, Penpol Creek Hayle Bowmer And Kirkland Ltd 20 Jun 2014
MLA/2014/00290/3 - CompletedApplication - Miscellaneous Disposal, Removals (inc. Grab Samples) Removal of Met Mast Foundation on Humber Gateway OWF Grouped under: Humber Gateway Offshore Wind Farm Showing 5 of 10 cases E.On Climate & Renewables Uk Limited23 Jun 201401 Dec 2015
MLA/2014/00291/1 - CompletedApplication - Renewables Lynn Offshore Wind Farm O&M Licence Grouped under: Lincs, Lynn and Inner Dowsing Offshore Wind Farm Showing 2 of 7 cases Lynn Offshore Wind Farm [1], Inner Dowsing Offshore Wind Farm Glid Wind Farms Topco Limited 23 Jun 201407 Nov 2022
MLA/2014/00292 - WithdrawnApplication - Renewables Inner Dowsing Offshore Wind Farm Inner Dowsing Offshore Wind FarmGlid Wind Farms Topco Limited 23 Jun 2014
MLA/2014/00293/1 - CompletedApplication - Dredged Material DisposalRenewal of Padstow Harbour's Dredged Sediment Disposal Licence PADSTOW BAY (LU010) Padstow Harbour Commissioners 23 Jun 201412 Jun 2024
MLA/2014/00294 - CompletedApplication - Construction Gurnard Sea Wall Repairs Ms Kuki Waterstone23 Jun 201411 Aug 2014
MLA/2014/00295/1 - CompletedApplication - Emergency Work RNLI - Burnham On Sea - Emergency Launch and Recovery Works Royal National Lifeboat Institution 24 Jun 201406 Aug 2014
MLA/2014/00297 - CompletedApplication - Construction Padstow SPS OutfallPadstow SPS South West Water Limited24 Jun 201417 Sep 2014
MLA/2014/00298 - CompletedApplication - Construction Brighton Marina Outer Harbour Development: Phase 1b Grouped under: Brighton Marina Master Case Showing 4 of 10 cases Brighton Marina Company Limited(The)24 Jun 201407 Jul 2014
MLA/2014/00299/2 - CompletedApplication - Construction Brighton Marina Outer Harbour Development: Phase 1c Grouped under: Brighton Marina Master Case Showing 4 of 10 cases Phase 1c Application Area Brighton Marina Company Limited(The)24 Jun 201425 Sep 2015
MLA/2014/00300/1 - CompletedApplication - Dredged Material DisposalShoreham Port Maintenance Dredging Maintenance Dredge Box A, Maintenance Dredge Box B, Maintenance Dredge Box C, Maintenance Dredge Box D, SHOREHAM (WI031)Shoreham Port Authority 24 Jun 201420 Feb 2015
MLA/2014/00301 - CompletedApplication - Construction Nuplex ResinsNuplex Resins - Construction of river wall, Nuplex Resins - Sprayed Concrete Wall Nuplex Resins Limited 25 Jun 201430 Mar 2015
MLA/2014/00302/5 - CompletedApplication - Dredging Isle of Grain Maintenance Dredging Bp Oil Uk Ltd 26 Jun 201426 Sep 2019
MLA/2014/00303 - CompletedApplication - Construction 32 Market Street Falmouth Mylor Building Co 26 Jun 201423 Jul 2014
MLA/2014/00304/4 - CompletedApplication - Aggregate Dredging, Removals (inc. Grab Samples) Area 484 Deme Building Materials Limited 26 Jun 201409 Dec 2021
MLA/2014/00306/1 - CompletedApplication - Aggregate Dredging, Removals (inc. Grab Samples) Area 396 Inner Owers Grouped under: Aggregate Area 488 Showing 2 of 6 casesArea 396/1, Area 396/2Tarmac Marine Dredging Limited27 Jun 201416 Feb 2017
MLA/2014/00307/1 - CompletedApplication - Aggregate Dredging, Removals (inc. Grab Samples) Area 435 Grouped under: Aggregate Area 488 Showing 2 of 6 casesArea 435/1, Area 435/2Hanson Aggregates Marine Limited27 Jun 201424 Feb 2017
MLA/2014/00308/3 - CompletedApplication - Aggregate Dredging, Removals (inc. Grab Samples) Area 483 483, Humber 5 Deme Building Materials Limited 27 Jun 201407 Jul 2022
MLA/2014/00309 - CompletedApplication - Construction Millbay Marina Wavescreen Repairs Millbay Marina Village27 Jun 201402 Sep 2014
MLA/2014/00310/10 - Completed Application - Construction Lowestoft South Beach Flint Seawall. Urgent stabilisation works Waveney District Council30 Jun 201410 Dec 2015
MLA/2014/00311 - CompletedApplication - Construction The Bristol General Hospital Redevlopment City & Country Bristol Limited30 Jun 201401 Sep 2014
MLA/2014/00312 - CompletedApplication - Construction River Medway Railway Bridge brick pier and abutment maintenace repairs Balfour Beatty Rail Limited 30 Jun 201430 Jul 2014
MLA/2014/00313/1 - CompletedApplication - Miscellaneous Disposal 120mm proof (inert rounds for BAE Systems) firing to sea Qinetiq Group Plc 30 Jun 201419 Sep 2014
MLA/2014/00314 - CompletedApplication - Construction Pontoon Replacement - Port of Ramsgate - Outer West Marina Grouped under: Port of Ramsgate Pontoon Replacement Showing 2 of 2 casesPort of Ramsgate - Outer West MarinaPort Of Ramsgate01 Jul 201408 Sep 2014
MLA/2014/00315/1 - CompletedApplication - Construction Baynard House Discharge Point Structure Relocation Baynard House working area1 British Telecommunications Public Limited Company 01 Jul 201429 Sep 2015
MLA/2014/00316 - CompletedApplication - Construction Millbay Marina kml file for Linden Homes Linden Homes Sout West01 Jul 201408 Sep 2015
MLA/2014/00317 - CompletedApplication - Construction, Miscellaneous Disposal RSPB Titchwell Marsh storm surge remediation Rspb01 Jul 201413 Aug 2014
MLA/2014/00318 - CompletedApplication - Construction St Michael's Mount Storm Damage Repair Mrda Architects 02 Jul 201421 Aug 2014
MLA/2014/00319 - CompletedApplication - Dredging Jurgens Jetty Annual Maintenance DredgeJurgens Jetty Pura Foods Limited03 Jul 201417 Dec 2015
MLA/2014/00320/2 - CompletedApplication - Dredging Faversham Creek Basin Dredging Faversham Creek Basin Faversham Creek Navigation Company Cic03 Jul 201431 Aug 2018
MLA/2014/00322/1 - CompletedApplication - Construction In situ preservation of Coronation Protected Wreck Coronation Offshore protected wreck, defined by a circle of radius 150 metres centred on point belowCoronation Wreck Project04 Jul 201426 May 2015
MLA/2014/00323/2 - CompletedApplication - Emergency Work Queenborough River Wall M.I.T. (Machining) Limited04 Jul 201416 Sep 2015
MLA/2014/00324/1 - CompletedApplication - Construction RN Lifeboat Institution Padstow - Maintenance and Renewal Works Royal National Lifeboat Institution 06 Jul 201428 Nov 2014
MLA/2014/00325 - CompletedApplication - Construction Greenwich PR2 - Surface Water OutfallGreenwich Peninsula Knight Dragon Developments Limited07 Jul 201423 Jul 2015
MLA/2014/00326/2 - CompletedApplication - Dredged Material Disposal, DredgingWoolverstone Marina Maintenance Dredge Woolverstone Marina, RIVER ORWELL (ABP) (TH034) Marina Developments Limited 07 Jul 201424 Mar 2016
MLA/2014/00327 - CompletedApplication - Miscellaneous Disposal, Removals (inc. Grab Samples) Removal of Seaweed - Marazion Beach Grouped under: St Aubyn Estate Showing 4 of 7 casesMarazion Beach dredge area, Marazion Beach (PL095)St Aubyn Estates07 Jul 201407 Nov 2014
MLA/2014/00328 - CompletedApplication - Construction Cidadel Intake Pipe Reinstatement The Marine Biological Association Of The United Kingdom 08 Jul 201410 Jul 2014
MLA/2014/00329/1 - CompletedApplication - Construction Otter Cottage - Sea Wall Mr Peter Visick 08 Jul 201404 Sep 2014
