As the results of a freedom of information request, the Tees Valley Combined Authority (TVCA) issued this list of groundworks.

N.B. One question that TVCA were unable to answer for all works has been removed. The question “Please supply any risk assessments carried out pertaining to these works” where the answer from TVCA for all groundworks was “Risk assessments pertaining to the works are prepared and by the construction contractor. Therefore, we do not hold this information”.

SubjectWhat are the commencement and completion dates of each section of work / demolition covered in 13 to 16What were the exact works involved in 13 to 16Please supply details of all considerations pertaining to human and environmental risks carried out pre , during and post works of 13 to 16 inclusively
South Bank
South Bank Quay Phase 1Construction commencement: 04-Oct-21 Construction completion: 05-Dec-23Construction of a new quay wall of 450m length plus 100m transitions at either end (combi-wall construction typology), to create a new deep-water port facility, inclusive of capital dredging works to the river channel, the turning circle and the berth pocket in front of the quay, where a significant proportion of dredged material was designated for onshore disposal under the Marine Licence, which was duly done, and the remainder permitted to be disposed of at sea.Pre-works: these documents are publicly available and therefore exempt from disclosure under Section 21 of the Freedom of Information Act 2000.
During the works: Monitoring for compliance with the conditions applicable to the various publicly available consents for the works is undertaken and the respective regulatory bodies undertake their own audits for compliance.
Post-works: The works are not yet complete.
Site Preparation and Ground Remediation Works
Area C (GE Blade Manufacturing Facility site)Construction commencement: 07-Jun-21 Construction completion: 31-Mar-22Ground remediation works involving the excavation of the existing ground down to 7.5m AOD and the reprocessing of earthworks materials for re-use as engineering fill to the site, where the site was brought back up to a level of 9.25m AOD utilising layers of reprocessed slag, crushed concrete, and natural rock, all in accordance with the Materials Management Plan issued under the CL:AIRE DoW:CoP protocol, as approved by the Environment Agency.Pre-works: these documents are publicly available and therefore exempt from disclosure under Section 21 of the Freedom of Information Act 2000.
During the works: Monitoring for compliance with the conditions applicable to the various publicly available consents for the works was undertaken throughout their duration, inclusive of earthworks materials testing and analysis, materials re-use records, etc.
Post-works: A validation report was prepared by the appointed technical consultant in confirmation of satisfactory completion of the works.
Area B1 (Land immediately behind South Bank Quay Phase 1)Construction commencement: 02-Aug-21 Construction completion: 03-Dec-21Excavation works to the hinterland behind the proposed South Bank Quay Phase 1, to lower ground levels in readiness for the construction of the quay. As South Bank Quay is an inland quay, constructed on land, the excavation works were set back from the Mean High- Water Line (the river edge) by some 20 metres, and there was, therefore, no direct interaction with the river environment. All the material excavated as part of these earthworks was reprocessed and utilised as engineering fill material inn site preparation works on the South Bank land zone, including on land set back from the proposed quay and the above referenced Area C, in accordance with the approved Materials Management Plan issued under the CL:AIRE DoW:CoP protocol, as approved by the Environment Agency.Pre-works: these documents are publicly available and therefore exempt from disclosure under Section 21 of the Freedom of Information Act 2000.
During the works: Monitoring for compliance with the conditions applicable to the various publicly available consents for the works was undertaken throughout their duration, inclusive of earthworks materials testing and analysis, materials re-use records, etc.
Post-works: The area was handed over to the contractor for the construction of South Bank Quay Phase 1.
Demolition Works Programme
Heavy Fuel Oil Tank Farm and Buildings at South BankDemolition commencement: 01-Sep-20 Demolition completion: 30-Apr-21Decanting of residual heavy fuel oil deposits from within redundant storage tanks, and disposal off-site for incineration. Cleaning of tanks and demolition of the facility to ground level. Demolition methods largely comprised mechanical shearing.Pre-works: Risk assessments pertaining to the works are prepared and by the construction contractor. Therefore, we do not hold this information.
During the works: Environmental monitoring pertaining to the works are prepared and by the construction contractor. Therefore, we do not hold this information.
Post-works: Demolition works, no requirement for post-completion environmental considerations.
Advance Demolitions, Redcar (the Foundry and NZT sites)Demolition commencement: 01-Mar-21 Demolition completion: 26-Nov-22Demolition to ground level of a range of shed buildings and bulk raw materials conveyor systems and junction houses. Demolition methods largely comprised mechanical shearing and explosive blowdown.Pre-works: Risk assessments pertaining to the works are prepared and by the construction contractor. Therefore, we do not hold this information.
