MLA/2015/00334 - updated 25th May 2024
Initial Application - Submitted 29-Jul-2015
Case ref: MLA/2015/00334/12
Licence ref: L/2017/00012/10
Project title
Able Seaton Port berths, Holding Basin and Channel
Project background
Requesting new licence to replace previous one L/2012/00160/8.
Objective is to improve access into Able Seaton Port by deepening approach channel and maintaining access thereafter.
The facility is an emerging business and works will be undertaken on demand in accordance with commercial developments.
Programme of works
There is an immediate need (Q1/2017) to dredge the approach channel and holding to -6.5mCD in order to receive the Shell Brent Delta module.
As discussed at a meeting with MMO (Adam Chumley/Matthew Kinmond) on 26/10/16, further dredging campaigns will be undertaken in response to commercial demand.
Volumes of material to be dredged and disposed of are given in the attached spreadsheet.
Dredging to be undertaken on a 24/7 basis to maximise use of plant.
Other information
Applicant details
Mr Colin Harrison / +44 (0)1642 806 080 / charrison@ableuk.com
ABLE UK LTD / ABLE HOUSE BILLINGHAM REACH INDUSTRIAL ESTATE HAVERTON HILL ROAD BILLINGHAM / TS23 1PX
View application and documents
MLA/2015/00334
Response Documents - Licence L/2017/00012/1
File | Date |
Licence schedule 5 Channel Dredging Slope Failure Contingency Plan.pdf 36 KB | 17-Jan-2017 |
Schedule 6 MLA Volumes to -9.5mCD-Rev C .pdf 78 KB | 18-Jan-2017 |
Returns.pdf 13 KB | 02-Mar-2017 |
Decision Letter (Marine).pdf 642 KB | 02-Mar-2017 |
Marine Coordinate Schedules.pdf 8 KB | 02-Mar-2017 |
Licence Document (Marine).pdf 89 KB | 02-Mar-2017 |
Additional Documents
File | Date |
3 EIS Appendices (3).pdf 31 MB | 29-Jul-2015 |
ASC-001-00006 A Seaton Channel MMO Application 2015.pdf 868 KB | 29-Jul-2015 |
ASC-001-00007 A Dredge Volumes 2015.pdf 2 MB | 29-Jul-2015 |
Appendix 20.4 - CEFAS results data sheets etc.pdf 1 MB | 29-Jul-2015 |
99_263-Model ASP atest Soundsings 1 of 2.pdf 2 MB | 29-Jul-2015 |
99a_200-Model (2).pdf 741 KB | 29-Jul-2015 |
501 - Water FD MASTER.pdf 1 MB | 18-May-2016 |
Sample Results 20.04.2016.xlsm 540 KB SAM/2015/00048 08/02/2016 Seaton Harbour and Channel | 18-May-2016 |
502 - Waste FD MASTER.pdf 1 MB | 18-May-2016 |
502 - Waste FD MASTER.pdf 1 MB | 18-May-2016 |
Appendix 16.1a - DNV Report Rev1 2004.pdf 6 MB | 01-Nov-2016 |
Appendix 16.1b - DNV Addendum Report 2005.pdf 2 MB | 01-Nov-2016 |
Appendix 16.1d 2006-0416 V01 - Scenario 11 hydrodynamics.pdf 3 MB | 01-Nov-2016 |
ASC-001-00009 A Dredge Locations 2016.pdf 895 KB | 02-Nov-2016 |
99A_211.pdf 3 MB | 02-Nov-2016 |
MLA Volumes.xlsx 31 KB | 02-Nov-2016 |
MLA/2015/00334/1
Variation 1 - Submitted 15-Mar-2017 Accepted
What would you like to vary about your current licence(s)/response(s)?
To include the removal of silt sediment which has accumulated on the grounding bed situated within the Dry dock which is now open and cofferdam partially removed
Why would you like to vary your licence(s)/response(s) in this way?
To allow the precise grounding position of barges onto the grounding bed. The grounding bed is 200 meters long and 70 meters wide.Situated within the Dry Dock. In order not to disturb the Grounding Bed the operation would be carried out by divers using hand suction equipment dispersing the silt into the surrounding area within the water body. The maximum anticipate amount that may have to be removed in any campaign would be in the region of 700 dry tons. Ref. for Sampling Please see Sam/2015/00048
What date would the varied licence(s)/response(s) come into effect?