MLA/2014/00330/4 - CompletedApplication - Construction Long's Wharf Jetty, Yarmouth Long's Wharf JettyMr Richard Leonard08 Jul 201430 Oct 2018
MLA/2014/00331/4 - CompletedApplication - Construction Mamhead Slipway, Exmouth, DevonMamhead Slipway East Devon District Council 08 Jul 201415 Dec 2016
MLA/2014/00332 - CompletedApplication - Emergency Work Millbay Docks Flap Valves South West Water Limited08 Jul 201411 Jul 2014
MLA/2014/00333/2 - CompletedApplication - Construction Centenary Quay Marine Inlet and River Edge Works Marine Inlet and River Edge Licence BoundaryCrest Nicholson Operations Limited08 Jul 201408 Aug 2018
MLA/2014/00334/1 - CompletedApplication - Construction Construction of Test Piles as part of the Mersey Gateway Project North Side Test Location, South Side Test LocationMersey Link 09 Jul 201414 Nov 2014
MLA/2014/00336/1 - CompletedApplication - Construction DONG Energy Burbo (UK) Ltd - Operational Marine Licence Inter Array Cable Repair DONG Energy Burbo (UK) Ltd. Dong Energy Burbo (Uk) Limited11 Jul 201417 Jan 2018
MLA/2014/00337 - CompletedApplication - Construction RN Lifeboat Institution Lizard - Maintenance and Renewal Works Royal National Lifeboat Institution 11 Jul 201405 Aug 2014
MLA/2014/00338/1 - CompletedApplication - Construction Acorn Shipyard - Construction of new barge gridAcorn Shipyard - ChathamAcorn Shipyard Ltd14 Jul 201424 Sep 2015
MLA/2014/00340 - CompletedApplication - Dredged Material Disposal, DredgingScarborough Harbour Maintenance Dredging Scarborough Inner Harbour, Scarborough Outer Harbour, Scarborough Harbour Inner Approaches, SCARBOROUGH ROCK (TY190)Scarborough Borough Council 15 Jul 201408 Dec 2014
MLA/2014/00341 - CompletedApplication - Construction Form a Lagoon and Erect Single Storey Toilet Block and Associated LandscapeLagoonSouthend On Sea Borough Council 15 Jul 201407 Dec 2015
MLA/2014/00342/1 - CompletedApplication - Construction Upgrade of Careening Apron Careening apron adjacent to slipway Eastney Lake, Eastney,PortsmouthEastney Cruising Association16 Jul 201402 Sep 2015
MLA/2014/00343 - CompletedApplication - Dredging, Miscellaneous Disposal Hinkley Point A - Clearance of stormwater outlet Grouped under: Hinkley Point Seawall Applications Showing 2 of 2 cases Hinkley Point A 16 Jul 201401 Aug 2014
MLA/2014/00344 - CompletedApplication - Construction, Dredged Material Disposal, Dredging, Removals (inc. Grab Samples)Ipswich Flood Defence Management Scheme: Tidal Barrier Works Environment Agency17 Jul 201403 Aug 2015
MLA/2014/00345 - CompletedApplication - Construction The Causeway resurfacing Phase 4 The Causeway, NorthumberlandNorthumberland County Council 18 Jul 201416 Sep 2014
MLA/2014/00346 - CompletedApplication - Aggregate Dredging, Removals (inc. Grab Samples) Areas 296 Cross SandsArea 296Tarmac Marine Dredging Limited18 Jul 201420 Jul 2015
MLA/2014/00347 - CompletedApplication - Construction RECONSTRUTION OF ATLANTIC HOTEL CSO & MINOR REPAIRS TO OTHER OUTFALLSATLANTIC HOTEL CSO, MERMAID INN OUTFALL, OLD TOWN BAY OUTFALL Council Of The Isles Of Scilly18 Jul 201430 Oct 2014
MLA/2014/00348 - CompletedApplication - Construction Millbay Docks redevelopmentMillbay MarinaKier Construction 18 Jul 201416 Sep 2014
MLA/2014/00349 - CompletedApplication - Removals (inc. Grab Samples) Removal of Landing Stage, Portland CastlePortland Castle Jetty English Heritage18 Jul 201413 Oct 2014
MLA/2014/00350 - CompletedApplication - Construction, Removals (inc. Grab Samples) Storm Recovery Works to Southwick and Portslade BeachesSouthwick Beach, Portslade BeachShoreham Port Authority 18 Jul 201402 Mar 2015
MLA/2014/00351 - CompletedApplication - Construction, Removals (inc. Grab Samples) Apron repairs at Brading Haven Yacht Club, Isle of Wight Brading Haven Yacht Club21 Jul 201425 Jul 2014
MLA/2014/00352 - CompletedApplication - Construction Sea Wall at The Hayling Yacht Co Ltd Hayling Yacht Company Limited(The)21 Jul 201413 Aug 2014
MLA/2014/00354/2 - CompletedApplication - Aggregate Dredging, Removals (inc. Grab Samples) Area 494 North Cross Sands Area 494Tarmac Marine Dredging Limited23 Jul 201429 Apr 2019
MLA/2014/00355 - CompletedApplication - Miscellaneous Disposal Dawlish- Woodland Avenue LandslipWoodlands Avenue Landslip Network Rail Limited24 Jul 201413 Oct 2014
MLA/2014/00356 - CompletedApplication - Construction, Removals (inc. Grab Samples) Port Solent Inner Waiting Pontoon PilesPort solent inner waiting pontoon, Port solent inner waiting pontoonPremier Marinas Limited 24 Jul 201403 Nov 2014
MLA/2014/00357 - CompletedApplication - Construction Bishops Tawton Scour ProtectionBishops Tawton NDN209-68Dyer And Butler Limited 25 Jul 201422 Oct 2014
MLA/2014/00358 - CompletedApplication - Construction Reinstatement of Wet Wok and Rock Cottage Miss Samantha Cheraga 29 Jul 201429 Aug 2014
MLA/2014/00360 - CompletedApplication - Construction Cyclops Wharf Flood Defence Repairs Moore Project Management Solutions Llp30 Jul 201415 Aug 2014
MLA/2014/00362 - CompletedApplication - Burial at Sea Charles Lister30 Jul 201401 Aug 2014
MLA/2014/00363 - CompletedApplication - Construction Claxton Beck bank Stabilisation and Gas pipe support Claxton Beck, Cowpen Bewley Country ParkSalix 31 Jul 201406 Oct 2014
MLA/2014/00364 - CompletedApplication - Construction Proposed concrete pads to refix steel coastline staircaseThe moorings, 32 lower castle roadMrs J Wilcox31 Jul 201417 Sep 2014
MLA/2014/00365 - CompletedApplication - Construction National Recovery Programme Emergency Repairs to Baiter car park wallBaiter Car park Poole DorsetBorough Of Poole Council31 Jul 201424 Sep 2014
MLA/2014/00366 - CompletedApplication - Construction Hayle Harbour Swing Bridge Major Work Repairs Hammond (Ecs) Limited 01 Aug 201429 Aug 2014
MLA/2014/00367/1 - CompletedApplication - Dredged Material Disposal, DredgingPortsmouth International Port Maintenance Dredge 2014 Grouped under: Portsmouth City Council - Pre appllication advice Showing 2 of 2 casesAlbert Johnson and Flathouse Quay (Area A), Berth 5 and North Quay, HMS Bristol, NAB TOWER (WI060)Portsmouth International Port 01 Aug 201413 Feb 2017
MLA/2014/00368/6 - CompletedApplication - Dredged Material Disposal, Dredging, Removals (inc. Grab Samples)Portsmouth International Port - Demolition of Floating Dock Jetty. Grouped under: Portsmouth City Council - Pre appllication advice Showing 2 of 2 cases Capital Dredge, Floating Dock Jetty (Demolition), Seabed Obstructions, NAB TOWER (WI060)Portsmouth City Council 01 Aug 201419 Apr 2016
MLA/2014/00369 - CompletedApplication - Construction Morecambe Wastewater Treatment Outfall (River Lune) Site Investigation WorkRBH501, TP502, RBH502, TP503, WS501, BH501, BH502, BH503, BH504, BH505United Utilities Plc01 Aug 201431 Mar 2015