During the works: Environmental monitoring pertaining to the works are prepared and by the construction contractor. Therefore, we do not hold this information.
Post-works: Demolition works, no requirement for post-completion environmental considerations.
Primary Demolition Programme
Stock Houses and Area WorkshopsDemolition commencement: 18-Apr-21 Demolition completion: 31-Mar-23Demolition to ground level of buildings, bulk raw materials storage bunkers, pipelines, and pipe bridges, including decanting of product from pipelines and offsite disposal. Demolition methods largely comprised mechanical shearing and explosive blowdown.Pre-works: Risk assessments and method statements pertaining to the works were prepared by the construction contractor/ Therefore, we do not hold this information.
During the works: Environmental monitoring was undertaken by the contractor during the currency of the works, such as dust and air quality monitoring. Therefore, we do not hold this information.
Post-works: Demolition works, no requirement for post-completion environmental considerations.
South Bank Coke Ovens By-Products PlantDemolition commencement: 04-Oct-21 Demolition completion: 10-Mar-23Cleaning/decontamination of vessels and pipelines to remove residual CoMAH products, and disposal offsite to approved facilities for incineration or other treatment. Demolition to ground level of all assets including buildings, vessels, pipelines, and pipe bridges. Demolition methods largely comprised mechanical shearing and explosive blowdown.Pre-works: Risk assessments pertaining to the works are prepared and by the construction contractor. Therefore, we do not hold this information.
During the works: Environmental monitoring was undertaken by the contractor during the currency of the works, such as dust and air quality monitoring. Therefore, we do not hold this information.
Post-works: Demolition works, no requirement for post-completion environmental considerations.
South Bank Coke Ovens Battery FacilityDemolition commencement: 07-Jun-21 Demolition completion: 30-Nov-21Demolition to ground level of coke ovens battery and related plant and facilities, including cleaning and decontamination of certain assets, where necessary, prior to their demolition. Demolition methods largely comprised mechanical shearing and explosive blowdown.Pre-works: Risk assessments pertaining to the works are prepared and by the construction contractor. Therefore, we do not hold this information.
During the works: Environmental monitoring was undertaken by the contractor during the currency of the works, such as dust and air quality monitoring. Therefore, we do not hold this information.
Post-works: Demolition works, no requirement for post-completion environmental considerations.
BOS PlantDemolition commencement: 03-May-21 Demolition completion: 26-May-23Demolition to ground level of former steelmaking facility, comprising large scale industrial shed buildings, by methods largely comprising mechanical shearing and explosive blowdown.Pre-works: Risk assessments pertaining to the works are prepared and by the construction contractor. Therefore, we do not hold this information.
During the works: Environmental monitoring was undertaken by the contractor during the currency of the works, such as dust and air quality monitoring. Therefore, we do not hold this information.
Post-works: Demolition works, no requirement for post-completion environmental considerations.
BOS Plant COGMDemolition commencement: 02-Aug-21 Demolition completion: 25-Mar-22Cleaning and decontamination of pipelines, with recovered products disposed of offsite to appropriate facilities for incineration or other treatmentPre-works: Risk assessments pertaining to the works are prepared and by the construction contractor. Therefore, we do not hold this information.
During the works: Environmental monitoring was undertaken by the contractor during the currency of the works, such as dust and air quality monitoring. Therefore, we do not hold this information.
Post-works: Demolition works, no requirement for post-completion environmental considerations.
Redcar Blast FurnaceDemolition commencement: 01-Nov-21 Demolition completion: 09-Jun-23Demolition to ground level of blast furnace and related plant and facilities, including cleaning and decontamination of certain assets (pipelines), where necessary, prior to their demolition. Demolition methods largely comprised mechanical shearing and explosive blowdown.Pre-works: Risk assessments pertaining to the works are prepared and by the construction contractor. Therefore, we do not hold this information.
During the works: Environmental monitoring was undertaken by the contractor during the currency of the works, such as dust and air quality monitoring. Therefore, we do not hold this information.
Post-works: Demolition works, no requirement for post-completion environmental considerations.
Redcar Coke Ovens Battery FacilityDemolition commencement: 06-Sep-21 Demolition completion: 31-Jan-23Demolition to ground level of coke ovens battery and related plant and facilities, including cleaning and decontamination of certain assets, where necessary, prior to their demolition. Demolition methods largely comprised mechanical shearing and explosive blowdown.Pre-works: Risk assessments pertaining to the works are prepared and by the construction contractor. Therefore, we do not hold this information.
During the works: Environmental monitoring was undertaken by the contractor during the currency of the works, such as dust and air quality monitoring. Therefore, we do not hold this information.