20-MAR-2017
Closed Date
07-APR-2017
Response Documents - Licence L/2017/00012/2
File | Date |
Marine Coordinate Schedules.pdf 8 KB | 07-Apr-2017 |
Decision Letter (Marine).pdf 641 KB | 07-Apr-2017 |
Licence Document (Marine).pdf 93 KB | 07-Apr-2017 |
Returns.pdf 13 KB | 07-Apr-2017 |
Additional Documents: Information box,No published documents
MLA/2015/00334/2
Response Documents - Licence L/2017/00012/3
File | Date |
Licence Document (Marine).pdf 92 KB | 18-Sep-2017 |
Returns.pdf 13 KB | 18-Sep-2017 |
Marine Coordinate Schedules.pdf 8 KB | 18-Sep-2017 |
Decision Letter (Marine).pdf 641 KB | 18-Sep-2017 |
Additional Documents: Information box,No published documents
MLA/2015/00334/3
Variation 3 - Submitted 11-Oct-2017 : Withdrawn View Variation ==== Response Documents: Information box,No published documents Additional Documents
File | Date |
20171110 SAM201700066A Able Seaton Port Berth 8 9 MMO Results Template.xlsm SAM/2017/00066/A Able Seaton Port Berth 8 & 9 02/10/2017 544 KB | 10-Nov-2017 |
|20171110 SAM201700066A Able Seaton Port Berth 8 9 MMO Results Template.xlsm SAM/2017/00066/A Able Seaton Port Berth 8 & 9 02/10/2017 544 KB | 10-Nov-2017 |
20171110 SAM201700066A Able Seaton Port Berth 8 9 MMO Results Template.xlsm SAM/2017/00066/A Able Seaton Port Berth 8 & 9 02/10/2017 544 KB | 10-Nov-2017 |
20171110 SAM201700066A Able Seaton Port Berth 8 9 MMO Results Template.xlsm SAM/2017/00066/A Able Seaton Port Berth 8 & 9 02/10/2017 544 KB | 15-Nov-2017 |
MLA/2015/00334/4
Variation 4 - Submitted 09-Feb-2018 Accepted
Response Documents - Licence L/2017/00012/4
File | Date |
Licence Schedule 7 Drawing showing the depths and coordinates of dredge areas.pdf 1 MB | 19-Oct-2018 |
Licence Document (Marine).pdf 102 KB | 09-Nov-2018 |
Decision Letter (Marine).pdf 643 KB | 09-Nov-2018 |
Returns.pdf 25 KB | 09-Nov-2018 |
Marine Coordinate Schedules.pdf 9 KB | 09-Nov-2018 |
Additional Documents
File | Date |
509 - WFD Assessment.pdf 1 MB | 10-Aug-2018 |
509 - WFD Scoping Assessment.pdf 1 MB | 10-Aug-2018 |
Able draft LSE_AA for V4 NE Agreed .pdf 240 KB | 24-Oct-2018 |
MLA/2015/00334/5
Variation 5 - Submitted 02-Sep-2020 Withdrawn
View Variation ==== Response Documents: No published documents Additional Documents: No published documents
MLA/2015/00334/6
Variation 6 - Submitted 04-Sep-2020 Accepted View Variation
Response Documents - Licence L/2017/00012/5
File | Date |
Marine Coordinate Schedules.pdf 9 KB | 14-Sep-2020 |
Decision Letter (Marine).pdf 675 KB | 14-Sep-2020 |
Licence Document (Marine).pdf135 KB|14-Sep-2020| |[[this>Teesworks/Planning/MLA_2015_00334/6/Response Documents/Returns.pdf|Returns.pdf 30 KB | 14-Sep-2020 |
Additional Documents: No published documents
MLA/2015/00334/7
Variation 7 - Submitted 14-Sep-2020 Accepted
Response Documents - Licence L/2017/00012/6
File | Date |
Schedule 6 ASC-001-00009 G Dredge Locations.pdf 869 KB | 28-Oct-2020 |
Marine Coordinate Schedules.pdf 9 KB | 29-Oct-2020 |
Decision Letter (Marine).pdf 675 KB | 29-Oct-2020 |
Licence Document (Marine).pdf 134 KB | 29-Oct-2020 |
Returns.pdf 33 KB | 29-Oct-2020 |
Additional Documents: No published documents
MLA/2015/00334/8
Variation 8 - Submitted 03-Nov-2020 Accepted View Variation
Response Documents - Licence L/2017/00012/7
File | Date |
Licence schedule 5 Channel Dredging Slope Failure Contingency Plan.pdf 36 KB | 23-Jul-2021 |
Schedule 6 - ASC-001-00009 K Dredge Locations drawing.pdf.pdf387 KB|23-Jul-2021| |[[this>Teesworks/Planning/MLA_2015_00334/8/Response Documents/Decision Letter (Marine).pdf|Decision Letter (Marine).pdf 1 MB | 02-Aug-2021 |
Marine Coordinate Schedules.pdf 9 KB | 02-Aug-2021 |
Returns.pdf 33 KB | 02-Aug-2021 |
Licence Document (Marine).pdf 137 KB | 02-Aug-2021 |
Additional Documents
File | Date |
ASP-006-00213 A Q11 Batter Erosion Protection.pdf 176 KB | 08-Dec-2020 |
ASP-006-00213 A Q11 Batter Erosion Protection.pdf212 KB | 04-Jan-2021 |
Variation 8 HRA Considerations.docx493 KB | 04-Jan-2021 |
MMO_Results_Template - MAR00562.xlsm 623 KB | 06-Dec-2021 |
MLA/2015/00334/9
Variation 9 - Submitted 06-May-2022 Accepted
Response Documents - Licence L/2017/00012/8
File | Date |
Marine Coordinate Schedules.pdf9 KB | 09-Sep-2022 |
Decision Letter (Marine).pdf 1 MB | 09-Sep-2022 |
Returns.pdf 36 KB | 09-Sep-2022 |
Additional Documents: No published documents
Licence Document (Marine).pdf 138 KB | 09-Sep-2022 |
MLA/2015/00334/10
Variation 10 - Submitted 28-Sep-2022 Accepted View Variation
Response Documents - Licence L/2017/00012/9
File | Date |
Decision Letter (Marine).pdf 1 MB | 30-Jan-2023 |
Licence Document (Marine).pdf 138 KB | 30-Jan-2023 |
Returns.pdf 40 KB | 30-Jan-2023 |
|[[this>Teesworks/Planning/MLA_2015_00334/10/Response Documents/Marine Coordinate Schedules.pdf|Marine Coordinate Schedules.pdf 9 KB | 30-Jan-2023 |
Additional Documents
File | Date |
MLA 2015 00334_10 - Cefas advice required on dredge_disposal variation in the Tees.pddf 122 KB | 07-Dec-2022 |
MLA/2015/00334/11
Variation 11 - Submitted 14-Mar-2023 Accepted View Variation
Response Documents - Licence L/2017/00012/10
File | Date |
Schedule 7 - Sampling locations.pdf 795 KB | 06-Jun-2023 |
Decision Letter (Marine).pdf 1 MB | 12-Jun-2023 |
Returns.pdf 44 KB | 12-Jun-2023 |
Licence Document (Marine).pdf 140 KB | 12-Jun-2023 |
Marine Coordinate Schedules.pdf 9 KB | 12-Jun-2023 |
Additional Documents
File | Date |
20230518_MLA20150033411_R6.5_MMO_ Discharge_Letter.pdf 302 KB | 18-May-2023 |
MLA20150033411_R6.4 R6.5_MMO_Actions required letter.pdf 321 KB | 18-May-2023 |
MLA/2015/00334/12
Variation 12 - Submitted 07-May-2024 Open View Variation Response Documents: No published documents Additional Documents: No published documents
Consultations
Natural England - 1 - Northumbria Consulted on 23 November 2017. Responded on 11 December 2017.