MLA/2014/00370/2 - CompletedApplication - Construction, Removals (inc. Grab Samples) Happisburgh rock bundHappisburgh rock sill North Norfolk District Council04 Aug 201416 Sep 2015
MLA/2014/00371 - CompletedApplication - Construction North Quay, South Harbour Piling works North Quay South Harbour Port of BlythPort Of Blyth 04 Aug 201422 Oct 2014
MLA/2014/00372/2 - CompletedApplication - Dredged Material Disposal, DredgingWhitby Harbour Maintenance DredgingWhitby Upper Harbour, Whitby Lower Harbour, Whitby Harbour Bar, Whitby TY 180 (Disposal Site).Scarborough Borough Council 05 Aug 201413 Oct 2017
MLA/2014/00373/2 - CompletedApplication - Dredging Middleton Wharf Dredging Middleton Wharf Riverside Resource Recovery Ltd 05 Aug 201427 Nov 2019
MLA/2014/00374 - CompletedApplication - Dredging Dredging of S-JettyS-Jetty Shell Uk Oil Products Ltd 06 Aug 201431 Jul 2017
MLA/2014/00375/6 - CompletedApplication - Construction, Removals (inc. Grab Samples) Eastern Breakwater Refurbishment Eastern Breakwater RefurbishmentFalmouth Petroleum Limited06 Aug 201428 Nov 2017
MLA/2014/00376 - CompletedApplication - Construction Portsmouth Harbour - Hants Network Rail Infrastructure Limited 06 Aug 201419 Aug 2014
MLA/2014/00377/1 - CompletedApplication - Removals (inc. Grab Samples) Lynn and Inner Dowsing - Breather Pipe Location and Removal on Skegness Beach Glid Limited07 Aug 201403 Oct 2014
MLA/2014/00379 - CompletedApplication - Construction MILL HALL RIVER WALL WORKS Mill Hall Chartway Group Limited07 Aug 201411 Dec 2014
MLA/2014/00380 - CompletedApplication - Dredged Material DisposalDisposal of maintenance dredge from nav channels & berths in Fleetwood SHA MORECAMBE BAY: LUNE DEEP (IS170)Associated British Ports Holdings Limited 08 Aug 201401 Oct 2015
MLA/2014/00381/4 - CompletedApplication - Construction Wind and direction measurement buoy and wave buoy deployment Mainstream FLiDAR Buoy 1, Mainstream FLiDAR Buoy 2Neart Na Gaoithe Offshore Wind Limited11 Aug 201408 Apr 2015
MLA/2014/00382/1 - CompletedApplication - Renewables PLAT-O Prototype - Initial trials at Yarmouth Grouped under: PLAT-O Prototype - Testing at Yarmouth Showing 3 of 3 cases Sustainable Marine Energy Limited 11 Aug 201409 Oct 2014
MLA/2014/00383/1 - CompletedApplication - Emergency Work The cottage by the lake and number 1 solent Breezes Grouped under: Solent Breezes Showing 2 of 2 cases Mr Jerry Lewis12 Aug 201422 Oct 2014
MLA/2014/00384 - CompletedApplication - Construction Residential development of Brunswick Wharf BarnstapleBrunswick Wharf, Barnstaple, DevonTeignmouth Maritime Services Limited12 Aug 201419 Dec 2014
MLA/2014/00385/1 - CompletedApplication - Construction TURNCHAPEL BOATYARDTurnchapel Boatyard (various works relating to existing sea wall) Mr Anthony Collins12 Aug 201410 Dec 2015
MLA/2014/00386 - CompletedApplication - Miscellaneous Disposal Mooring For British Americas Cup race yacht Ben Ainslie Racing13 Aug 201401 Sep 2014
MLA/2014/00387 - CompletedApplication - Construction Dock Cottage, Appledore outfall investigationDock Cottage, Appledore outfallsSouth West Water Limited13 Aug 201419 Sep 2014
MLA/2014/00388 - CompletedApplication - Construction Dungeness B Nuclear Power Station Rock Armour PlacementDungeness B Nuclear Power Station Edf Energy Plc14 Aug 201407 Nov 2014
MLA/2014/00389 - CompletedApplication - Construction Immingham Outer Habour berth zeroImmingham Outer Harbour berth zero - floating pontoon and linkspanAssociated British Ports14 Aug 201409 Mar 2015
MLA/2014/00390 - CompletedApplication - Alternative Use of Dredged MaterialBeach Managemen Plan Wittering Beach Renourishment Jollife Road Shingle Deposition SiteChichester District Council 14 Aug 201408 Dec 2014
MLA/2014/00391/3 - CompletedApplication - Dredging Stone Creek Dredging South Holderness Internal Drainage14 Aug 201415 Oct 2015
MLA/2014/00392/6 - CompletedApplication - Dredged Material Disposal, DredgingGosport Marina Maintenance DredgeGosport Marina, NAB TOWER (WI060) Premier Marinas Limited 14 Aug 201418 Dec 2019
MLA/2014/00393 - CompletedApplication - Construction, Removals (inc. Grab Samples) Gosport Ferry Portsea Berth RemediationGosport Ferry Terminal, Portsea Gosport Ferry Limited 14 Aug 201420 Jan 2015
MLA/2014/00394 - CompletedApplication - Construction Seaham Marina Pontoon ExtensionSeaham Marine Pontoon Extension Seaham Harbour Marina 15 Aug 201421 Jan 2015
MLA/2014/00396 - CompletedApplication - Construction Calshot Sea Wall Calshot Sea WallHampshire County Council20 Aug 201401 Apr 2015
MLA/2014/00397 - CompletedApplication - Removals (inc. Grab Samples) Removal of Weston Mill Creek Culvert Weston Mill Creek Culvert Mvv Umwelt O&M Gmbh 20 Aug 201429 Oct 2014
MLA/2014/00398/1 - CompletedApplication - Construction Repairs and Maintenance to Aids to NavigationN Felixstowe groyne D5, N Felixstowe groyne D9, N Felixstowe groyne D13, N Felixstowe groyne D17, N Felixstowe groyne D19, N Felixstowe groyne E1, N Felixstowe groyne E2, N Felixstowe groyne E3, N Felixstowe groyne E4, N Felixstowe groyne E5, N Felixstowe groyne E6, N Felixstowe groyne E7, N Felixstowe groyne E8, N Felixstowe groyne E9, N Felixstowe groyne E10, N Felixstowe groyne E11, N Felixstowe groyne E12, N Felixstowe groyne E13, N Felixstowe groyne E14, N Felixstowe groyne E15, N Felixstowe groyne E16, N Felixstowe groyne E17, N Felixstowe groyne E18, N Felixstowe groyne E19, N Felixstowe groyne E20, R Deben groyne 1, R Deben groyne 3, R Deben groyne 10, Bawdsey Manor OutfallWaveney District Council21 Aug 201416 Jul 2015
MLA/2014/00399 - WithdrawnApplication - Construction Brighton Marina Outer Harbour Development: Phase 2a Grouped under: Brighton Marina Master Case Showing 4 of 10 cases Brighton Marina Company Limited(The)21 Aug 2014
MLA/2014/00401/1 - CompletedApplication - Construction, Removals (inc. Grab Samples) Sunnycliff Sewer Diversion Sunnycliff Location 1 South West Water Limited22 Aug 201425 Nov 2015
MLA/2014/00402 - CompletedApplication - Construction, Miscellaneous Disposal Dunball Sluice Dunball SluiceEnvironment Agency – South West Reg 22 Aug 201410 Oct 2014
MLA/2014/00403 - CompletedApplication - Construction Pier Cellars Parapet to Harbour Sea Wall Pier CellarsMorgan Sindall Group Plc22 Aug 201419 Sep 2014
MLA/2014/00404/2 - CompletedApplication - Dredged Material DisposalTeignmouth Harbour and Approaches Maintenance Dredging SPREY POINT (PO070) Teignmouth Harbour Commission 25 Aug 201431 Aug 2018
MLA/2014/00405/1 - CompletedApplication - Construction Otter Bridge - Sea WallOtter Bridge, Church Road, Mylor, Falmouth TR11 5NL Mr Alan Ireland 28 Aug 201405 Mar 2015
MLA/2014/00406/2 - CompletedApplication - Emergency Work Maintenance Dredge of Grain LNG Jetties 8 & 10 River Medway Grouped under: Isle of Grain maintenance dredging Showing 2 of 3 cases Grain LNG National Grid Grain Lng Ltd 28 Aug 201430 Sep 2014