Post-works: Demolition works, no requirement for post-completion environmental considerations.
Redcar Coke Ovens By-Products PlantDemolition commencement: 06-Dec-21 Demolition completion: 16-Jun-23Cleaning/decontamination of vessels and pipelines to remove residual CoMAH products, and disposal offsite to approved facilities for incineration or other treatment. Demolition to ground level of all assets including buildings, vessels, pipelines, and pipe bridges. Demolition methods largely comprised mechanical shearing and explosive blowdown.Pre-works: Risk assessments pertaining to the works are prepared and by the construction contractor. Therefore, we do not hold this information.
During the works: Environmental monitoring was undertaken by the contractor during the currency of the works, such as dust and air quality monitoring. Therefore, we do not hold this information.
SubjectWhat are the commencement and completion dates of each section of work / demolition covered in 13 to 16What were the exact works involved in 13 to 16Please supply details of all considerations pertaining to human and environmental risks carried out pre , during and post works of 13 to 16 inclusively
Post-works: Demolition works, no requirement for post-completion environmental considerations.
Redcar Sinter PlantDemolition commencement: 02-Aug-21 Demolition completion: 27-Jan-23Demolition to ground level of large scale industrial shed buildings, by methods largely comprising mechanical shearing and explosive blowdown. During the works: Environmental monitoring was undertaken by the contractor during the currency of the works, such as dust and air quality monitoring. Therefore, we do not hold this information.
Post-works: Demolition works, no requirement for post-completion environmental considerations.
Redcar Power StationDemolition commencement: 28-Feb-22 Demolition completion: 29-Sep-23Demolition to ground level of large scale industrial shed buildings and related plant and facilities, including cleaning and decontamination of certain assets, where necessary, prior to their demolition. Demolition methods largely comprised mechanical shearing and explosive blowdown.Pre-works: Risk assessments pertaining to the works are prepared and by the construction contractor. Therefore, we do not hold this information.
During the works Environmental monitoring was undertaken by the contractor during the currency of the works, such as dust and air quality monitoring. Therefore, we do not hold this information.
Post-works: Demolition works, no requirement for post-completion environmental considerations.
Net Zero Teesside Site
Ground Remediation WorksConstruction commencement: 03-Apr-23 Construction completion: 26-Apr-24Ground remediation works involving the excavation of the existing ground down to levels of 4.8m AOD in parts of the site, 3.8m AOD in one area, and to shallower depths elsewhere. Reprocessing of earthworks materials for re-use as engineering fill to the site, where the site will be brought back up to a level of 7.3m AOD utilising layers of reprocessed slag, crushed concrete, and natural rock, all in accordance with the Waste Recovery Plan submitted as part of the application for a permit from the Environment Agency and the conditions attached to the EA's Local Enforcement Position (LEP) for the works. The works have not yet commenced.Pre-works: these documents are publicly available and therefore exempt from disclosure under Section 21 of the Freedom of Information Act 2000.
During the works: Monitoring for compliance with the conditions applicable to the various publicly available consents for the works will be undertaken throughout their duration, inclusive of earthworks materials testing and analysis and groundwater monitoring, materials re-use records, etc.
Post-works: A validation report will be prepared by the appointed technical consultant in confirmation of satisfactory completion of the works, groundwater monitoring will be undertaken post- completion for period to be agreed with the EA.
GE Blade Manufacturing Facility, South Bank
Construction of facilityThis was to be a tenant development project that never proceeded. The site was taken over by SeAH Wind. The SeAH Wind development project dates are: Commencement: 01-Jul-22 Completion: 31-Dec-24The works involve the construction of a new monopile manufacturing facility by SeAH. This is not an STDC/Teesworks project. The land is being leased to SeAH for the purposes of the construction and operation of their facility. STDC/Teesworks was not involved in the consenting and planning for the project. These are not matters for STDC/ Teesworks. This is a tenant project where all such assessments would be prepared by SeAH and their delivery supply chain. We are therefore not in possession of any relevant documents.
Key Risks to Delivery With reference to number 17…please state what is meant by this paragraph and what were the mitigation processes and delivery issues
As the Board paper states, this relates to the risks to delivery to programme. The mitigating processes include the appointment of appropriately experienced project management consultants to manage delivery of the various projects such as are covered above, the development of robust project delivery schedules and the implementation of appropriate project controls. Delivery issues on construction projects typically include the availability of construction materials, particularly long-lead items, and their potential impact on schedule. On demolition projects, the primary delivery issue has been the availability of offsite routes to market for the safe disposal of recovered waste CoMAH substances from the cleaning and decontamination of assets prior to demolition.