The consultee was asked for their comments on an older version of this case (MLA/2015/00334/3). They responded:
Please detail your advice here.
see supporting document
The consultee included the following files with their response:
Environment Agency - North East Area Consulted on 23 November 2017. Responded on 13 December 2017.
The consultee was asked for their comments on an older version of this case (MLA/2015/00334/3). They responded:
Dear Sir/Madam,
Please find attached Environment Agency response to application ref: MLA/2015/00334/03.
If you have any questions regarding our comments, please do not hesitate to contact me using the details provided on the attached response.
Regards,
Louise Tait
The consultee included the following files with their response:
EA Response to app ref MLA201500334.pdf
Centre for Environment, Fisheries and Aquaculture Science - SEAL Consulted on 23 November 2017. Responded on 24 November 2017.
The consultee was asked for their comments on an older version of this case (MLA/2015/00334/3). They didn't have any comments.
The consultee included the following files with their response:
Centre for Environment, Fisheries and Aquaculture Science - SEAL Consulted on 29 August 2018. Responded on 26 September 2018.
The consultee was asked for their comments on an older version of this case (MLA/2015/00334/4). They responded:
Please see attached.
The consultee included the following files with their response:
20180925 MLA201500334 Able Seaton Port Marine Licence Advice Minute + JL QC (003)+ CC QC.docx
Environment Agency - North East Area Consulted on 29 August 2018. Responded on 21 September 2018.
The consultee was asked for their comments on an older version of this case (MLA/2015/00334/4). They responded:
Dear Sir/Madam,
Please find attached response from the Environment Agency on application ref: MLA/2015/00334/4.
If you have any questions in respect of the response, please do not hesitate to contact me.
Regards,
Louise Tait
The consultee included the following files with their response:
EA response to application ref MLA2015003344.pdf
Natural England - 1 - Northumbria Consulted on 29 August 2018. Responded on 26 September 2018.
The consultee was asked for their comments on an older version of this case (MLA/2015/00334/4). They responded:
Please find NE's attached response letter.
Many thanks,
Josh
The consultee included the following files with their response:
MLA201500334-4, NE Response to AA for ABLE Dredge Extension, 26.09.18, JP.pdf
NE (1 - Northumbria) Variation 11 HRA. Consulted on 2 May 2023. Responded on 22 May 2023.
The consultee was asked for their comments on 20230425_MLA201500334_Variation 11_HRA_v4.docx. They responded:
Please find attached supporting document.
The consultee included the following files with their response:
431900 MLA_2015_00334 MMO_Consultation_Response Able Port Tees.pdf
CEFAS (SEAL) R6.2 Consulted on 27 March 2020. Responded on 27 April 2020.
The consultee was asked for their comments on these documents:
MAR00562 Interim (003).xls MAR00562.pdf MAR00562.xls MMO_Results_Template - MAR00562.xlsm
They responded:
Please see my advice attached.
The consultee included the following files with their response:
20200427 MLA2015003344 Able Seaton L201700012 Mid-licence Marine Licence Advice Minute+sJB.docx
Returns
Notification of commencement MLA/2015/00334/R1 Open
The licence holder must notify the MMO prior to the commencement of the first instance of any licensed activity. This notice must be received by the MMO no less than five working days before the commencement of that licensed activity.
Subreturns Ref R1.1 Open Deadline No less than 5 working days before works start in 2019
Ref R1.2 Discharged Deadline No less than 5 working days before works start in 2020 Date received 16 Jan 2020 Date discharged 17 Jan 2020 Licence holder comments Able UK intend on commencing works on this exempted activity as described in the plan attached
ASC-002-00002 A Marine License L_2017_00012_4 Sampling Locations.pdf 1 MB
Created By: mr richard cram 16-JAN-2020 17:08:18
Ref R1.3 Discharged Deadline No less than 5 working days before works start in 2020 Date received 02 Sep 2020 Date discharged 16 Sep 2020 Licence holder comments Able UK intend on commencing works consisting of dredging as per licence
Ref R1.4 Discharged Deadline No less than 5 working days before works start in 2020 Date received 11 Nov 2020 Date discharged 17 Nov 2020 Licence holder comments Able UK intend on commencing works consisting of dredging as per licence
Ref R1.5 Discharged Deadline No less than 5 working days before works start in 2021 Date received 08 Sep 2021 Date discharged 09 Sep 2021 Licence holder comments Please can we notify you as we intend on commencing dredging at the locations on the drawing (the green HOLDING BASIN and the orange 65M CHANNEL)to a target depth of 9.0 mCD using the UKD Marlin commencing on 13th September 2021 for approx. 48 hours.