MLA/2014/00407 - CompletedApplication - Construction Quay House, Tuckenhay - Sewer ReplacementQuay House, Tuckenhay South West Water Limited28 Aug 201420 Oct 2014
MLA/2014/00408 - CompletedApplication - Construction Bere Ferrers Quay Outfall Repair Bere Ferrers Quay Outfall South West Water Limited29 Aug 201413 Mar 2015
MLA/2014/00409/1 - CompletedApplication - Construction Repairs & Maintenence to Aids to NavigationGunton & Corton coast, Suffolk groyne B1, Gunton & Corton coast, Suffolk groyne C5, Gunton & Corton coast, Suffolk groyne C13, Gunton & Corton coast, Suffolk groyne D4 Waveney District Council29 Aug 201420 Jul 2015
MLA/2014/00410 - CompletedApplication - Construction Wallasea Island Wild Coast Project (Cell 5 Regulated Tidal Exchange Lagoon) Grouped under: Wallasea Island Wild Coast Project (Cell 5 Regulated Tidal Exchange Lagoon) Showing 2 of 4 casesExisting sluice and 50m length of channel in Defra RealignmentRspb29 Aug 201401 May 2015
MLA/2014/00411 - CompletedApplication - Construction Robin Rigg Offshore Wind Farm Operational Marine Licence - Export CableExport Cable RouteE.On Climate & Renewables Uk Limited01 Sep 201418 Jun 2015
MLA/2014/00412/2 - CompletedApplication - Construction RNLI Scarborough New Lifeboat StationScarborough RNLIR.N.L.I. (Trading) Limited01 Sep 201408 Jan 2015
MLA/2014/00413 - CompletedApplication - Construction Environment Agency Asset Recovery Programme - URN 1200 Padstow Tidal GatePadstow Tidal GateEnvironment Agency - South West Region01 Sep 201424 Sep 2014
MLA/2014/00414/2 - CompletedApplication - Construction Environment Agency Asset Recovery Programme - URN 1159 Copperhouse GateCopperhouse GateEnvironment Agency - South West Region01 Sep 201426 Sep 2014
MLA/2014/00415 - CompletedApplication - Construction River Parrett at Combwich to BridgwaterRiver Parrett at Combwich to Bridgwater Environment Agency - South West Region01 Sep 201410 Oct 2014
MLA/2014/00416/3 - CompletedApplication - Construction Outer Coaling Pier Works Outer Coaling Pier WorksPortland Harbour Authority Ltd01 Sep 201411 Oct 2016
MLA/2014/00418/1 - CompletedApplication - Construction Withernsea Commercial Boat Slipway Withernsea Boat Slipway - Outline of proposed structure in red, Rock Groyne East Riding Of Yorkshire Council02 Sep 201413 Jan 2015
MLA/2014/00419/4 - CompletedApplication - Aggregate Dredging, Removals (inc. Grab Samples) Area 493 Area 493Tarmac Marine Dredging Limited02 Sep 201426 Sep 2019
MLA/2014/00420/2 - CompletedApplication - Dredged Material Disposal, DredgingPort Solent Approach Channel DredgePort Solent Approach Channel, NAB TOWER (WI060) Premier Marinas Limited 03 Sep 201428 Feb 2022
MLA/2014/00421 - CompletedApplication - Emergency Work Thames Oilport removal of silt from fire fighting water intake chamber Location of water chamber Morzine Limited 03 Sep 201410 Sep 2014
MLA/2014/00422 - CompletedApplication - Construction Riverside Cottage Newton Ferrers - pipeline replacementRiverside House South West Water Limited04 Sep 201421 Oct 2014
MLA/2014/00423/1 - CompletedApplication - Construction RNLI WaltonRNLI Walton R.N.L.I. (Trading) Limited04 Sep 201416 Sep 2015
MLA/2014/00424/2 - CompletedApplication - Construction of new worksHalftide House plinthLa Crevette, Halftide House Mr John Polley05 Sep 201401 Dec 2016
MLA/2014/00425/2 - CompletedApplication - Construction Outfalls Maintenance United Utilities Water Plc05 Sep 201420 May 2019
MLA/2014/00426 - CompletedApplication - Maintenance of existing worksKiln Quay RepairsKiln Quay Trefusis Estate 05 Sep 201409 Jul 2015
MLA/2014/00427 - CompletedApplication - Construction Repair of storm damaged slipway to Carrick Court, Restronguet Point, Feock Gilbert And Goode Limited 05 Sep 201408 Dec 2014
MLA/2014/00428 - CompletedApplication - Maintenance of existing works, Other depositsKingston Beach Recharge WorksKingston Beach Working Area Environment Agency (Southern Region)05 Sep 201415 Oct 2014
MLA/2014/00429 - CompletedApplication - Construction, Removals (inc. Grab Samples) RNLI Coventina Pile N1, Pile N2, Pile W1, Pile W2, Area of pile removal, North Pontoon, West Pontoon R.N.L.I. (Trading) Limited07 Sep 201431 Oct 2014
MLA/2014/00431/4 - CompletedApplication - Dredged Material DisposalMaintenance dredge disposal - Grimsby & Immingham and Sunk Dredged Channel Grouped under: ABP Humber Dredging Showing 3 of 3 cases HUMBER 1A (HU080), HUMBER 3A (HU060), HUMBER 2 (HU090)Associated British Ports. 09 Sep 201427 Jan 2023
MLA/2014/00432/3 - CompletedApplication - Dredged Material DisposalMaintenance Dredge Disposal - Port of Hull, approaches and riverside berths Grouped under: ABP Humber Dredging Showing 3 of 3 casesHUMBER 4B/HOOK (HU020), HUMBER 4 (HU030), Humber 4B/Hook Extension (HU021)Associated British Ports. 09 Sep 201415 Mar 2023
MLA/2014/00433/2 - CompletedApplication - Dredged Material DisposalMaintenance Dredge Disposal - Port of Goole and approaches Grouped under: ABP Humber Dredging Showing 3 of 3 cases WHITGIFT BIGHT (RIVER OUSE) (HU040), GOOLE REACH (HU041)Associated British Ports Holdings Limited 09 Sep 201415 Mar 2023
MLA/2014/00434 - CompletedApplication - Other deposits Yarmouth Roads Protected Wreck BuoyYarmouth Roads Protected WreckEnglish Heritage10 Sep 201403 Oct 2014
MLA/2014/00435 - CompletedApplication - Construction of new worksReconstruction of Town Quay, Lowestoft Town Quay, LowestoftAssociated British Ports. 11 Sep 201401 Oct 2014
MLA/2014/00436 - CompletedApplication - Construction of new works, Maintenance of existing works Littlehampton Fishing Hub and West Bank Mooring EnhancementFishing Hub, West Bank Moorings Littlehampton Harbour Board 11 Sep 201417 Dec 2014
MLA/2014/00437 - CompletedApplication - Construction of new worksPreston Terminal Pumping Station Outfall Preston Terminal Pumping Station OutfallUnited Utilities Plc11 Sep 201410 Mar 2015
MLA/2014/00438 - CompletedApplication - Maintenance of existing works, Navigational dredging (capital) Sankey Canal Lock RepairsSpike Island, Widnes / end of Sankey Canal Navigation Halton Borough Council11 Sep 201419 Mar 2015
MLA/2014/00439 - CompletedApplication - Other dredging RNLI Aldeburgh - Low Impact Maintenance Works (Fast Track Licence) Beach Re-profiling Area Aldeburgh - ALB, Beach Re-profiling Area Aldeburgh - ILBRnli11 Sep 201414 Oct 2014
MLA/2014/00440 - CompletedApplication - Other dredging RNLI Eastbourne - Low Impact Maintenance Works (Fast Track Licence)Beach Re-profiling Area Rnli11 Sep 201414 Oct 2014
MLA/2014/00441 - CompletedApplication - Other dredging RNLI Hastings - Low Impact Maintenance Works (Fast Track Licence)Area of Beach Re-profiling - Hastings Rnli11 Sep 201410 Oct 2014
MLA/2014/00442 - CompletedApplication - Other dredging RNLI Dungeness - Low Impact Maintenance Works (Fast Track Licence) RNLI Dungeness - Area of Beach Re-profiling Rnli11 Sep 201414 Oct 2014
MLA/2014/00443 - CompletedApplication - Other dredging RNLI Walmer - Low Impact Maintenance Works (Fast Track Licence)Walmer Beach Re-profiling AreaRnli11 Sep 201416 Oct 2014
MLA/2014/00444 - CompletedApplication - Dredging RoDMA Dredging Works KGV EntranceRoyal Docks Management Authority Limited12 Sep 201404 Jun 2015
MLA/2014/00445 - CompletedApplication - Maintenance of existing worksRNLI Minehead - Low Impact Maintenance Works (Fast Track Licence)Area of Maintenance works - recovery anchorsRoyal National Lifeboat Institution 15 Sep 201417 Sep 2014
MLA/2014/00446/1 - CompletedApplication - Construction Extension to existing slipway at Oddicombe Beach, Babbacombe Bay, TorquaySlipway extension at Oddicombe BeachBabbacombe Corinthian Sailing Club17 Sep 201427 Mar 2015
MLA/2014/00447/3 - CompletedApplication - Construction RNLI Swanage Swanage Development Works Rnli17 Sep 201406 May 2016
MLA/2014/00448 - CompletedApplication - Maintenance of existing worksDownderry Beach Manhole, SeatonDownderry Manhole South West Water Limited17 Sep 201403 Dec 2014
MLA/2014/00449/2 - CompletedApplication - Construction Swanwick Marina River Wall Premier Marinas (Hamble) Limited18 Sep 201418 Nov 2021
MLA/2014/00450 - CompletedApplication - Maintenance of existing worksWarfleet Creek - outfall capping Warfleet Creek 1, Warfleet Creek 2South West Water Limited18 Sep 201430 Oct 2014
MLA/2014/00451 - CompletedApplication - Dredged Material DisposalDisposal of dredgings from Harwich / Felixstowe Outer ChannelINNER GABBARD EAST (TH056)Harwich Haven Authority 19 Sep 201419 Feb 2015
MLA/2014/00452 - CompletedApplication - Construction Camperdown Terrace Surface Water OutfallsSlipway by No. 8, Slipway by No. 60, Access to No.30South West Water Authority19 Sep 201426 Nov 2014
MLA/2014/00454 - CompletedApplication - Maintenance of existing worksCidadel Intake Pipe Reinstatement - part 2 - Block AdditionCitadel Hill, PlymouthThe Marine Biological Association Of The United Kingdom 22 Sep 201421 Oct 2014
MLA/2014/00455 - CompletedApplication - Navigational dredging (maintenance)Emergency Dredging Application at West India Dock London West India Dock Lock Entrance Canal & River Trust 22 Sep 201425 Sep 2014
MLA/2014/00457 - CompletedApplication - Construction of new worksPort of Tilbury Riverside RoRo extension Port of Tilbury Riverside RoRo BerthPort Of Tilbury London Limited23 Sep 201409 Dec 2014
MLA/2014/00458 - CompletedApplication - Maintenance of existing worksWalkway to Pontoon Replacement Project Border Force, Gravesend, DA12 2BW Ksd Support Services Limited23 Sep 201407 Nov 2014
MLA/2014/00459 - CompletedApplication - Construction of new worksAddition of wave reflector to existing sea wall at The Boathouse, Salcombe.The Boathouse, Cliff Road, Salcombe TQ8 8JQ Mr Robert Tee 23 Sep 201409 Dec 2014
MLA/2014/00460 - CompletedApplication - Construction Repair work to concrete surround of drainage leat outlet at Porth Hellick BeachPorth Hellick Drainage Leat Duchy Of Cornwall 24 Sep 201414 Apr 2015
MLA/2014/00461/1 - CompletedApplication - Construction of new worksWide View Quay 83 Yealm Road, Wide View quay Mr Andrew Coughlan24 Sep 201422 Sep 2015
MLA/2014/00462/1 - CompletedApplication - Maintenance of existing worksAsset Recovery Programme - URN 705 Swanpool - Cornwall Council Cornwall Council Asset Recovery Programme - URN 705 Swanpool Coast Path Cornwall Council24 Sep 201429 Sep 2014
MLA/2014/00463 - CompletedApplication - Maintenance of existing worksAsset Recovery Programme - URN 1237 Portwrinkle - Cornwall Council Cornwall Council Asset Recovery Programme - URN 1237 PortwrinkleCornwall Council24 Sep 201401 Oct 2014
MLA/2014/00464 - CompletedApplication - Maintenance of existing worksRNLI Sennen - Low Impact Maintenance Works (Fast Track Licence)Lifeboat Station Sennen - Area of Maintenance Works Royal National Lifeboat Institution 24 Sep 201423 Oct 2014
MLA/2014/00465 - CompletedApplication - Maintenance of existing worksEnvironment Agency Asset Recovery Programme - URN 1472 Gorran Haven - Cornwall Council URN 1472 Gorran Haven Cornwall Council24 Sep 201401 Oct 2014
MLA/2014/00466 - CompletedApplication - Disposal of dredged material, Maintenance of existing works, Other dredgingRNLI Wells - Low Impact Maintenance Works (Fast Track Licence) Wells Beach Re-profiling Area - Recharge Area, Wells Beach Re-profiling Area - Source MaterialRoyal National Lifeboat Institution 24 Sep 201409 Oct 2014
MLA/2014/00467 - CompletedApplication - Other dredging S-Jetty Dredging S-Jetty Shell Haven Shell Uk Oil Products Ltd 25 Sep 201404 Dec 2014
MLA/2014/00468/2 - CompletedApplication - Maintenance of existing works, Other works Asset Recovery Programme - URN 1240 St Ives Wheal Dream - Cornwall Council Cornwall Council25 Sep 201417 Dec 2014
MLA/2014/00470/5 - CompletedApplication - Construction of new works, Maintenance of existing works, Other worksAsset Recovery Programme - URN 1210 & 1211 Newquay Towan - Cornwall CouncilLocation 1, Location 2, Location 3, Location 4Cornwall County Council 25 Sep 201427 May 2015
MLA/2014/00471 - CompletedApplication - Maintenance of existing worksAsset Recovery Programme - URN 1293 Oreston Wall - Plymouth CouncilURN 1293 Oreston Wall Plymouth City Council 25 Sep 201408 Oct 2014
MLA/2014/00472/1 - CompletedApplication - Maintenance of existing worksAsset Recovery Programme - URN 1254 Trevone Beach - Cornwall Council URN 1254 Trevone BeachCornwall Council25 Sep 201405 Jan 2015
MLA/2014/00473 - CompletedApplication - Maintenance of existing worksAsset Recovery Programme - URN 1147 St Mawes Sea Wall - Cornwall Council Cornwall Council Asset Recovery Programme - URN 1247 St Mawes Sea WallCornwall Council25 Sep 201414 Oct 2014
MLA/2014/00474/4 - CompletedApplication - Construction of new works, Maintenance of existing works Asset Recovery Programme - URN 1157 Constantine Bay - Cornwall Council Location 1, Location 2, Location 3Cornwall County Council 25 Sep 201419 Mar 2015
MLA/2014/00476/1 - CompletedApplication - Removals (inc. Grab Samples) Archaeological investigation of Hazardous Prize 1706 - a protected wreck at risk Intertidal foreshore of Bracklesham Bay Beach area, Hazardous Prize 1705 designated area defined under the Protection of Wrecks Act Warship Hazardous Prize Project Group 26 Sep 201428 Jul 2016
MLA/2014/00478 - CompletedApplication - Navigational dredging (capital)215/009 - Dredging at Halls Wharf, NorthfleetDredge Area Cemex Uk01 Oct 201401 May 2015
MLA/2014/00479 - WithdrawnApplication - Construction of new worksRoyal Wharf Ballymore Properties Limited02 Oct 2014
MLA/2014/00481 - CompletedApplication - Maintenance of existing worksRebuilding of Breakwater Combe MartinCombe Martin Breakwater Combe Martin Parish Council 06 Oct 201420 Oct 2014