ASC-001-00009 H Dredge Locations 2016.pdf 877 KB
Created By: mr richard cram 08-SEP-2021 17:05:16
Ref R1.6 Discharged Deadline No less than 5 working days before works start in 2022 Date received 08 Dec 2022 Date discharged 14 Dec 2022 Licence holder comments Able intend to commence dredging at the location shown on the accompanying drawing.
ASP-006-00317 B Dredging Position 1 for Voltaire.pdf 578 KB
Created By: mr richard cram 08-DEC-2022 13:09:37
Ref R1.7 Discharged Deadline No less than 5 working days before works start in 2022 Date received 05 Jan 2023 Date discharged 09 Jan 2023 Licence holder comments This is an update on the notification submitted on 8/12/22. Works are now extended to cover the areas shown on the accompanying drawing.
Ref R1.8 Discharged Deadline No less than 5 working days before works start in 2023 Date received 20 Jan 2023 Date discharged 25 Jan 2023 Licence holder comments This is an update to the drawing submitted under R1.7 showing both capital & maintenance dredge works on Q10& Q11.
ASP-006-00324 E Schedule of Dredging Works. Dec.2022-Jan 2023.pdf 225 KB
Created By: mr richard cram 20-JAN-2023 17:55:48
Ref R1.9 Discharged Deadline No less than 5 working days before works start in 2023 Date received 12 Jun 2023 Date discharged 12 Jun 2023
2023-06-11 Notification (5day).pdf 651 KB
Created By: mr richard cram 12-JUN-2023 13:26:33
Ref R1.10 Responded Deadline No less than 5 working days before works start in 2024 Date received 13 May 2024 Licence holder comments Works are due to start in the w/c 20 May 2024.
Works will include capital dredging of Seaton Channel and maintenance dredging of the TERRC Basin.
Works are likely to take between 6-8 weeks
Ref R1.11 Open Deadline No less than 5 working days before works start in 2024
Ref R1.12 Open Deadline No less than 5 working days before works start in 2025
Ref R1.13 Open Deadline No less than 5 working days before works start in 2025
PAH Sampling MLA/2015/00334/R10 Open
Annual sediment sample analysis for polycyclic aromatic hydrocarbons (PAHs) at sample locations SC1, SC2, and SC3 of Licence Schedule 7 (Sampling locations) must be undertaken and the analysis results submitted to the MMO. Year one samples must be taken in December 2023 and Year two samples taken in December 2024. The relevant sediment sampling and analysis must be completed by a laboratory validated by the MMO at least 6 weeks prior to the end of years one and two from the date of issue of the licence variation. This must be submitted to the MMO for review for two years consecutively unless otherwise agreed and/or required by the MMO.
Subreturns Ref R10.1 Responded Deadline 6 weeks prior to the end of years one and two Date received 21 Mar 2024 Licence holder comments PAH results for SC1, SC2 and SC3 included in the attached files. All sites were sample in December 2023 but sample SC3 was damaged in transit and re-sampled in February
Ref R10.2 Open Deadline 6 weeks prior to the end of years one and two
PBDE Sampling MLA/2015/00334/R11 Open
Annual sediment sample analysis for Polybrominated diphenyl ethers (PDBEs) at all 14 of the sample locations in Licence Schedule 7 must be undertaken and the analysis results submitted to the MMO Year one samples must be taken in December 2023 and Year two samples taken in December 2024.
The relevant sediment sampling and analysis must be completed by a laboratory validated by the MMO at least 6 weeks prior to the end of years one and two from the date of issue of the licence variation. This must be submitted to the MMO for review for two years consecutively unless otherwise agreed and/or required by the MMO.
Subreturns Ref R11.1 Responded Deadline 6 weeks prior to the end of years one and two Date received 21 Mar 2024 Licence holder comments The sample results are detailed in the attached files. All sites were sampled in February 2024.
Ref R11.2 Open Deadline 6 weeks prior to the end of years one and two
Agents / contractors / sub-contractors MLA/2015/00334/R2 Open
The licence holder must notify the MMO in writing of any agents, contractors or sub-contractors that will carry on any licensed activity listed in section 4 of this licence on behalf of the licence holder. Such notification must be received by the MMO no less than 24 hours before the commencement of the licensed activity.
The licence holder must ensure that a copy of this licence and any subsequent revisions or amendments has been provided to, read and understood by any agents, contractors or sub-contractors that will carry on any licensed activity listed in section 4 of this licence on behalf of the licence holder.
Subreturns Ref R2.1 Open Deadline no less than 24 hours before the commencement in 2019
Ref R2.2 Discharged Deadline no less than 24 hours before the commencement in 2020 Date received 26 Mar 2020 Date discharged 16 Sep 2020 Licence holder comments Plough dredging of the Grounding Bed planned to commence on 30 March. License issue to Dredging Company.