MLA/2014/00482/1 - CompletedApplication - Dredged Material DisposalPort of Blyth Maintenance Dredge disposal licence renewalBLYTH A + B [1] Blyth Harbour Commission07 Oct 201408 Jun 2018
MLA/2014/00483 - CompletedApplication - Construction of new works, Maintenance of existing works Weymouth Harbour Pontoon Replacement and Minor AdditionReplacement pontoons, New pontoon fingers Weymouth Harbour08 Oct 201409 Mar 2015
MLA/2014/00485 - CompletedApplication - Construction of new works, Other removalsDell Quay SC - Balcony and Jetty Replacement Project Dell Quay Dell Quay Sailing Club Ltd08 Oct 201419 Jan 2015
MLA/2014/00486/1 - CompletedApplication - Maintenance of existing worksSoutherham Grey Pit Bank Repair and StabilisationSoutherham Working Area Environment Agency09 Oct 201413 Jan 2015
MLA/2014/00487 - CompletedApplication - Construction of new works, Maintenance of existing works, Other removals Refurbishment of North Corner Pontoon Landing StageNorth Corner, Cornwall Beach, PlymouthPlymouth City Council 10 Oct 201414 Jan 2015
MLA/2014/00489 - CompletedApplication - Marine licence for the burial of human remains at sea NEEDLES (WI090) Mr John Lister14 Oct 201421 Oct 2014
MLA/2014/00490/1 - CompletedApplication - Maintenance of existing worksMorecambe Wind Limited - Operational Marine Licence for Inter Array Cable Repair for West of Duddon Sands Offshore Wind Farm West of Duddon Sands Wind FarmMorecambe Wind Limited14 Oct 201420 Dec 2017
MLA/2014/00492/1 - CompletedApplication - Other deposits Comparative Proof and Sentencing ConditionsQinetiQ Eskmeals RangeQinetiq Limited 16 Oct 201418 Dec 2014
MLA/2014/00494 - CompletedApplication - Maintenance of existing worksSwanscombe Marsh Headwall Improvements Swanscombe Marsh OutfallEnvironment Agency17 Oct 201412 Feb 2015
MLA/2014/00495 - CompletedApplication - Marine licence for the burial of human remains at sea NEEDLES (WI090) Mr John Lister17 Oct 201422 Oct 2014
MLA/2014/00497/1 - CompletedApplication - Maintenance of existing works, Navigational dredging (maintenance) RNLI Clovelly - Low Impact Maintenance Works (Fast Track Licence)Clovelly lifeboat station - area of maintenance activitiesRoyal National Lifeboat Institution 17 Oct 201406 Nov 2014
MLA/2014/00498 - CompletedApplication - Disposal of dredged material Waldringfield Boatyard - disposal at sea Island disposal at sea (beneficial use) site re Waldringfield Boatyard dredgingsMr Mark Barton19 Oct 201418 Mar 2015
MLA/2014/00500/1 - CompletedApplication - Decommissioning of works lowestoft redundant tide guage removal lowestoft redundant tide guageEnvironment Agency - Anglian Region 20 Oct 201418 Mar 2015
MLA/2014/00501 - CompletedApplication - Construction of new worksPontoon extension Inner HarbourWell HarbourWells Harbour Commissioners 21 Oct 201406 Jan 2015
MLA/2014/00502/3 - CompletedApplication - Maintenance of existing worksBlue Transmission London Array Ltd. - Marine Licence and Cable Protection Works at BritNed CrossingCable Protection Works at London Array Offshore Wiind Farm BritNed Crossing Blue Transmission London Array Limited21 Oct 201408 Jul 2015
MLA/2014/00503 - CompletedApplication - Marine licence for the burial of human remains at sea NEWHAVEN (WI011)Arthur C Towner Ltd 22 Oct 201423 Oct 2014
MLA/2014/00504 - CompletedApplication - Disposal of dredged material Disposal of dredgings - Loder's Cut Island Loder's Cut islandMr Tam Grundy 22 Oct 201418 Mar 2015
MLA/2014/00505 - CompletedApplication - Maintenance of existing worksRNLI Falmouth - Low Impact Maintenance Works (Fast Track Licence)Area of Pontoon Berth, Area of SlipwayRoyal National Lifeboat Institution 22 Oct 201414 Nov 2014
MLA/2014/00506/1 - CompletedApplication - Construction of new worksNorth Portsea CFERM Scheme - Phase 1 works North Portsea Island CFERM scheme - Phase 1 Eastern Solent Coastal Partnership23 Oct 201419 Oct 2015
MLA/2014/00507/1 - CompletedApplication - Sampling Central Promenade - Ground Investigation Work Grouped under: Whitley Bay Promenade Regeneration Project Showing 2 of 2 cases Central Promenade GI site boundaryNorth Tyneside Council23 Oct 201415 Jan 2015
MLA/2014/00508/1 - CompletedApplication - Construction Harrowside Beach Outfall Grill Repairs Harrowside Beach Outfall Grill Working Area United Utilities Plc23 Oct 201427 Jan 2015
MLA/2014/00510/1 - CompletedApplication - Maintenance of existing worksSea Line 3 & Replacement Sea Line Seaward Section Condition Assessment (Sellafield, Cumbria) Sellafield Beach. Sellafield Limited24 Oct 201413 Jul 2016
MLA/2014/00511/3 - CompletedApplication - Disposal of dredged material, Navigational dredging (maintenance), Other depositsBrighton Marina Dredge Brighton Marina, BRIGHTON/ ROTTINGDEAN (WI020), Temporary Disposal Duct Premier Marinas (Brighton) Limited24 Oct 201426 Aug 2022
MLA/2014/00512/1 - CompletedApplication - Construction of new worksCongresbury Yeo Tidal BanksPlacemark Environment Agency – South West Reg 27 Oct 201412 Apr 2016
MLA/2014/00513/2 - CompletedApplication - Wrecks and other archaeological remainsRhoda Mary SchoonerHoo MarinaWorking Sail Ltd29 Oct 201418 May 2017
MLA/2014/00514/1 - CompletedApplication - Maintenance of existing worksOwston Ferry Riverbank Stabilisation works Owston FerryEnvironment Agency - Midlands Region29 Oct 201404 Jun 2015
MLA/2014/00515 - CompletedApplication - Maintenance of existing worksHungerford Bridge RepairsHungerford (Charing Cross) Rail BridgeCostain Group Plc 30 Oct 201430 Jan 2015
MLA/2014/00516 - CompletedApplication - Construction of new worksEgerton Park Outfall Extension Egerton Park OutfallEnvironment Agency30 Oct 201430 Jan 2015
MLA/2014/00517 - CompletedApplication - Maintenance of existing worksGreenwich River Wall works Greenwich WallRsk Environment Limited 30 Oct 201416 Jan 2015
MLA/2014/00518 - CompletedApplication - Other worksSlipway development Thorney Island in Chichester Harbour Thorney Island Sailing Club, Thorney Island Channel Chichester Harbour, Baker Barracks, Emsworth, Hants,Army Sailing Association30 Oct 201411 Jun 2015
MLA/2014/00519 - CompletedApplication - Construction of new works, Maintenance of existing works Wall Reconstruction - Town Quay, Poole Town Quay & Fisherman's Marina, Poole Poole Harbour Commissioners 30 Oct 201429 Jan 2015
MLA/2014/00520 - CompletedApplication - Maintenance of existing worksRNLI Salcombe (ILB Slipway) - Low Impact Maintenance Works (Fast Track Licence)Area of ILB Slipway - SalcombeRoyal National Lifeboat Institution 31 Oct 201421 Nov 2014
MLA/2014/00521/1 - CompletedApplication - Construction of new worksRNLI Bridlington Seawall Works Bridlington seawall works Rnli31 Oct 201406 Aug 2015
MLA/2014/00523/2 - CompletedApplication - Construction of new worksR Lym YC Pontoon replacement and maintenance Lymington river Royal Lymington Yacht Club31 Oct 201430 Oct 2015
MLA/2014/00524 - CompletedApplication - Removals (inc. Grab Samples) Silvertown Tunnel - Ground Investigation Works River Thames between Greenwich Peninsula and Silvertown Transport For London31 Oct 201401 Dec 2014
MLA/2014/00525 - CompletedApplication - Construction Conservation off-shore pile foundation approach bridge C.RO Ports Purfleet Grouped under: C.RO Ports Purfleet terminal Showing 3 of 5 casesC.RO Ports Purfleet berthsCdmr Purfleet Limited 03 Nov 201404 Jun 2015
MLA/2014/00526 - CompletedApplication - Construction of new worksHumber Gateway Offshore Wind Farm - Transmission Assets Grouped under: Humber Gateway Offshore Wind Farm Showing 5 of 10 cases Humber Gateway OWF Transmission AssetsE.On Climate & Renewables Uk Humber Wind Limited03 Nov 201405 Aug 2015
MLA/2014/00528 - CompletedApplication - Maintenance of existing worksChilling Lane, Warsash Grouped under: Solent Breezes Showing 2 of 2 casesChilling, Warsash Mr David Foster 05 Nov 201428 Nov 2014
MLA/2014/00529/1 - CompletedApplication - Maintenance of existing worksTyne Tanker Berth, C1 Repairs and Bollard Upgrades (2014)Tyne Tanker Berth Port Of Tyne Authority05 Nov 201414 Dec 2015
MLA/2014/00532 - CompletedApplication - Maintenance of existing worksNewhaven Swing Bridge Mechanical and Electrical RefurbishmentNewhaven Swing Bridge East Sussex County Council06 Nov 201420 Nov 2014
MLA/2014/00533 - CompletedApplication - Other worksImprovement to Existing Boatslip at 79/81 Brighton Road, Shoreham by Sea 79 / 81 Brighton Road W.N. Developments Limited 07 Nov 201401 May 2015
MLA/2014/00535 - CompletedApplication - Construction of new works, Other depositsTwo Tree Island Slipway RepairsTwo Tree Island slipway Southend-On-Sea Borough Council 13 Nov 201406 Feb 2015
MLA/2014/00536 - CompletedApplication - Maintenance of existing worksRepair granite steps and ancillary parts of landing stage and maintain sea wallRoyal Fowey Yacht ClubRoyal Fowey Yacht Club15 Nov 201412 Mar 2015
MLA/2014/00538 - CompletedApplication - Maintenance of existing worksNorth Haven Slipway Repair Sandbanks, PooleThe Bournemouth Swanage Motor Road And Ferry Compnay Inc17 Nov 201420 Nov 2014
MLA/2014/00539 - CompletedApplication - Sampling Central Promenade - Ground Investigation Work (Trial Pits Only) Grouped under: Whitley Bay Promenade Regeneration Project Showing 2 of 2 cases Central Promenade Ground Investigation site boundary - Trial Pits North Tyneside Council18 Nov 201415 Jan 2015
MLA/2014/00541 - CompletedApplication - Other deposits 11kv cable replacement St Micheals Mount Marazion Cornwall marazionWestern Power Distribution Limited18 Nov 201424 Nov 2014
MLA/2014/00542 - CompletedApplication - Construction of new worksWatersideWaterside Waterside Cowes Limited 19 Nov 201401 Apr 2015
MLA/2014/00543/1 - CompletedApplication - Other removals Medmerry Groyne RemovalMedmerry Working Area Environment Agency (Southern Region)19 Nov 201427 Feb 2015
MLA/2014/00544 - CompletedApplication - Maintenance of existing worksMevagissey Culvert Culvert South West Water Limited20 Nov 201408 Apr 2015
MLA/2014/00545 - CompletedApplication - Construction of new works, Other works EXTENSION OF EXISTING MUSSEL SITE ST.AUSTELL BAY EXTENSION OF MUSSEL FARM, NEW PROPOSALFowey Sea Farms Ltd 21 Nov 201408 Oct 2015
MLA/2014/00546/1 - CompletedApplication - Navigational dredging (maintenance)Annual spot dredging on the Ribble Link canal Canal & River Trust 24 Nov 201417 Feb 2015
MLA/2014/00547 - CompletedApplication - Construction of new worksTower of London ForeshoreTower of London Foreshore Historic Royal Palaces24 Nov 201402 Apr 2015
MLA/2014/00548 - CompletedApplication - Maintenance of existing worksWhitby Saline RemovalWhitby Harbour Wall J.N. Bentley Limited25 Nov 201402 Feb 2015
MLA/2014/00549 - CompletedApplication - Maintenance of existing worksPile Replacement Pile No.1 on end of C Pontoon, Pile No.2 on end of D Pontoon, Pile No.5 on India PontoonHornet Sailing Club 25 Nov 201426 May 2015
MLA/2014/00552/1 - CompletedApplication - Aggregate dredging Area 501 Marine Aggregate Application Westminster Gravels Limited 26 Nov 201425 Jun 2024
MLA/2014/00553/2 - CompletedApplication - Maintenance of existing works, Other works Shoeburyness Emergency Flood Defence Works FO-13, FO-14, 14A, & 15, FO-16, FO-17, FO-18, FO-19 Qinetiq 26 Nov 201422 Jun 2016
MLA/2014/00554 - CompletedApplication - Maintenance of existing worksMaintenance of Embankment and OutfallSimon Riverside Ltd Simon Riverside Limited 27 Nov 201413 Feb 2015
MLA/2014/00555/2 - CompletedApplication - Maintenance of existing worksDONG Energy Westermost Rough Limited - Operational Marine Licence for Inter Array Cable Repair for Westermost Rough Offshore Wind Farm Westermost Rough Offshore Wind Farm siteOrsted Westermost Rough Limited 27 Nov 201430 Jun 2022
MLA/2014/00556/1 - CompletedApplication - Construction, Dredged Material Disposal, DredgingHarrowside Outfall Harrowside Long Sea Outfall Working Area, MORECAMBE BAY: LUNE DEEP (IS170)United Utilities27 Nov 201409 Jul 2015
MLA/2014/00557 - CompletedApplication - Maintenance of existing worksSouth Railway Jetty Fender and Backboard InstallationSouth Railway Jetty Bae Systems Plc 27 Nov 201411 Mar 2015
MLA/2014/00558/1 - CompletedApplication - Construction of new works, Decommissioning of works, Other removals24 Church road , Mylor - pontoon and gangway installationPontoon installationMr Tony Murtagh 27 Nov 201413 Jul 2015
MLA/2014/00559 - CompletedApplication - Maintenance of existing works, Other works Bridge Street OutfallOutfall, Access to OutfallNorthumbrian Water Limited27 Nov 201416 Feb 2015
MLA/2014/00562 - CompletedApplication - Construction of new worksPortishead Quays Marina - Pontoon ExtensionPortishead Quays Marina - Area 1, Portishead Quays Marina - Area 2Quay Marinas Limited28 Nov 201416 Jul 2015
MLA/2014/00563/2 - CompletedApplication - Construction of new works, Other depositsPerpetuus Tidal Energy Centre (PTEC) PTEC Demonstrator Site, PTEC Export Cable Perpetuus Tidal Energy Centre Limited 29 Nov 201429 Apr 2021
MLA/2014/00564 - CompletedApplication - Construction of new worksSkinningrove Coastal Protection WorksSkinningrove site Redcar & Cleveland Borough Council01 Dec 201416 Feb 2015
MLA/2014/00565 - CompletedApplication - Maintenance of existing worksWheatcroft Outfall Repair Grouped under: Wheatcroft Long Sea Outfall Showing 2 of 7 casesWheatcroft LSOYorkshire Water Services Limited01 Dec 201412 Mar 2015
MLA/2014/00566/2 - CompletedApplication - Construction, Dredging, Removals (inc. Grab Samples) Thames Oilport Jetties 1 to 5Jetty 5 [1], Jetty 3 [1], Jetty 1 [1], Jetty 2 [1], Jetty 4 [1] Morzine Limited 02 Dec 201417 Feb 2020
MLA/2014/00567 - CompletedApplication - Construction of new worksHeadland and Block Sands Coastal Protection Scheme HeadlandHartlepool Borough Council03 Dec 201417 Apr 2015