Ref R2.3 Discharged Deadline no less than 24 hours before the commencement in 2020 Date received 16 Sep 2020 Date discharged 16 Sep 2020 Licence holder comments Capital dredging to commence on 15th September please see email attached
Ref R2.4 Discharged Deadline no less than 24 hours before the commencement in 2020 Date received 11 Nov 2020 Date discharged 17 Nov 2020 Licence holder comments Capital dredging to start on 14/11/2020
Ref R2.5 Discharged Deadline no less than 24 hours before the commencement in 2021 Date received 08 Sep 2021 Date discharged 09 Sep 2021 Licence holder comments Vessel Name: UKD MARLIN Masters Name: James Wright Vessel Type: Trailing Suction Hopper Dredger IMO Number: 9064176 Operator: UK Dredging Start Date: 13th September 2021 Duration: Approx. 48hrs Licence: L/2017/00012/7
Ref R2.6 Open Deadline no less than 24 hours before the commencement in 2022
Ref R2.7 Open Deadline no less than 24 hours before the commencement in 2022
Ref R2.8 Discharged Deadline no less than 24 hours before the commencement in 2023 Date received 07 Jan 2023 Date discharged 09 Jan 2023 Licence holder comments PD Ports, Andrew Ridley, Andrew.Ridley@pdports.co.uk
Ref R2.9 Discharged Deadline no less than 24 hours before the commencement in 2023 Date received 07 Jan 2023 Date discharged 09 Jan 2023 Licence holder comments Rohde Nielsen, Paul Hoggaard, tmo@rohde-nielsen.dk
Ref R2.10 Responded Deadline no less than 24 hours before the commencement in 2024 Date received 23 May 2024 Licence holder comments Boskalis Westminster Ltd - Gerrit Jan van den Bosch gerrit.jan.vd.bosch@boskalis.com PD Ports - Andrew Ridley Andrew.Ridley@pdports.co.uk
Ref R2.11 Open Deadline no less than 24 hours before the commencement in 2024
Ref R2.12 Open Deadline no less than 24 hours before the commencement in 2025
Ref R2.13 Open Deadline no less than 24 hours before the commencement in 2025
Vessels MLA/2015/00334/R3 Open
The licence holder must notify the MMO in writing of any vessel being used to carry on any licensed activity listed in section 4 of this licence on behalf of the licence holder. Such notification must be received by the MMO no less than 24 hours before the commencement of the licensed activity. Notification must include the master's name, vessel type, vessel IMO number and vessel owner or operating company.
The licence holder must ensure that a copy of this licence and any subsequent revisions or amendments has been read and understood by the masters of any vessel being used to carry on any licensed activity listed in section 4 of this licence, and that a copy of this licence is held on board any such vessel.
Subreturns Ref R3.1 Open Deadline no less than 24 hours before the commencement in 2019
Ref R3.2 Discharged Deadline no less than 24 hours before the commencement in 2020 Date received 26 Mar 2020 Date discharged 28 Jul 2020 Licence holder comments Vessel : Tees Guardian Official number 920811 (no IMO due to size) Owner/operator – PD Teesport ltd Vessel type: Tug/workboat Master/s: K.Daniels, R.Bunn, M.Pearson, K.Yale
Ref R3.3 Discharged Deadline no less than 24 hours before the commencement in 2020 Date received 16 Sep 2020 Date discharged 17 Nov 2020 Licence holder comments Backhoe Dredger “Odin” Master: Bram Geluk MMSI number: 209453000 Operating company: Boskalis Westminster Ltd
Split Hopper Barge: “B1001” and “B1002” and “B602” (3 barges in total) Unmanned IMO number: N.A. Operating company: Boskalis Westminster Ltd
Ref R3.4 Discharged Deadline no less than 24 hours before the commencement in 2020 Date received 11 Nov 2020 Date discharged 17 Nov 2020 Licence holder comments • BHD HH 12/Cat390. • Baars Split Hopper Barges B1001 and B1002 • Tug; Sea Bronco or Similar, to be confirmed • Survey vessel: F48 tug Sea Bronco
Ref R3.5 Discharged Deadline no less than 24 hours before the commencement in 2021 Date received 08 Sep 2021 Date discharged 09 Sep 2021 Licence holder comments Vessel Name: UKD MARLIN Masters Name: James Wright Vessel Type: Trailing Suction Hopper Dredger IMO Number: 9064176 Operator: UK Dredging Start Date: 13th September 2021 Duration: Approx. 48hrs Licence: L/2017/00012/7
Ref R3.6 Open Deadline no less than 24 hours before the commencement in 2022
Ref R3.7 Open Deadline no less than 24 hours before the commencement in 2022
Ref R3.8 Discharged Deadline no less than 24 hours before the commencement in 2023 Date received 07 Jan 2023 Date discharged 09 Jan 2023 Licence holder comments 9th Jan: Masters name: Andrew Ridley Vessel Type: Hoertnesse IMO number: 7817189 Operating company: PD Ports
Ref R3.9 Discharged Deadline no less than 24 hours before the commencement in 2023 Date received 07 Jan 2023 Date discharged 09 Jan 2023 Licence holder comments commencing 11th/12th Jan Masters name: Paul Hoggaard Vessel type: Heimdal R IMO number: 9127320 Operating company: Rohde Nielsen
Ref R3.10 Responded Deadline no less than 24 hours before the commencement in 2024 Date received 23 May 2024 Licence holder comments Commencing 24th May 2024. Details of all vessels involved with licensed activities included in attached table
Ref R3.11 Open Deadline no less than 24 hours before the commencement in 2024
Ref R3.12 Open Deadline no less than 24 hours before the commencement in 2025
Ref R3.13 Open Deadline no less than 24 hours before the commencement in 2025
Alternative use of dredged material MLA/2015/00334/R4 Open
The MMO must be supplied with a written statement setting out the continued consideration of alternative options for the use of the dredged material yet to be disposed of no later than 1 February each year.