MLA/2014/00568 - CompletedApplication - Maintenance of existing worksrepair to sea wall/coastal slope Appledore North Devon to safeguard south west coast pathAppledore WestDevon County Council04 Dec 201411 Feb 2015
MLA/2014/00570 - CompletedApplication - Construction of new worksSwanwick Marina piles at X & A Swanwick Marina piles at X and APremier Marinas (Hamble) Limited05 Dec 201409 Mar 2015
MLA/2014/00571 - CompletedApplication - Other deposits PLAT-O Prototype - Testing at Yarmouth Grouped under: PLAT-O Prototype - Testing at Yarmouth Showing 3 of 3 cases Sustainable Marine Energy Limited 08 Dec 201427 Mar 2015
MLA/2014/00572 - CompletedApplication - Maintenance of existing worksQueens Wharf & Riverside Studios Queens Wharf Riverside StudiosMount Anvil Plc 08 Dec 201410 Mar 2015
MLA/2014/00573/3 - CompletedApplication - Disposal of dredged material, Navigational dredging (maintenance)Liverpool Docks Maintenance Disposal SITE Z (IS140), MERSEY (MID-RIVER SITE) (IS120), Seaforth Dock, Canada Dock, Huskisson Dock, Langton Dock, Gladstone Dock Mersey Docks & Harbour Company08 Dec 201413 Nov 2019
MLA/2014/00574/1 - CompletedApplication - Construction of new worksExtension to Musselfarm, St Austell BayCornwall Mussel FarmWest Country Mussels Of Fowey Limited 09 Dec 201415 Dec 2020
MLA/2014/00575 - CompletedApplication - Construction of new works, Other dredging, Other removalsNorthern Link Walker QuayNorthern Link Walker Quay Newcastle City Council09 Dec 201427 Aug 2015
MLA/2014/00576 - CompletedApplication - Construction of new worksPort of Dover Berth 7 Fender Replacement Port of Dover ED7 Dover Harbour Board 09 Dec 201430 Apr 2015
MLA/2014/00577 - CompletedApplication - Navigational dredging (maintenance)St. George Wharf Pier Dredging St. George Wharf Pier St George South London09 Dec 201425 Feb 2015
MLA/2014/00579 - CompletedApplication - Maintenance of existing worksPontoon Replacement - Port of Ramsgate - Outer West Marina Grouped under: Port of Ramsgate Pontoon Replacement Showing 2 of 2 casesPontoon Replacement Port Of Ramsgate10 Dec 201413 Mar 2015
MLA/2014/00580 - CompletedApplication - Miscellaneous Disposal Teesside Offshore Wind FarmTeesside Offshore Wind Farm Teesside Windfarm Limited 10 Dec 201417 Mar 2015
MLA/2014/00581/2 - CompletedApplication - Other dredging Wallasea Island Wild Coast Project (Cell 1 Existing Sea Walls Breaching) Grouped under: Wallasea Island Wild Coast Project (Cell 5 Regulated Tidal Exchange Lagoon) Showing 2 of 4 cases Wallasea Island Wildcoast Project (Cell 1, Breach 1), Wallasea Island Wildcoast Project (Cell 1, Breach 2), Wallasea Island Wildcoast Project (Cell 1, Breach 3)Bam Nuttall Limited 10 Dec 201409 Jul 2015
MLA/2014/00582 - CompletedApplication - Other removals Universal Marina - Removal of High level Jetty Universal Marina High Level Jetty John Willment Marine Limited11 Dec 201411 May 2015
MLA/2014/00584 - CompletedApplication - Disposal of dredged material, Other removals Clevedon Marine Lake Repair WorksClevedon Marine Lake, Clevedon Lake (LU067) North Somerset District Council 11 Dec 201412 May 2015
MLA/2014/00585/3 - CompletedApplication - Alternative use of dredged materialLittlestone Beach ReplenishmentLittlestone Beach deposition site Environment Agency-Southern Region12 Dec 201402 Mar 2016
MLA/2014/00586 - CompletedApplication - Construction of new worksBen Ainslie Racing Pontoon BAR Ben Ainslie Racing15 Dec 201429 Apr 2015
MLA/2014/00587 - CompletedApplication - Construction of new worksLanding berths Grouped under: Master case for construction of ladder Hartlepool Quay Showing 2 of 2 casesVictoria Dock HartlepoolHartlepool Fishco Ltd 15 Dec 201416 Feb 2015
MLA/2014/00588 - CompletedApplication - Other worksInstallation of sea plug, into cooling water outfall, at Heysham B Power Station, and subsequent removal Middleton Sands, around Red Nab Edf Energy Nuclear Generation Limited 16 Dec 201422 Jan 2015
MLA/2014/00589 - CompletedApplication - Other deposits Mooring Buoy alongside No Man's Land Fort Grouped under: No Man's Land Island mooring Showing 2 of 2 cases NMLF Buoy Clarenco Llp17 Dec 201419 Feb 2015
MLA/2014/00591 - CompletedApplication - Construction of new worksFalmouth Marina Dry Stack PontoonFalmouth Marina Drystack PontoonPremier Marinas (Falmouth) Limited18 Dec 201414 May 2015
MLA/2014/00592/5 - Variation RequestedApplication - Dredged Material Disposal, DredgingABP Southampton - Maintenance Dredge Licence River Itchen Berths and Approaches, Southampton Water, River Test Berths and Channels, Nab Channel, Solent Approaches, NAB TOWER (WI060)Associated British Ports, Southampton 18 Dec 201402 Sep 2024
MLA/2014/00593/3 - CompletedApplication - Construction of new worksInfill of Part of William Wright Dock, Port of HullPartial Infill William Wright DockAssociated British Ports Holdings Limited 19 Dec 201419 Oct 2015
MLA/2014/00594 - CompletedApplication - Maintenance of existing worksHellarcher Outfall Hellarcher OutfallSouth West Water Limited19 Dec 201410 Mar 2015
MLA/2014/00595 - CompletedApplication - Construction of new worksArnside - Scour Protection Arnside - Scour ProtectionStory Contracting Limited 19 Dec 201422 May 2015
MLA/2014/00596/1 - CompletedApplication - Dredged Material Disposal, DredgingMaintenance Dredging of Burgh Castle MarinaBurgh Castle Marina, River Waveney midstreamBurgh Castle Marina 19 Dec 201431 Oct 2018
MLA/2014/00597 - CompletedApplication - Wrecks and other archaeological remainsVictory Shipwreck Project The Maritime Heritage Foundation19 Dec 201416 Jul 2020
MLA/2014/00598 - CompletedApplication - Other worksMorecambe WwTW Outfall Site Investigation WorksOption 2 Heysham Lake, cable percussive drilling via Haagland, Option 1 Middleton Sands, Option 2 Heysham Lake, cable percussive drilling via jackup platform, Option 2 Heysham Lake, cable percussive drilling via Haagland area 2, option 3 - Red Nab United Utilities22 Dec 201422 Jun 2015
MLA/2014/00599 - CompletedApplication - Other worksURN 1550e Parrett at Stathe - West Sedgemoor Pumping Station Scour holeEnvironment Agency - South West Region22 Dec 201402 Feb 2015
MLA/2014/00600/1 - CompletedApplication - Construction Shoreham Viaduct Strengthening Works Part 1Shoreham ViaductBam Nuttall Limited 23 Dec 201410 Sep 2015
MLA/2014/00601 - CompletedApplication - Construction of new worksOcean Business 2015Empress Dock, Southampton Mr Keith Birch23 Dec 201420 Mar 2015
MLA/2014/00602/1 - CompletedApplication - Navigational dredging (maintenance)MAINTENANCE DREDGING OF GRAIN LNG JETTIES 8 & 10 Grouped under: Isle of Grain maintenance dredging Showing 2 of 3 casesGRAIN LNG JETTY 8, GRAIN LNG JETTY 10 National Grid Grain Lng Ltd 29 Dec 201419 Jul 2023
MLA/2014/00603 - CompletedApplication - Maintenance of existing worksSpragger Clough Gate Repairs Spragger Clough Outfall Carter Jonas Llp31 Dec 201421 Jan 2015