No disposal of material after 1 March each year may be undertaken until this statement is approved in writing by the MMO.
R4.1 Consideration of alternate use of dredged material for 2018 - 2019
R4.2 Consideration of alternate use of dredged material for 2019 - 2020
R4.3 Consideration of alternate use of dredged material for 2020 - 2021
R4.4 Consideration of alternate use of dredged material for 2021 - 2022
R4.5 Consideration of alternate use of dredged material for 2022 - 2023
R4.6 Consideration of alternate use of dredged material for 2023 - 2024
R4.7 Consideration of alternate use of dredged material for 2024 - 2025
R4.8 Consideration of alternate use of dredged material for 2025 - 2026
Subreturns Ref R4.1 Discharged Deadline 01 Feb 2018 Date received 09 Feb 2018 Date discharged 14 Feb 2018 Licence holder comments We have considered alternative uses for dredged material, but know of no option other than disposal at sea.
Ref R4.2 Discharged Deadline 01 Feb 2019 Date received 17 Jan 2020 Date discharged 20 Jan 2020 Licence holder comments We have considered alternative uses for dredged material, but know of no option other than disposal at sea.
Ref R4.3 Discharged Deadline 01 Feb 2020 Date received 17 Jan 2020 Date discharged 20 Jan 2020 Licence holder comments We have considered alternative uses for dredged material, but know of no option other than disposal at sea.
Ref R4.4 Discharged Deadline 01 Feb 2021 Date received 08 Jan 2021 Date discharged 08 Jan 2021 Licence holder comments We have considered alternative uses for dredged material, but know of no option other than disposal at sea.
Ref R4.5 Discharged Deadline 01 Feb 2022 Date received 17 Feb 2022 Date discharged 22 Feb 2022 Licence holder comments We have considered alternative uses for dredged material, but know of no option other than disposal at sea.
Ref R4.6 Discharged Deadline 01 Feb 2023 Date received 17 Jan 2023 Date discharged 26 Jan 2023 Licence holder comments We have considered alternative uses for dredged material and have identified an alternative use for some of the excavated clay to be used as capping material at our Seaton Meadows landfill.
Ref R4.7 Discharged Deadline 01 Feb 2024 Date received 15 Jan 2024 Date discharged 07 Feb 2024 Licence holder comments We are no longer the owner or operator of Seaton Meadows landfill. We have further considered alternative uses for the dredged material, but know of no option other than disposal at sea.
Ref R4.8 Open Deadline 01 Feb 2025
OSPAR returns MLA/2015/00334/R5 Open
The MMO must be informed of the location and quantities of material disposed of each month under this licence. This information must be submitted to the MMO by 15 February each year for the months August to January inclusive, and by 15 August each year for the months February to July inclusive using the MMO's online system.
R6.1 OSPAR reporting disposal for 1 February 2017 - 31 July 2017
R6. 2 OSPAR reporting disposal for 1 August 2017 - 31 January 2018
R6.3 OSPAR reporting disposal for 1 February 2018 - 31 July 2018
R6. 4 OSPAR reporting disposal for 1 August 2018 - 31 January 2019
R6.5 OSPAR reporting disposal for 1 February 2019 - 31 July 2019
R6. 6 OSPAR reporting disposal for 1 August 2019 - 31 January 2020
R6.7 OSPAR reporting disposal for 1 February 2020 - 31 July 2020
R6. 8 OSPAR reporting disposal for 1 August 2020 - 31 January 2021
R6.9 OSPAR reporting disposal for 1 February 2021 - 31 July 2021
R6. 10 OSPAR reporting disposal for 1 August 2021 - 31 January 2022
R6.11 OSPAR reporting disposal for 1 February 2022 - 31 July 2022
R6. 12 OSPAR reporting disposal for 1 August 2022 - 31 January 2023
R6.13 OSPAR reporting disposal for 1 February 2023 - 31 July 2023
R6. 14 OSPAR reporting disposal for 1 August 2023 - 31 January 2024
R6. 15 OSPAR reporting disposal for 1 February 2024 - 31 July 2024
R6. 16 OSPAR reporting disposal for 1 August 2024 - 31 January 2025
R6. 17 OSPAR reporting disposal for 1 February 2025 - 31 July 2025
R6. 18 OSPAR reporting disposal for 1 August 2025 - 31 January 2026
Subreturns Ref R5.1 Discharged Deadline 15 Aug 2017 Date received 09 Feb 2018 Date discharged 26 Feb 2019 Licence holder comments None
Ref R5.2 Discharged Deadline 15 Feb 2018 Date received 09 Feb 2018 Date discharged 26 Feb 2019 Licence holder comments Submitted
Ref R5.3 Discharged Deadline 15 Aug 2018 Date received 25 Feb 2019 Date discharged 26 Feb 2019 Licence holder comments No dredging has been undertaken within this time period
Ref R5.4 Discharged Deadline 15 Feb 2019 Date received 30 Nov 2021 Date discharged 13 Dec 2021 Licence holder comments No dredging has been undertaken within this time period
Ref R5.5 Discharged Deadline 15 Aug 2019 Date received 30 Nov 2021 Date discharged 13 Dec 2021 Licence holder comments No dredging has been undertaken within this time period
Ref R5.6 Discharged Deadline 15 Feb 2020 Date received 30 Nov 2021 Date discharged 13 Dec 2021 Licence holder comments No dredging has been undertaken within this time period
Ref R5.7 Discharged Deadline 15 Aug 2020 Date received 30 Nov 2021 Date discharged 13 Dec 2021 Licence holder comments No dredging has been undertaken within this time period
Ref R5.8 Discharged Deadline 15 Feb 2021 Date received 30 Nov 2021 Date discharged 13 Dec 2021 Licence holder comments submitted
Ref R5.9 Discharged Deadline 15 Aug 2021 Date received 30 Nov 2021 Date discharged 13 Dec 2021 Licence holder comments No dredging has been undertaken within this time period
Ref R5.10 Open Deadline 15 Feb 2022
Ref R5.11 Open Deadline 15 Aug 2022
Ref R5.12 Open Deadline 15 Feb 2023
Ref R5.13 Open Deadline 15 Aug 2023
Ref R5.14 Open Deadline 15 Feb 2024
Ref R5.15 Open Deadline 15 Aug 2024
Ref R5.16 Open Deadline 15 Feb 2025
Ref R5.17 Open Deadline 15 Aug 2025
Ref R5.18 Open Deadline 15 Feb 2026
Sampling MLA/2015/00334/R6 Open
A relevant sediment sampling plan request must be submitted at least 6 months prior to the end of years 3 and 6 from the date of issue. The relevant sediment sampling and analysis must be completed by a laboratory validated by the MMO at least 6 weeks prior to the end of years 3 and 6 from the date of issue.
The licensed activities must not recommence until written approval is provided by the MMO.
Subreturns Ref R6.1 Discharged Deadline 01 Sep 2019 at least 6 months prior to the end of year 3 Date received 11 Mar 2020 Date discharged 11 Mar 2020 Licence holder comments Refer to SAM/2019/00053
Ref R6.2 Discharged Deadline 25 Jan 2020 at least 6 weeks prior to the end of year 3 Date received 10 Mar 2020 Date discharged 20 May 2020 Licence holder comments Results updated to include the PBDE data.
MAR00562 Interim (003).xls 179 KB
Created By: mr richard cram 20-FEB-2020 14:37:29
MAR00562.pdf 521 KB
Created By: mr richard cram 10-MAR-2020 11:46:50
MAR00562.xls 196 KB
Created By: mr richard cram 10-MAR-2020 11:46:52
MMO_Results_Template - MAR00562.xlsm 623 KB
Created By: mr richard cram 10-MAR-2020 11:46:52
Ref R6.3 Open Deadline 01 Sep 2022 at least 6 months prior to the end of year 6
Ref R6.4 Rejected Deadline 25 Jan 2023 at least 6 weeks prior to the end of year 6 Date received 25 Jan 2023
Ref R6.5 Discharged Deadline at least 6 weeks prior to the end of year 6 Date received 05 Apr 2023 Date discharged 18 May 2023
ASC-002-00004 A Seaton Channel Sampling Locations 2022.pdf 795 KB
Created By: mr richard cram 05-APR-2023 12:52:37
MAR01671 MMO_Results_Template Rev 1.xlsm 603 KB
Created By: mr richard cram 05-APR-2023 12:52:41
MAR01671.pdf 525 KB
Created By: mr richard cram 05-APR-2023 12:52:42
Ocean Ecology PSA confirmation.msg 239 KB
Created By: mr richard cram 05-APR-2023 12:52:44
MAR01671 MMO_Results_Template Rev 1.2.xlsm 597 KB
Original file had positive longitudes entered as positive, so use this corrected file MAR01671 MMO_Results_Template Rev 1.2.xlsm 597 KB
Created By: Adam Tillotson 11-MAY-2023 14:30:38
Ref R6.6 Discharged Deadline TBC Date received 11 May 2023 Date discharged 18 May 2023 Licence holder comments As per letter dated 9th May 2023, in response to the discharge of conditions 5.2.13 & 5.2.14, please find attached updated results template with the correct coordinates.
Ref R6.7 Open Deadline TBC
Local Office Notification MLA/2015/00334/R7 Open
The North Shields Marine Office must be notified of the timetable of works/operations at least 10 days prior to any activities commencing.
Subreturns Ref R7.1 Discharged Deadline at least 10 days prior to any activities commencing in 2019 Date received 07 Dec 2022 Date discharged 14 Dec 2022
Notification of Dredging Works - Dec '22 dredge.msg 1 MB
Created By: mr richard cram 07-DEC-2022 16:23:37
Ref R7.2 Discharged Deadline at least 10 days prior to any activities commencing in 2020 Date received 26 Mar 2020 Date discharged 16 Sep 2020 Licence holder comments E-mail sent to North Shields Marine Office.
Ref R7.3 Discharged Deadline at least 10 days prior to any activities commencing in 2021 Date received 08 Sep 2021 Date discharged 09 Sep 2021
RE Able UK Notification of starting dredging works in September 2021.msg 1 MB
Created By: mr richard cram 08-SEP-2021 17:09:18
Ref R7.4 Discharged Deadline at least 10 days prior to any activities commencing in 2022 Date received 07 Dec 2022 Date discharged 14 Dec 2022
Notification of Dredging Works - Dec '22 dredge.msg 1 MB
Created By: mr richard cram 07-DEC-2022 17:01:16
Ref R7.5 Discharged Deadline at least 10 days prior to any activities commencing in 2023 Date received 06 Jun 2023 Date discharged 07 Jun 2023
ASP Marine Licence L2012000129 Condition 5.2.8 .msg 797 KB
Created By: mr richard cram 06-JUN-2023 12:39:27
Ref R7.6 Discharged Deadline at least 10 days prior to any activities commencing in 2024 Date received 08 May 2024 Date discharged 09 May 2024 Licence holder comments Copy of e-mail notification attached
Ref R7.7 Open Deadline at least 10 days prior to any activities commencing in 2025
Ref R7.8 Open Deadline at least 10 days prior to any activities commencing in 2026
Local Office Notification MLA/2015/00334/R8 Open
The District Marine Office must be notified within 10 days of completion of each of the dredging campaigns.
Subreturns Ref R8.1 Open Deadline within 10 days of completion of each of the dredging campaigns in 2019
Ref R8.2 Discharged Deadline within 10 days of completion of each of the dredging campaigns in 2020 Date received 21 Jul 2020 Date discharged 17 Nov 2020 Licence holder comments notification on 16th July 2020 given by email to daniel.thompson@marinemanagement.org.uk see email attached
Licence number L2017000124.msg 260 KB
Created By: mr richard cram 21-JUL-2020 13:05:53
Ref R8.3 Discharged Deadline within 10 days of completion of each of the dredging campaigns in 2020 Date received 12 Oct 2020 Date discharged 17 Nov 2020 Licence holder comments notification on 12th October 2020 given by email to daniel.thompson@marinemanagement.org.uk, hdcfiles@ukho.gov.uk and SM-MMO-SH - MFA Marine Consents (MMO) <marine.consents@marinemanagement.org.uk
Able UK - Seaton Port L2017000124 - OFFICIAL NOTIFICATION Dredging stage completion .msg 277 KB
Created By: mr richard cram 12-OCT-2020 13:53:03
Ref R8.4 Discharged Deadline within 10 days of completion of each of the dredging campaigns in 2021 Date received 16 Sep 2021 Date discharged 17 Sep 2021 Licence holder comments Good Afternoon
Please can I confirm completion of these dredging works on Monday 13th September
RE Able UK Notification of starting dredging works in September 2021.msg 382 KB
Created By: mr richard cram 16-SEP-2021 16:27:42
Ref R8.5 Discharged Deadline within 10 days of completion of each of the dredging campaigns in 2020 Date received 16 Dec 2020 Date discharged 16 Dec 2020 Licence holder comments notification on 12th October 2020 given by email to daniel.thompson@marinemanagement.org.uk, hdcfiles@ukho.gov.uk and SM-MMO-SH - MFA Marine Consents (MMO) <marine.consents@marinemanagement.org.uk
Able UK - Seaton Port L2017000124 - OFFICIAL NOTIFICATION Dredging stage completion 2020.msg 240 KB
Created By: mr richard cram 16-DEC-2020 08:44:20
Ref R8.6 Open Deadline within 10 days of completion of each of the dredging campaigns in 2022
Ref R8.7 Open Deadline within 10 days of completion of each of the dredging campaigns in 2022
Ref R8.8 Open Deadline within 10 days of completion of each of the dredging campaigns in 2023
Ref R8.9 Discharged Deadline within 10 days of completion of each of the dredging campaigns in 2023 Date received 13 Feb 2023 Date discharged 14 Mar 2023
Ref R8.10 Open Deadline within 10 days of completion of each of the dredging campaigns in 2020
Ref R8.11 Open Deadline within 10 days of completion of each of the dredging campaigns in 2020
UKHO notification MLA/2015/00334/R9 Open
The Source Data Receipt team, UK Hydrographic Office, Taunton, Somerset, TA1 2DN (Email: sdr@ukho.gov.uk; Tel: 01823 337900) must be notified of completion of the licensed activities, no later than 3 weeks after their completion.
A copy of the notification must be sent to the MMO within one week of the notification being sent.
Subreturns Ref R9.1 Open Deadline within one week of the notification being sent in 2019
Ref R9.2 Discharged Deadline within one week of the notification being sent in 2020 Date received 12 Oct 2020 Date discharged 17 Nov 2020 Licence holder comments Email confirmation sent to (Email: sdr@ukho.gov.uk
Able UK - Seaton Port L2017000124 - OFFICIAL NOTIFICATION Dredging stage completion .msg 277 KB
Created By: mr richard cram 12-OCT-2020 13:54:22
Ref R9.3 Discharged Deadline within one week of the notification being sent in 2020 Date received 16 Dec 2020 Date discharged 16 Dec 2020 Licence holder comments Email confirmation sent to (Email: sdr@ukho.gov.uk
Able UK - Seaton Port L2017000124 - OFFICIAL NOTIFICATION Dredging stage completion 2020.msg 240 KB
Created By: mr richard cram 16-DEC-2020 08:46:26
Ref R9.4 Discharged Deadline within one week of the notification being sent in 2021 Date received 16 Sep 2021 Date discharged 17 Sep 2021 Licence holder comments Good Afternoon
Please can I confirm completion of these dredging works on Monday 13th September
Thankyou
Created By: mr richard cram 16-SEP-2021 16:29:04
Ref R9.5 Open Deadline within one week of the notification being sent in 2022
Ref R9.6 Open Deadline within one week of the notification being sent in 2023
Ref R9.7 Open Deadline within one week of the notification being sent in 2024
Ref R9.8 Open Deadline within one week of the notification being sent in 2025